Third Notice BLD | 3/5/2008 | 3/5/2008 | 3/17/2008 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 1/9/2008 | 1/9/2008 | 3/5/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 12/11/2007 | 1/9/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/11/2007 | | DONE |
|
|
|
|
BLD-Final | 11/7/2007 | 11/7/2007 | 11/7/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/7/2007 at 9:48:31 AM. Contact: ###-####. ok for perm occ
|
FIRE-Final Inspection | 10/30/2007 | 10/31/2007 | 10/31/2007 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed, seal at one door to be installed prior to structural final.
|
BLD-Wall cover | 10/18/2007 | 10/18/2007 | 10/18/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/18/2007 at 10:40:45 AM. Contact: ###-####. ok to cover ceiling in second phase
|
BLD-Wall cover | 10/8/2007 | 10/9/2007 | 10/9/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/8/2007 at 2:29:06 PM. Contact: ###-####.ok to cover lid in doorway
|
BLD-Conference | 9/21/2007 | 9/21/2007 | 9/24/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/21/2007 at 10:05:27 AM. Contact: ###-####.duct work across corradors
|
BLD-Wall cover | 9/21/2007 | 9/21/2007 | 9/24/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/21/2007 at 7:13:47 AM. Contact: ###-####. ok to cover walls
|
BLD-Final | 9/6/2007 | 9/6/2007 | 9/6/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/6/2007 at 7:37:23 AM. Contact: ###-####. ok to move into phase one area
|
FIRE-Final Inspection | 9/4/2007 | 9/6/2007 | 9/6/2007 | A | PART |
Forrest France
|
|
|
Fire life safety for the area indicated as phase one is acceptable.
|
BLD-Framing/Rough-in | 8/30/2007 | 8/31/2007 | 8/31/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/30/2007 at 2:59:35 PM. Contact: ###-####. ok to cover ceiling corr wall around phase one ok
|
FIRE-Conference | 8/30/2007 | 8/31/2007 | 8/31/2007 | A | DONE |
Forrest France
|
|
|
On site conference to discuss HVAC changes related to F/S dampers and supply units affecting submitted fire alarm plans, also discussed project phasing and inspection schedule.
|
FIRE-Conference | 8/29/2007 | 8/30/2007 | 8/30/2007 | A | CANC |
Forrest France
|
|
|
Overbooked
|
BLD-Other | 8/23/2007 | 8/24/2007 | 8/24/2007 | A | PART |
Dave Hannah
|
|
|
steve Note: ceiling grid Phone #: ###-#### ok to cover but still needs to finish fire protecting corrador wallls
|
BLD-Other | 8/22/2007 | 8/23/2007 | 8/24/2007 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/22/2007 at 2:58:15 PM. Contact: ###-####. resceduled for tomorrow
|
BLD-Wall cover | 7/6/2007 | 7/6/2007 | 7/6/2007 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/6/2007 at 7:43:54 AM. Contact: ###-####.
|
BLD-Wall cover | 7/3/2007 | 7/3/2007 | 7/3/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/3/2007 at 7:08:53 AM. Contact: ###-####. ok to one side but needs fire protect floor pent.
|
Issue PAID IN FULL permit | | | 6/8/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/7/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/7/2007 | | DONE |
|
|
|
teresa preston out of office for a couple of weeks - left vm for mark hershey at ###-#### - permit ready and fees given - also need gc name and rce#
|
Permit Ready to Issue | | | 5/7/2007 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 4/5/2007 | | 5/4/2007 | | PASS |
|
|
|
5/4/2007 15:50:28 DRS - activity updated through activity BLDA022 from case BLD07-00792.
|
Routing - PLUMBING | 5/3/2007 | | 5/4/2007 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - PLAN CHECK | 5/4/2007 | | 5/4/2007 | | PASS |
|
|
|
Plans to permit desk for issuing permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/2007 | | PASS |
|
|
|
|
Telephone call | | | 5/3/2007 | | DONE |
|
|
|
Call to Bill Vandegrift, plumbing plan review to see if he will be in today. Taking plans to his cubicle.
|
Routing - PLAN CHECK | 4/24/2007 | | 5/3/2007 | | PEND |
|
|
|
No further resubmittals required. Routing back to plumbing for re-review.
|
Plan resubmittals received | | | 5/2/2007 | | DONE |
|
|
|
Received 1 letter of transmittal,1 response,and 2 copys of sheets
G0.2,A2.1,A2.2,A10.1,M1.1,M2.1,P2.1,P1.1,P2.1,P2.2,E0.1,E1.1,E2.1,E2.1 taken to Dan S.
|
Routing - FIRE | 4/23/2007 | | 4/24/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
1st review completed | | | 4/24/2007 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 4/6/2007 | | 4/23/2007 | | FAIL |
|
|
|
Resubmittals required. Copy to architect. Routing to fire code analyst.
|
Plan resubmittals requested | | | 4/23/2007 | | DONE |
|
|
|
E-mailed copy of plan review to Teresa Preston, CSHQA.
|
Plan resubmittals received | | | 4/10/2007 | | DONE |
|
|
|
Received 1 letter of transmittal,and 2 copys of sheets P2.1,P2.2 taken to Dan S.
|
Routing - PLUMBING | 4/5/2007 | | 4/6/2007 | | FAIL |
|
|
|
provide piping plans.
|
Routing - PUBLIC WORKS | 4/5/2007 | | 4/5/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 3/30/2007 | | 4/5/2007 | | DONE |
|
|
|
4/5/2007 12:34:40 MYS - activity updated through activity BLDA168 from case BLD07-00792.
|
Plans ACCEPTED BY PLAN TECH | | | 3/30/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/28/2007 | | DONE |
|
|
|
|
Application received | | | 3/28/2007 | | |
|
|
|
|