Second Notice BLD | 9/13/2007 | 9/13/2007 | 10/1/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 8/24/2007 | 8/24/2007 | 9/13/2007 | | DONE |
Jim Sly
|
|
|
|
BLD-Final | 8/23/2007 | 8/24/2007 | 8/24/2007 | P | PASS |
Jim Sly
|
|
|
jim Phone #: 941-451 Verified affidavit from MTI and final letter from Engineer. C/C issued
|
DOC - Permit Finaled | 8/24/2007 | 8/24/2007 | 8/24/2007 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 8/23/2007 | 8/23/2007 | 8/23/2007 | P | NR |
Jim Sly
|
|
|
JIM Phone #: ###-#### Need 2 HVAC permits finaled.
|
BLD-Final | 8/21/2007 | 8/22/2007 | 8/22/2007 | P | PART |
Tony Young
|
|
|
jim Phone #: ###-#### temp occ ok,, need trades complete finals,, letter of approval for special inspections,, and any letter of approvals from architect
|
FIRE-Final Inspection | 8/21/2007 | 8/22/2007 | 8/22/2007 | A | PASS |
Forrest France
|
|
|
Required corrections have been completed, fire life safety passed inspection.
|
FIRE-Final Inspection | 8/20/2007 | 8/21/2007 | 8/21/2007 | A | FAIL |
Forrest France
|
|
|
Missing required exit signs as indicated on approved plan set for the second floor level, also need to install one EM light and repair one existing EM light as annotated, remainder of life safety is acceptable.
|
BLD-Framing/Rough-in | 8/14/2007 | 8/14/2007 | 8/14/2007 | P | PASS |
Tony Young
|
|
|
Ceiling grid; Jim; Phone #: ###-#### Internet Inspection Request from: Hattie James all ceiling grid ok
|
FIRE-Conference | 8/7/2007 | 8/8/2007 | 8/8/2007 | A | DONE |
Forrest France
|
|
|
On site visit to discuss fire code review notes and project related fire life safety issues including door hardware, exit signs/EM lighting, sprinkler coverage, fire alarm work, etc.
|
BLD-Other | 8/2/2007 | 8/3/2007 | 8/6/2007 | P | NR |
Dave Hannah
|
|
|
jim Note: ceiling grid Late as possible Phone #: ###-####
|
BLD-Framing/Rough-in | 8/1/2007 | 8/1/2007 | 8/1/2007 | P | PASS |
Tony Young
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang stair tower drop ceiling ok
|
BLD-Framing/Rough-in | 7/27/2007 | 7/30/2007 | 7/30/2007 | A | PART |
Tony Young
|
|
|
Jim,, stair tower; Phone #: ###-#### stair tower frame ok,, pending ele, r/in one area
|
BLD-Framing/Rough-in | 7/26/2007 | 7/27/2007 | 7/27/2007 | A | NR |
Tony Young
|
|
|
jim Phone #: ###-#### need u l listings,,
|
BLD-Framing/Rough-in | 7/19/2007 | 7/20/2007 | 7/20/2007 | P | PART |
Tony Young
|
|
|
jim - sheet rock in basement; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang rock under beam ok
|
BLD-Other | 7/18/2007 | 7/18/2007 | 7/18/2007 | P | PART |
Tony Young
|
|
|
jim Phone #: ###-#### masonary window infill ok
|
BLD-Other | 7/17/2007 | 7/17/2007 | 7/17/2007 | P | PART |
Tony Young
|
|
|
jim - covering ceiling and fire taping Phone #: ###-#### all 4 ft areas that had been removed for seismic ties are ok now,, back to 1hr via 5/8 X sheetrock and sealed up,,
|
FIRE-Conference | 7/12/2007 | 7/12/2007 | 7/13/2007 | P | DONE |
Forrest France
|
|
|
On site visit, discussed repair of existing emergency lighting at the stairways, project schedule, related fire sprinkler and alarm permits.
|
BLD-Conference | 7/12/2007 | 7/12/2007 | 7/13/2007 | A | PART |
Tony Young
|
|
|
Jim; Phone #: ###-#### stair beam ok w/ wrapping w/ 5/8" to make 1hr assbly,, also 4' around classrooms ok replacing lath and plaster w/ 5/8" and seal to the you can w/ firecaulk,, sprinkler system is in portions of area above and below drop ceilings
|
BLD-Framing/Rough-in | 7/13/2007 | 7/13/2007 | 7/13/2007 | P | PART |
Tony Young
|
|
|
jim NOte: 2nd floor Phone #: ###-#### ok to cover hallway areas,,
|
BLD-Framing/Rough-in | 7/12/2007 | 7/12/2007 | 7/13/2007 | P | CANC |
Tony Young
|
|
|
Jim; Phone #: ###-####
|
BLD-Conference | 7/11/2007 | 7/11/2007 | 7/12/2007 | P | PASS |
Tony Young
|
|
|
JIM Phone #: ###-#### RFI# wrap of steel beam ok
|
BLD-Framing/Rough-in | 7/6/2007 | 7/9/2007 | 7/9/2007 | P | PART |
Tony Young
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang 3rd floor walls as noted on plans,, pendind elec r/in on some areas
|
BLD-Footing | 6/29/2007 | 7/2/2007 | 7/2/2007 | A | PASS |
Tony Young
|
|
|
Jim; Phone #: ###-#### stair ftg ok,, also all seismic ties in place
|
BLD-Footing | 6/28/2007 | 6/29/2007 | 7/2/2007 | A | PASS |
Tony Young
|
|
|
jim Note: rebar - if possible mid morning - concrete order about 11:00 Phone #: ###-####
|
Telephone call | | | 7/2/2007 | | DONE |
|
|
|
Spoke with Stan Beus of Shiloh Fire Protection. Stan was inquiring whether or not the floor control valves will be required to be installed during the retorfit of the existing fire sprinkler system within the Boise high school.
|
Meeting | | | 7/2/2007 | | DONE |
|
|
|
Met with Dave Hanneman regarding the request by Shiloh sprinkler to eliminate the requirement to add floor control assembly valves to the existing fire protection sprinkler system at Boise High school. The fire marshal has agreed not to require the installation of new floor control valve assemblys in this existing 3 story building.
|
BLD-Framing/Rough-in | 6/27/2007 | 6/28/2007 | 6/28/2007 | A | PART |
Tony Young
|
|
|
jim Phone #: ###-#### remainder of seismic straps
|
BLD-Framing/Rough-in | 6/25/2007 | 6/26/2007 | 6/26/2007 | P | PART |
Tony Young
|
|
|
jim Phone #: ###-#### 1st floor and ceiling seismic strapping,, see inspection sheet for room #s
|
BLD-Other | 6/15/2007 | 6/22/2007 | 6/22/2007 | A | PASS |
Tom Arcoraci
|
|
|
jim - seismic bracing; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang 3rd floor 333 334 336 337 rms ok wip
|
BLD-Other | 6/15/2007 | 6/21/2007 | 6/21/2007 | A | PART |
Jim Sly
|
|
|
jim - seismic bracing; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang Floor infill framing (old stairway) 2nd to 3rd floor......OK
|
BLD-Other | 6/15/2007 | 6/20/2007 | 6/20/2007 | A | CANC |
Jim Storey
|
|
|
jim - seismic bracing; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
BLD-Other | 6/15/2007 | 6/19/2007 | 6/19/2007 | A | CANC |
Tony Young
|
|
|
jim - seismic bracing; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
BLD-Other | 6/15/2007 | 6/18/2007 | 6/18/2007 | A | PART |
Dave Hannah
|
|
|
jim - seismic bracing; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang third floor seismic straping ok to cover
|
Issue PAID IN FULL permit | | | 5/30/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/21/2007 | | |
|
|
|
Received 1 cover transmittal and 1 copy of Project start up for special inspections and per Dan Stuart original added to RDY plans and copy taken to records
|
Plan assigned to (DRS) | 4/19/2007 | | 5/18/2007 | | PASS |
|
|
|
5/18/2007 08:25:12 DRS - activity updated through activity BLDA022 from case BLD07-00917.
|
Routing - PLAN CHECK | 5/18/2007 | | 5/18/2007 | | PASS |
|
|
|
Outside structural review completed and approved. routing to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/18/2007 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 5/18/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/18/2007 | | DONE |
|
|
|
t/c w margie kennedy at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/18/2007 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/16/2007 | | 5/17/2007 | | PASS |
|
|
|
Routing structural plan review response to outside engineering for re-review.//Called Action Courier for pick up--5/16/07 @ 9:07 AM BAS 5/18/07 - Received fax from structural engineering performing plan review approving thier review.
|
Routing - PLAN CHECK | 5/11/2007 | | 5/15/2007 | | PEND |
|
|
|
New plan sheets added to plans. New structural engineering data resubmitted. Routing back to structural engineering review firm.
|
Plan resubmittals received | | | 5/15/2007 | | |
|
|
|
Received 1 cover transmittal, 1 letter from Hummel Architects, 1 copy of project special inspections, 3 copies of Plan Review comments/responses from Lochsa Engineering, 3 copies of sheet S3.04 and taken to Dan Stuart
|
Plan Reviewer's activity | | | 5/15/2007 | | DONE |
|
|
|
Start Up for special Inspection form resubmitted did not have the special inspection firm specified. This firm is to be hired by the owner or the disign professional in responsible charge. The contractor cannot hire them. Sent Margie Kennedy a fax requesting this information. Response to structural review data is being sent to outsource contract structural engineering firm for re-review.
|
1st review completed | | | 5/11/2007 | | FAIL |
|
|
|
|
Routing - FIRE | 5/10/2007 | | 5/11/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
Routing - PLAN CHECK | 4/19/2007 | | 5/10/2007 | | FAIL |
|
|
|
Resubmittals required for completed Special Inspection form and structural engineering plan review. Routing to fire code analyst for review.
|
Plan resubmittals requested | | | 5/10/2007 | | DONE |
|
|
|
Copy of plan review e-mailed to Margie Kennedy.
|
Plan resubmittals requested | | | 5/8/2007 | | DONE |
|
|
|
Copy of structural plan review faxed to Margie Kennedy for response.
|
Routing Off Site - STRUCTURAL | 4/19/2007 | | 5/1/2007 | | FAIL |
|
|
|
Received structural review corrections list and faxed copy of required corrections and cover letter to Margie Kennedy.
|
Routing - Addressing | 4/19/2007 | | 4/19/2007 | | PASS |
|
|
|
|
Telephone call | | | 4/19/2007 | | DONE |
|
|
|
called action couriers for pick up to off site engineering
|
Routing - PUBLIC WORKS | 4/19/2007 | | 4/19/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 4/12/2007 | | 4/19/2007 | | DONE |
|
|
|
4/19/2007 10:12:31 MYS - activity updated through activity BLDA168 from case BLD07-00917.
|
Plans ACCEPTED BY PLAN TECH | | | 4/12/2007 | | |
|
|
|
Need G.C. number, did not see mech compliance
|
Recd Pcfee & Taken To Pln CK | | | 4/12/2007 | | DONE |
|
|
|
|
Application received | | | 4/12/2007 | | |
|
|
|
|
Third Notice BLD | 10/1/2007 | 10/1/2007 | | | |
|
|
|
Second Notice has not been responded to.
|