BLD-Final | 8/6/2007 | 8/7/2007 | 8/7/2007 | A | PASS |
Tom Arcoraci
|
|
|
brett Phone #: ###-####
|
DOC - Permit Finaled | 8/7/2007 | 8/7/2007 | 8/7/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
Code Occupancy Approval | 8/6/2007 | 8/6/2007 | 8/6/2007 | P | PASS |
Joe R Venneman
|
|
|
Meets DR requirements
|
BLD-Final | 8/1/2007 | 8/3/2007 | 8/3/2007 | A | NR |
Mike Jordan
|
|
|
brett Phone #: ###-####. Needs code enforcement.
|
Plan Reviewer's activity | | | 7/11/2007 | | DONE |
|
|
|
Recieved Common Wall agreement and delivered them to Josh Wilson with Planning and Zoning. I then deleted the Parcel Tag. (SRZ)
|
BLD-Energy code compliance | 6/27/2007 | 6/28/2007 | 6/28/2007 | P | PASS |
Tom Arcoraci
|
|
|
brett - insulation Phone #: ###-####
|
BLD-Framing/Rough-in | 6/27/2007 | 6/27/2007 | 6/27/2007 | P | PASS |
Dave Hannah
|
|
|
brett Phone #: ###-####
|
Override - Parcel Holds | 6/27/2007 | 1/1/1900 | 6/27/2007 | | |
|
|
|
framing
|
BLD-Framing/Rough-in | 6/26/2007 | 6/26/2007 | 6/26/2007 | P | NR |
Jim Storey
|
|
|
brett Phone #: ###-####
|
Override - Parcel Holds | 6/26/2007 | 1/1/1900 | 6/26/2007 | | |
|
|
|
framing
|
BLD-Footing | 5/21/2007 | 5/21/2007 | 5/21/2007 | P | PASS |
Jim Storey
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Delphine Kavanaugh
|
Override - Parcel Holds | | | 5/11/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/11/2007 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 5/10/2007 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/10/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/10/2007 | | DONE |
|
|
|
t/c w doug mccleery at ###-#### - permit ready and fees given
|
Override - Parcel Holds | | | 5/10/2007 | | |
|
|
|
|
Permit Ready to Issue | | | 5/10/2007 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 4/25/2007 | 4/25/2007 | 5/9/2007 | | PASS |
|
|
|
5/9/2007 11:46:57 SRZ - activity updated through activity BLDA022 from case BLD07-00877.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/3/2007 | | 5/8/2007 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 5/8/2007 | | |
|
|
|
|
Case Summary (BLD) | | | 5/8/2007 | | |
|
|
|
|
Telephone call | | | 5/3/2007 | | DONE |
|
|
|
Called applicant and designer and let them know re-submittals are required again. (SRZ)
|
Routing - PLAN CHECK | 5/3/2007 | | 5/3/2007 | | FAIL |
|
|
|
Recieved Truss layout. Does not match plans. Structure incomplete. resubmittals required to finish Plan review.(SRZ)
|
Telephone call | | | 5/3/2007 | | DONE |
|
|
|
I spoke with Designer and requested a roof layout. His structure is incomplete.(SRZ)
|
Plan resubmittals requested | | | 5/3/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 4/25/2007 | | 5/2/2007 | | PASS |
|
|
|
Plan review Pending Roof Layout. (SRZ)
|
Telephone call | | | 4/25/2007 | | DONE |
|
|
|
I spoke with Applicant and let him know about failed plans. left message with designer. (SRZ)
|
Plan resubmittals requested | | | 4/25/2007 | | |
|
|
|
|
Plan resubmittals received | | | 4/25/2007 | | |
|
|
|
received Declaration of Common Party Wall; took to Sam Z.
|
Pending Assignment by SRZ | 4/9/2007 | | 4/25/2007 | | DONE |
|
|
|
4/25/2007 10:28:43 SRZ - activity updated through activity BLDA160 from case BLD07-00877.
|
Routing - PLAN CHECK | 4/11/2007 | | 4/25/2007 | | FAIL |
|
|
|
Plans failed review: No wall bracing called out on plans, Common wall detail for zero lot line wall, Location on lot (structure projection) issues, Need Fire rated eve details, all beams need to be called out on the plans, common wall agrement. (SRZ)
|
Routing - PLANNING | 4/9/2007 | | 4/11/2007 | | PASS |
|
|
|
Routed to Josh Wilson DRH07-59 4/9/07
|
Routing - PUBLIC WORKS | 4/11/2007 | | 4/11/2007 | | PASS |
|
|
|
|
Application received | | | 4/9/2007 | | |
|
|
|
|
Routing - Addressing | 4/9/2007 | | 4/9/2007 | | PASS |
|
|
|
|