Permit NumberBLD07-00845
StatusFinaled
Name PKC CONSTRUCTION
Site Address 105 N 9TH ST
Project NameSONNA BLDG
Customer Number 
ePlanReviewNo
Description
(CHARLES SCHWAB - SONNA BLDG) To perform interior and minor exterior work to expand an existing 1,653 sq.ft. office into an adjacent 2067 square feet retail space to bring the office to 3,760 square feet. To relocate the existing store front entry door to make an accessible entrance. NOTE: This building is fully fire sprinklered for substitution of one-hour fire-resistive construction. All construction shall be per the approved plans and attached comment list. CZC07-00076. MJP
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD11/13/200711/13/200712/7/2007 DONE
First Notice has not been responded to.
First Notice 10/8/200711/13/2007 DONE
BLD-Final10/5/200710/8/200710/8/2007APASS
DetailsDave Hannah
c r marvin Phone #: ###-#### ok for perm occ
Permanent Occupancy UNPAID FEE  10/8/2007 DONE
BLD-Final9/21/20079/24/20079/26/2007PPART
DetailsDave Hannah
C R MARVIN Phone #: ###-#### nOTE: LATE AS POSSIBLE ok to move into phase two walked project with contractor he will call for final after he finishs several items
FIRE-Final Inspection9/21/20079/24/20079/24/2007PPASS
DetailsForrest France
Fire life safety is acceptable, need to provide signage above the main entry/exit door and install indicator on the egress side.
BLD-Other9/18/20079/19/20079/20/2007PPART
DetailsDave Hannah
C R BARVIN nOTE: GRID Phone #: ###-#### ceiling grid phase two ok to cover
BLD-Framing/Rough-in9/11/20079/12/20079/12/2007PPART
DetailsDave Hannah
metal ceiling; C.R. Marvin; Phone #: ###-#### Internet Inspection Request from: Hattie James ok to cover hard ceiling
BLD-Framing/Rough-in9/10/20079/11/20079/12/2007PNR
DetailsDave Hannah
C R MARVIN Phone #: ###-####
BLD-Framing/Rough-in9/7/20079/10/20079/11/2007PPART
DetailsDave Hannah
CR MARVIN Phone #: ###-#### walls ph 2 ok to cover
FIRE-Final Inspection9/4/20079/5/20079/6/2007PPART
DetailsForrest France
Final pending completion of the scope of work at the south office area, manual thumbturn at the NW exit door to be removed.
BLD-Final9/4/20079/5/20079/5/2007PPART
DetailsDave Hannah
CR Marvin; Phone #: ###-#### Internet Inspection Request from: Hattie James ok to move into phase one
BLD-Framing/Rough-in8/23/20078/24/20078/24/2007APART
DetailsDave Hannah
c.r. marvin - ceiling grid Phone #: ###-#### ceiling grid phase one ok to cover
BLD-Final8/22/20078/23/20078/24/2007PNR
DetailsDave Hannah
C.R., early p.m. if possible; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
Meeting  8/23/2007 DONE
Denied "partial occupancy" request. "Walk-in" meeting with "CR" Marvin, Supt for PKC Const requesting approval to occupy a portion of the TI space, while they work on another portion of the space. I denied the request because fire alarms are not completed and plans were being resubmitted by the vendor at the moment of our discussion, the sprinkler permit had just been issued the day before for 33 new sprinkler heads (which he said had been installed overnight), and no life safety inspections had been completed as the scheduled inspection was cancelled for "not ready".
CHANGE STATUS TO (ISS)  7/26/2007 DONE
(F) Reprint permit  7/26/2007 DONE
BLD-Framing/Rough-in6/26/20076/27/20076/27/2007APASS
DetailsDave Hannah
cr marvin Phone #: ###-#### ok to cover walls
BLD-Conference6/11/20076/12/20076/12/2007APART
DetailsDave Hannah
cr marvin-- ###-#### cell-
Issue PAID IN FULL permit  6/11/2007  
Print Occupancy Form  5/22/2007 DONE
Telephone call  5/22/2007 DONE
left vm for mike michaels at ###-#### - permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  5/22/2007  
Routing - PLAN CHECK5/2/2007 5/21/2007 PASS
Plan assigned to (M_P)4/18/2007 5/21/2007 PASS
5/21/2007 15:08:55 M_P - activity updated through activity BLDA022 from case BLD07-00845.
PLANS/APPL TAKEN TO FRONT DESK  5/21/2007 DONE
Plan resubmittals received  5/16/2007  
Received by mail transmittal, 2pg. response letter, 1pg. letter from owner of building with floor plan of 1st and 2nd floor (8 1/2" x 11"), copy of Boise City Plan Review Comments, two copies of pages G1.1 & A1.3; taken to Mike Phillips
Routing - PLAN CHECK4/23/2007 5/2/2007 FAIL
Second reveiw failed, sent correction report to the architect. Requesting additional information to be submitted for further review prior to issuing permit.
Plan resubmittals received  5/1/2007  
Received 1 cover transmittal, 2 copies of response letter from New Dimension of Design (7 pgs), 2 copies of response letter from KLH Engineers (2 pgs), 2 copies of sheets G1.0, A1.0, SP1.0, A1.1, A1.4, A2.0, A4.1, E1.1, M1.1 and taken to Mike Phillips
1st review completed  4/23/2007 FAIL
Failed plan check.
Routing - FIRE4/20/2007 4/23/2007 PASS
Attached review comments to plans.
Routing - PLAN CHECK4/13/2007 4/20/2007 FAIL
Plan review completed, sent correction report to the architect requesting additional information to be submtted for further review prior to issuing permit.
Plan assigned to (CJW)4/12/2007 4/18/2007 DEFR
Reassigned to Mike Phillips by MSouthard on 4/18/2007.
Routing - PUBLIC WORKS4/12/2007 4/13/2007 PASS
Pending Assignment by MYS4/4/2007 4/12/2007 DONE
4/12/2007 12:05:10 MYS - activity updated through activity BLDA172 from case BLD07-00845.
Routing - PLANNING4/4/2007 4/4/2007 PASS
CZC07-00076- Sarah Shafer
Application received  4/4/2007  
Recd Pcfee & Taken To Pln CK  4/4/2007 DONE
Plans ACCEPTED BY PLAN TECH  4/4/2007