Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD07-00948
StatusFinaled
Name ESI
Site Address 10751 W OVERLAND RD
Project NameFRED MEYER
Customer Number 
ePlanReviewNo
Description
(FRED MEYER - REMODEL AND ADDITION TO GARDEN CENTER) 7/3/07 - PLAN MODIFICATION FOR ELECTRICAL, LIGHTING COMPLIANCE CERTIFICATE AND ELEC/PLUMBING STAMPED "7/3/07, PLAN MOD. RESUBMITTAL" WERE CHANGED. ALL OTHER PLAN REVIEW CONDITIONS AND PLAN SHEETS REMAIN AS ORIGINALLY APPROVED. This building is fully sprinklered for allowable area increase. Work includes selective demolition to prepare for new interior layout and finishes for existing sales floor display and customer service areas of 169,458 sq. ft. main floor and preparation of Garden Center area for construction of a 3,000 sq. ft. cover with support structure and expansion of the outdoor garden/sales area to become 8,871 sq. ft. To construct a new wall to create a new 1,440 sq. ft. (1,392 interior) merchandise pick-up area; add a new loading platform, stairs and rails in the dock area from existing storage area; add a new overhead door to the garden sales/display area and man door as an exit directly to the exterior along the exterior side of new fenced in garden open sales site from the new MPA. To upgrade interior ceilings, floors and wall finishes; display fixtures, freezers, coolers, display and service counters; upgrade bakery equipment and relocate Type I hood with protected grease duct exhaust system; upgrade electrical, mechanical and plumbing; replace interior and exterior doors as indicated, all per approved plans. DRH07-00150 & CFH07-00015. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD3/5/20083/5/20083/5/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD2/6/20082/6/20083/5/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 1/8/20082/6/2008 DONE
BLD-Final1/8/20081/8/20081/8/2008PPASS
DetailsMike Jordan
All issues resolved. Final ok.
Permanent Occupancy  1/8/2008 DONE
BLD-Final12/19/200712/20/200712/20/2007AFAIL
DetailsMike Jordan
Scheduled by a contractor via Hello! on 12/19/2007 at 10:01:03 AM. Contact: ###-####. Needs to provide 36x36 counters for checkout stands, nedds to be dispursed.
FIRE-Final Inspection12/19/200712/19/200712/19/2007PPASS
DetailsTroy Cobbley
Life safety passed.
FIRE-Final Inspection12/4/200712/5/200712/5/2007AFAIL
DetailsTroy Cobbley
The duct smoke detectors have been installed on the supply side not the return side as required per the IMC. The testing has been stopped.
FIRE-Final Inspection11/19/200711/20/200711/20/2007AFAIL
DetailsTroy Cobbley
Still waiting to final the fire alarm permit then the life safety inspection can be started.
FIRE-Final Inspection11/16/200711/19/200711/19/2007AFAIL
DetailsTroy Cobbley
Need the project related fire alarm permit finaled.
FIRE-Final Inspection11/15/200711/16/200711/16/2007AFAIL
DetailsTroy Cobbley
The project is not ready for a final yet but the ham hood is ok to use.
Code Occupancy Approval11/14/200711/14/200711/14/2007APASS
DetailsScott M.Brown
OK FOR FINAL
FIRE-Final Inspection11/12/200711/13/200711/13/2007AFAIL
DetailsTroy Cobbley
The project is not ready for a final inspection yet. The inspection for today was just for the installation and/or repair of the exit discharge lights. They now work.
FIRE-Final Inspection11/6/200711/7/200711/7/2007AFAIL
DetailsTroy Cobbley
The inspection today was to test the new and existing exit signs and emergency lights. Everything operated ok but exit discharge lights are missing from all of the exits. Exit discharge lights do not need to be added outside of the two exits in the Garden Area due to the interior lighting and two parking lot lights that are powered from the emergency generator that provide adequate lighting.
FIRE-Final Inspection10/31/200711/1/200711/2/2007AFAIL
DetailsTroy Cobbley
This was actually for a conference. I provided a correction notice siting specific code sections for life safety requirements. These code sections were written as follows: (1) Provide a racking permit as per IBC section 2208. Contact Dan Stuart at ###-####. (2) Provide Means of Egress Illumination as per IFC 1006.1 This includes the exit discharge. Emergency power shall be per IFC 1006.3. This is to be in the scope of work and in all paths of exit from the scope of work/remodeled areas. (3) Provide exit signs as per IFC 1011.1. Also see IFC 1011.53 for power source. This is to be in the scope of work and in all paths of exit from the scope of work/remodeled areas. (4) Provide door hardware that complies with IFC 1008.1.8.1 and 1008.1.8.3. (5) Access controlled egress doors, such as in Daycare, must comply with IFC 1008.1.3.4 or receive variance from Dan Stuart ###-####.
BLD-Framing/Rough-in10/17/200710/17/200710/17/2007PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/17/2007 at 9:04:04 AM. Contact: ###-####. ceiling grid ok.
FIRE-Conference10/17/200710/17/200710/17/2007PDONE
DetailsTroy Cobbley
I deferred a fire watch request to dave hanniman and answered general questions about a racking permit.
BLD-Wall cover10/16/200710/16/200710/16/2007APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/16/2007 at 7:27:51 AM. Contact: ###-####. ceiling grid ok, Main restrooms ok.
FIRE-Conference10/6/200710/8/200710/8/2007ADONE
DetailsTroy Cobbley
Conference was for the life safety requirements in the new garden area.
BLD-Conference10/8/200710/8/200710/8/2007PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/8/2007 at 9:50:45 AM. Contact: ###-####. ceiling grid in seafood area ok. pend. fire.
BLD-Other9/28/20079/28/20079/28/2007APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/28/2007 at 7:28:16 AM. Contact: ###-####. soffit at seafood area, ceiling grid, pend. sprinkler.
BLD-Other9/11/20079/11/20079/11/2007APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/11/2007 at 5:45:46 AM. Contact: ###-####. ceiling grid ok, pending fire.
FIRE-Final Inspection9/6/20079/7/20079/7/2007AFAIL
DetailsTroy Cobbley
This was an inspection for the egress corridor near the bakery. I need verification that this corridor has emergency lighting. I also noticed overspaced pendants in the bakery that need addressed prior to a final.
BLD-Other9/4/20079/4/20079/4/2007PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/4/2007 at 9:48:04 AM. Contact: ###-####. Ceiling grid in bakery ok.
BLD-Other8/31/20078/31/20078/31/2007PNR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 8/31/2007 at 7:37:14 AM. Contact: ###-####.
FIRE-Final Inspection8/27/20078/27/20078/27/2007PPART
DetailsTroy Cobbley
The remodeled pharmacy area is ok to occupy.
BLD-Final8/27/20078/27/20078/27/2007PCANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/27/2007 at 8:54:03 AM. Contact: ###-####.
BLD-Other8/27/20078/27/20078/27/2007PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/27/2007 at 8:54:03 AM. Contact: ###-####. Pharmacy ok.
BLD-Final8/24/20078/24/20078/24/2007ACANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/24/2007 at 6:51:21 AM. Contact: ###-####.
BLD-Other8/24/20078/24/20078/24/2007APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/24/2007 at 6:51:21 AM. Contact: ###-####. Ceiling grid insp. Received RFI # 16 from arcchitect changing grid requirements to 0-2 application.
(F) Reprint permit  8/24/2007  
BLD-Other8/20/20078/20/20078/20/2007PFAIL
DetailsMike Jordan
Ceiling grid not installed as per plan. c/n issued.
FIRE-Final Inspection8/17/20078/17/20078/17/2007PPART
DetailsTroy Cobbley
This inspection was for the electronics area only. This area is ok to occupy.
FIRE-Conference8/15/20078/15/20078/15/2007PDONE
DetailsTroy Cobbley
This inspection was for the electronics area only. I found six missing sprinkler heads. See the city approved fire sprinkler plans for locations.
BLD-Final8/15/20078/15/20078/15/2007PNR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/15/2007 at 8:00:02 AM. Contact: ###-####. Not a blg. final. Looking to move in to new electronics area. Needs fire to final. Grid system installed not as per plan. Need RFI from architect prior to signing off grid system.
BLD-Conference8/15/20078/15/20078/15/2007PCANC
DetailsMike Jordan
Nate; Phone #: ###-#### Internet Inspection Request from: Hattie James Inspection cancelled from web by: Hattie James
BLD-Other8/13/20078/14/20078/14/2007APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/13/2007 at 6:04:03 PM. Contact: ###-####. Received and reviewed paperwork for polycoolite that arrived on site. Paperwork from SGS testing labs indicates that this shipment carries a CC1 rating as required. Will have paperwork scanned in with permit. Allso noted that railing and stairs at docks has been added back in. Plans must be submitted to architect for approval then resubmitted to plan review for approval.
BLD-Energy code compliance8/13/20078/13/20078/13/2007APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/13/2007 at 6:46:25 AM. Contact: ###-####. insul at new pickup demissing wall.
BLD-Framing/Rough-in8/8/20078/8/20078/8/2007PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/8/2007 at 9:16:20 AM. Contact: ###-####. New demissing wall for merchandising/pickup room.
FIRE-Alarm Testing8/2/20078/3/20078/3/2007ADONE
DetailsTroy Cobbley
This inspection actually turned into a conference. I spoke to the superintendant and told him that for the two hood suppression systems all I need is the certification from the hood suppression contractor that states they are ok with the new appliances and setup. I also was shown what was going on in the rest or the store as far as sprinkler work. This work is in progress and has a early start go ahead.
BLD-Other8/2/20078/2/20078/2/2007PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/2/2007 at 10:33:11 AM. Contact: ###-####. Framing for new soffitt at deli area.
BLD-Footing7/31/20077/31/20077/31/2007PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/31/2007 at 8:56:25 AM. Contact: ###-####. wip for footing for new wall at exisiting garden center. Noted special insp. on site.
BLD-Footing7/27/20077/30/20077/30/2007APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 7/27/2007 at 12:27:28 PM. Contact: ###-####. pendig spec insp
BLD-Framing/Rough-in7/19/20077/19/20077/19/2007APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/19/2007 at 6:29:35 AM. Contact: ###-####. Inspected new soffit framing, and exisiting modified soffitts. Will need RFI from architect for framing changes on diamond soffitt in elec\tronics and for change in grid system. Also reviewed plan review report with contractor.
Plan resubmittals received  7/18/2007  
Per Dan Stuart ok to accept deferred resubmittals; received transmittal, two copies of counter details and full size plan page A5.1-2; taken to Dan S.
Telephone call  7/18/2007 DONE
Telcon from Randy at Shiloh reqesting approval to start sprinkler work without plans, which he estimates will require approx 2-3 weeks to prepare. He indicated scope of their was was primarily raising sprinklers approx 3' to accomodate new ceiling level at 15' height, but scope of building permit is considerably larger. He indicated he has existing sprinkler plans, which he agreed would facilitate preparing their plans more readily. I indicated we need to abide by our Early Start Policy and could not approve starting work until plans have been prepared and submitted; at that time they could request an Early Start approval if they wanted to do work during the plan review period.
CHANGE STATUS TO (ISS)  7/13/2007 DONE
Plan Modification picked up
Telephone call  7/13/2007 DONE
Call from Julie, ESI, from CDH office, Plan modification submittals to me on 7/3/07, per Bud Fullerton, CDH plan reviewer, were shown on his plas and approved 4/17/07. I talked with Bub on the phone to verify. He will sign the MEP1.0, MEP1.1 & MEP2.1 sheets presented to me as modification and Julie will have plans brought in for review.
Meeting  7/13/2007 DONE
Met with Walt Cook who delivered plans from ESI with CDH approval. Inserted one copy into the plan modification site plans and one into city record plans. Required fee's paid to Barb at permit desk and permit was issued for plan modification with hold removed.
Print Occupancy Form  7/11/2007 DONE
Telephone call  7/11/2007 DONE
t/c w brittney at ESI ###-#### - permit ready and fees given - also needs to check out CDHD - tried to call casey mckenna 3 times but the call would not go through (###-####)
Override - Parcel Holds  7/11/2007  
Permit Ready to Issue  7/11/2007 DONE
Telephone call  7/11/2007 DONE
Bud Fullerton, CDH, says when Julie of ESI called him she had told him they were changing out some aisle refrigeration units and interior finishes, so he couldn't figure out why he would need to see and approve additional plans since he had allready approved original Fred Meyer remodel plans for the food prep / dining remodel. I explained to Bud that Plan Modification Plans "MEP1, 1.1 & 3.1" indicated the change out of existing sinks and installation of new sinks in deli prep areas of meet /salad departments. Bud said he would like to review and approve plans again. I told him I would call back Julia at ESI and let her know he does need to review and approve.
Telephone call  7/11/2007 DONE
7/11/07 - Called Julie at ESI and told her the CDH, Bud Fullerton does need to review the plumbing plan changes "MEP" sheets for new sinks. She will take two sets of plans down to Bud for review.
Plan assigned to (DRS)7/3/20077/3/20077/10/2007 PASS
7/10/2007 18:16:13 DRS - activity updated through activity BLDA022 from case BLD07-00948.
Routing - PLAN CHECK7/3/2007 7/10/2007 PEND
Inserted new electrical & plumbing plans into office set. New Lighting compliance certificate provided. Plans routed to Public Works to review for fee's based on new sinks being added.
Routing - PUBLIC WORKS7/10/2007 7/10/2007 PASS
To Louise - Plan Modification Sheets showing new sink fixtures in Bakery & Kitchen Areas. Fee's assessed with schedule attached to plans.
Routing - PLUMBING7/10/2007 7/10/2007 PASS
Reviewed plans at my desk with Bill Vandegrift. New sinks added. Okay - does not need to re-review. Compliance will be field verified. drs
Routing - PLAN CHECK7/10/2007 7/10/2007 PASS
Plan modification routed to Public Works for reappraisal of fee's for new plumbing and to plumbing for re-evaluation. Plan Mod completed.
Override - Parcel Holds  7/10/2007  
Print Pending Permit.LaserJet4  7/10/2007  
Additional plans submitted  7/10/2007 PASS
7/2/07 - Plans from Leggett & Platt, Tarrant Interiors for layout and details for accessible dressing rooms, for deferred submittal item #2 of 6/19/07 plan review.
Additional plans submitted  7/10/2007 DONE
7-5-07 - E-mail Sheet provided deleting specific items from scope of work, including new landing and stairs at rear loading dock area, deleting Item #4 from requirement of deferred submittal as it is no longer part of project scope.
PLANS/APPL TAKEN TO FRONT DESK  7/10/2007 PASS
Plan mod & deferred submittal items #2 & #4 to permit desk to issue. New CV, Sewer Use Fee's and plan review time.
Plan Modification Accepted  7/3/2007  
Plan modification accepted for BLD07-00948 for the redeisgn of new lighting over the food sales area on sheets E-1.6-2; MEP-1.0; MEP-1.1; MEP-1.2; E-1.2A; E-1.2-2A; E-1.2-5A; E-1.2-6A; E-3.1-2A; E-1.1A; EC-1.1-2A and routed to Dan Stuart
CHANGE STATUS TO (REV)  7/3/2007 DONE
Plan modification
Plan resubmittals received  7/2/2007  
Ok to take in as deferred submittal per Dan Stuart: Received transmittal and two copies of the following pages: A (cover), B, C, 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, drawing of fitting room louver door, free standing wall assembly, progressive installation instructions; taken to Dan Stuart
BLD-Conference6/28/20076/29/20076/29/2007ADONE
DetailsMike Jordan
craig Phone #: ###-####
Issue PAID IN FULL permit  6/22/2007 DONE
Plan assigned to (DRS)5/2/2007 6/21/2007 PASS
6/21/2007 10:37:35 DRS - activity updated through activity BLDA022 from case BLD07-00948.
Routing - PLAN CHECK6/15/2007 6/21/2007 PASS
Approved with notes and all attached plan review conditions. To permit desk.
PLANS/APPL TAKEN TO FRONT DESK  6/21/2007 PASS
Print Occupancy Form  6/21/2007  
Telephone call  6/21/2007 DONE
left vm for casey mckenna ###-#### - permit ready and fees given - also need gc name, rce#, rp name and ACHD receipt
Permit Ready to Issue  6/21/2007  
Plan Reviewer's activity  6/20/2007 DONE
Verified test data is current with Greg Banansky, SGS U.S. Testing @ ###-####. He is the Supervisor Fire Technology. Attached copies of data to plans and modified permit & plan review. Routed to permit desk.
Telephone call  6/20/2007 DONE
Greg Banasky, SGS U.S. Testing Co., Supervisor fire Technology. Lab Accredited TL-220 Look up test report and date and said test is still listed. Said test was originally done for Polygall Plastics to seek ICC Evaluation servies report. No indicated to date. ###-####, California site.
Plan resubmittals received  6/19/2007 DONE
Recieved test data on Polycoolite 8mm Structural Polycarbonate.
Plan resubmittals received  6/15/2007  
Received transmittal, two copies of plan review response from architect, Summary of major changes in the 2001 North American specification for the desig n of cold-formed steel sturctural members, Verolite technical specifications, Project Start up for Special Inspections application, pages G1.1, G1.2, S1.2, S1.5, S1.6, E1.2-1, E1.2-2, E1.2-3, E1.2-4, E1.2-5, E1.2-6, E1.2-7, E1.2-8, S1, S2, S3, S4, A1.5, A1.5-2, A6.1; taken to Dan Stuart
Routing - PLAN CHECK5/31/2007 6/7/2007 FAIL
Plan resubmittals of 6/5/07 inserted into original plans. Plans reviewed for compliance. Plan resubmittals were incomplete or not correct. Plan review modified and new copy of remaining items needing corrected were e-mailed to Casey McKenna at Mullvany G2 Architects.
Plan resubmittals requested  6/7/2007 DONE
Plan resubmittals for 2nd review required. copy of modified plan review e-mailed to Casey McKeena, Mullvany G2.
Plan resubmittals received  6/5/2007  
Received transmittal, 5pg. response letter, application for Project Start Up for Special Inspections, 8 1/2" x 11" drawing and calcs, letter from Joanna Pang, two copies of the following pages: G1.2, A1.5, A1.5-2, A4.1, A6..1-1, E1.2-1, E1.2-2, E1.2-3, E1.2-4, E1.2-5, E1.2-6, E1.2-7, E1.2-8, H4.1, S1, S2, S3, S4; one copy of pages E0.1, E1.0, E2.0; taken to Dan Stuart
Telephone call  6/4/2007 DONE
Talked to Mark Sequala from Mulvaney G2 about a temp trailer for the pharmacy to operate in parking lot until remodel within building is complete. Told him a zoning certificate is required, no bldg permit, and elect permit is required for temp power.
1st review completed  5/31/2007 FAIL
Routing - FIRE5/24/2007 5/31/2007 PASS
Attached review comments to plans.
Routing - PLAN CHECK5/18/2007 5/24/2007 FAIL
Faxed copy of plan review to architect. Routing plans to fire code analyst.
Plan resubmittals requested  5/24/2007 DONE
Faxed copy of plan review to Casey McKenna
Routing - Erosion and Sediment5/23/2007 5/23/2007 PASS
ESC waiver request approved with attached conditions.
Routing - PLANNING5/16/2007 5/18/2007 PASS
Josh Johnson CFH07-00015--PASS
Josh Wilson DRH07-00015-- PASS
Routing Off Site - STRUCTURAL5/16/2007 5/17/2007 PASS
Routing structural plan review response to outside engineering for re-review.//Called Action Courier for pick up--5/16/07 @ 9:07 AM BAS 5/17/07 - Fax from David Haugland approving structural plans review.
Plan Reviewer's activity  5/16/2007 DONE
Copy of structural plan review resubmittals taken to permit desk to have delivered to structural engineer.
Routing - PLUMBING5/8/2007 5/16/2007 PASS
all kitchen fixtures are to be indirectly wasted, a PVB will be required upstream of all hose reels.
Routing Off Site - STRUCTURAL5/3/2007 5/15/2007 FAIL
Resubmittals required. Copy of structural plan review sent to Casey McKeena with cover letter.
Plan resubmittals received  5/15/2007  
Received one copy of structural calculations by fax; took to Dan Stuart
Plan resubmittals requested  5/15/2007 DONE
Received fax copy of report from outside structural engineering review. Faxed copy to Casey McKeena, Mulvanny | G2 Architects.
Plan resubmittals received  5/15/2007 DONE
Received faxed copy of Structural calculations for greenhouse structure stamped by Idaho Licensed Engineer.
Routing - Erosion and Sediment5/4/2007 5/8/2007 FAIL
No ESC waiver request included with submittal, contacted applicant (Al Kendall ###-####).
Routing - PUBLIC WORKS5/3/2007 5/4/2007 PASS
Routing PW Environmental5/4/2007 5/4/2007 PASS
Existing GIs in place for deli and meat dept
Routing PW Flood Plain5/4/2007 5/4/2007 PASS
Pending Assignment by MYS4/17/2007 5/2/2007 DONE
5/2/2007 16:40:41 MYS - activity updated through activity BLDA168 from case BLD07-00948.
Plans ACCEPTED BY PLAN TECH  4/18/2007  
Application received  4/17/2007  
Recd Pcfee & Taken To Pln CK  4/17/2007 DONE