Third Notice BLD | 12/11/2007 | 12/11/2007 | 1/31/2008 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 11/13/2007 | 11/13/2007 | 12/11/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 10/11/2007 | 11/13/2007 | | DONE |
|
|
|
|
BLD-Final | 10/10/2007 | 10/11/2007 | 10/11/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/10/2007 at 4:44:54 PM. Contact: ###-####. ok for perm occ
|
FIRE-Final Inspection | 10/9/2007 | 10/11/2007 | 10/11/2007 | A | PASS |
Forrest France
|
|
|
All corrections were made per forrest notes
|
Permanent Occupancy UNPAID FEE | | | 10/11/2007 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 10/4/2007 | 10/5/2007 | 10/5/2007 | A | CANC |
Dave Hannah
|
|
|
Keith; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt ext ceiling grid repaired areas ok ok to cover
|
Code Occupancy Approval | 10/4/2007 | 10/4/2007 | 10/4/2007 | A | PASS |
Michael Garner
|
|
|
site inspection complete - bldg/grounds completed according to approved plans - PASS
|
FIRE-Final Inspection | 10/3/2007 | 10/4/2007 | 10/4/2007 | P | FAIL |
Forrest France
|
|
|
Need to add EM lighting per plan including the exit discharge, post max. occupant load signs as discussed, provide one PFE for the basement level, clear the area blocking access to the basement exit door, need to tag the fire extinguishers with current certification.
|
BLD-Framing/Rough-in | 6/25/2007 | 6/26/2007 | 6/26/2007 | P | PASS |
Dave Hannah
|
|
|
keith Phone #: ###-#### ok to cover walls
|
BLD-Framing/Rough-in | 6/20/2007 | 6/21/2007 | 6/21/2007 | P | PART |
Dave Hannah
|
|
|
Keith, partial inspection at this time; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt walk in cooler ok to cover
|
Telephone call | | | 6/5/2007 | | DONE |
|
|
|
t/c w keith phillips at ###-#### - permit ready and fees given - also need gc name and rce#
|
Permit Ready to Issue | | | 6/5/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/5/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/1/2007 | | 6/4/2007 | | PASS |
|
|
|
prepared paperwork and took plans to permit desk to issue (msouthard)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/4/2007 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 4/19/2007 | | 6/4/2007 | | PASS |
|
|
|
6/4/2007 14:51:52 MYS - activity updated through activity BLDA022 from case BLD07-00922.
|
Routing - FIRE | 5/30/2007 | | 6/1/2007 | | PASS |
|
|
|
Plans are approved as noted in red. Attached IFC review comments to plans.
|
Routing - PLANNING | 5/24/2007 | | 5/29/2007 | | PASS |
|
|
|
Sarah Shafer
Approved per DRH07-00181 and the enclosed elevation submitted with 5/29/07 date.
|
Routing - PLAN CHECK | 5/15/2007 | | 5/24/2007 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Plan resubmittals received | | | 5/22/2007 | | |
|
|
|
received (2) letters from ota whitworth arch & waiver request for mike phillips, & (6) pages a-2000 cabinets product specs & (15) pages of z-max lighting control product specs-- & "2" sheets each of A1-1, A2-1, & E1.O----gave plans to Mike Phillips
|
Routing - PLUMBING | 5/8/2007 | | 5/15/2007 | | PASS |
|
|
|
All floor sinks and hub drains to be vented per code requirements
Change hot water sizing from water heater to mop sink to 3/4 inch
Provide adequate sizing to all fixtures.
|
Plan resubmittals received | | | 5/9/2007 | | DONE |
|
|
|
Received via fax. 1 fax cover,1 resopnse taken to Mike P.
|
1st review completed | | | 5/8/2007 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 5/8/2007 | | 5/8/2007 | | |
|
|
|
Routing to plumbing.
|
Routing - FIRE | 5/7/2007 | | 5/8/2007 | | FAIL |
|
|
|
Emailed resubmittal items to architect. No fax number was provided by applicant. Inserted fire review comments into plans.
|
Routing - PLAN CHECK | 5/2/2007 | | 5/7/2007 | | FAIL |
|
|
|
Plan review complete, sent corretion report to the architect. Requesting additional information to be submitted for further review prior to issuing permit.
|
Plan resubmittals received | | | 5/7/2007 | | |
|
|
|
received "3" sheets each of P-1--plans taken to mike phillips
|
Routing - PLUMBING | 4/30/2007 | | 5/2/2007 | | FAIL |
|
|
|
the cold water line to the restroom is undersized. is the existing system large enough to handle this system? where is the water heater located? provide detail. provide fixture schedule, lable fixtures. what are the fixtures on each side of the cooler? how is the drainage system at the bar vented?
|
Plan resubmittals received | | | 4/30/2007 | | |
|
|
|
received 3 copys of sheet A2-1 taken to Mike P.
|
Routing - PLAN CHECK | 4/27/2007 | | 4/30/2007 | | |
|
|
|
Routing resubmittals to Plumbing.
|
Routing - PLANNING | 4/24/2007 | | 4/27/2007 | | FAIL |
|
|
|
Sarah Schafer DRH07-00105 and DRH07-00181
There are no exterior elevations included in the packet and there are changes to the exterior of the building. Called and left a message with Tom Whitworth.
|
Routing - PLUMBING | 4/19/2007 | | 4/24/2007 | | FAIL |
|
|
|
provide plumbing plans stamped by a licensed architect or engineer.
|
Pending Assignment by MYS | 4/18/2007 | | 4/19/2007 | | DONE |
|
|
|
4/19/2007 10:41:04 MYS - activity updated through activity BLDA170 from case BLD07-00922.
|
Routing - PUBLIC WORKS | 4/19/2007 | | 4/19/2007 | | PASS |
|
|
|
|
Routing - Addressing | 4/19/2007 | | 4/19/2007 | | PASS |
|
|
|
|
Telephone call | | | 4/18/2007 | | |
|
|
|
Spoke with Bob Mayer from CDHD he said that he does not need to see the plans, the applicant will turn in to CDHD an application and write a statment to the effect that they are not serving food and if they plan on doing so at a later date they will contact CDHD.
|
Plans ACCEPTED BY PLAN TECH | | | 4/18/2007 | | |
|
|
|
|
Telephone call | | | 4/16/2007 | | DONE |
|
|
|
Called Bob Mayer w/CDHD. Per this is tavern, no food served and if he still needs to look at plans.
|
Application received | | | 4/13/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/13/2007 | | DONE |
|
|
|
|