BLD-Aging Inspection | 5/19/2010 | 5/19/2010 | 5/19/2010 | | CANC |
Mike Jordan
|
|
|
|
DOC - Permit Expired | 5/19/2010 | 5/19/2010 | 5/19/2010 | A | PASS |
Mike Jordan
|
|
|
Pool house has been completed. No further inspections were called in. Permit is expired.
|
BLD-Aging Inspection | 9/5/2007 | 9/5/2007 | 9/5/2007 | | PASS |
Mike Jordan
|
|
|
wip.
|
Issue PAID IN FULL permit | | | 6/6/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/25/2007 | | DONE |
|
|
|
t/c w kenny at remington carter inc at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/25/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 5/23/2007 | | 5/24/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2007 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/24/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/24/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/24/2007 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 4/10/2007 | | 5/24/2007 | | PASS |
|
|
|
5/24/2007 14:12:25 M_P - activity updated through activity BLDA022 from case BLD07-00896.
|
Routing - PUBLIC WORKS | 5/22/2007 | | 5/23/2007 | | PASS |
|
|
|
Taken from Mike Phillips and given to Louise Waldorf
|
Routing PW Sewer Design | 5/23/2007 | | 5/23/2007 | | PASS |
|
|
|
Sewer tap permit required per Jim P.
|
Routing - FIRE | 5/11/2007 | | 5/16/2007 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Routing - PUBLIC WORKS | 5/16/2007 | | 5/16/2007 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 5/9/2007 | | 5/11/2007 | | |
|
|
|
Routing to fire.
|
Plan resubmittals received | | | 5/10/2007 | | |
|
|
|
received transmittal letter for houston, bugatsch, arch & letter for mike phillips. received "2" sheets of 1 of 1, (2) sheets each of A1, & A2, & "2" sheets each of sheet "1" & "2" sheets each of M1.O--plans taken to Mike Phillips
|
Additional plans submitted | | | 5/9/2007 | | DONE |
|
|
|
Bob Unger dropped off site plan to Fire.
|
Routing - PUBLIC WORKS | 5/8/2007 | | 5/9/2007 | | FAIL |
|
|
|
Received grading plans reflecting utilities, route back to P.W.
|
Routing - PLAN CHECK | 5/7/2007 | | 5/8/2007 | | |
|
|
|
Routing to P.W.
|
1st review completed | | | 5/7/2007 | | FAIL |
|
|
|
|
Routing - FIRE | 5/4/2007 | | 5/7/2007 | | FAIL |
|
|
|
Emailed and Faxed resubmittal items to archtiect.
|
Routing - PLANNING | 5/4/2007 | | 5/4/2007 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 5/4/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 4/25/2007 | | 5/4/2007 | | FAIL |
|
|
|
Plan review complete, sent correction report to the architect requesting additional information to be submitted for further review prior to issuing permit.
|
Routing - PLANNING | 4/24/2007 | | 4/25/2007 | | FAIL |
|
|
|
DRH04-00289 Sarah S; CUP04-00106 Susan R.
|
Routing - PLUMBING | 4/17/2007 | | 4/24/2007 | | PASS |
|
|
|
per plans and 2003 upc
|
Plan resubmittals received | | | 4/18/2007 | | |
|
|
|
received (2) sheets 1 of 1--plans taken to mike phillips
|
Routing - Erosion and Sediment | 4/16/2007 | | 4/17/2007 | | PASS |
|
|
|
ESC waiver request approved with attached conditions.
|
Routing - PUBLIC WORKS | 4/11/2007 | | 4/16/2007 | | FAIL |
|
|
|
Boise Sewer ordinance requires that each lot & block with a building be separatly & independently connected to public sewer. Contact Jim Pardy ###-####
|
Routing - PLANNING Land Div | 4/11/2007 | | 4/11/2007 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/11/2007 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 4/11/2007 | | |
|
|
|
|
Application received | | | 4/10/2007 | | |
|
|
|
|
Pending Assignment by MYS | 4/10/2007 | | 4/10/2007 | | DONE |
|
|
|
4/10/2007 15:54:34 JCM - activity updated through activity BLDA170 from case BLD07-00896.
|
Recd Pcfee & Taken To Pln CK | | | 4/10/2007 | | DONE |
|
|
|
|