Second Notice BLD | 11/7/2008 | 11/7/2008 | 12/3/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 10/21/2008 | 11/7/2008 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/21/2008 | 10/21/2008 | 10/21/2008 | P | NR |
Forrest France
|
|
|
Pending request for fire alarm permit doc final.
|
Telephone call | | | 10/21/2008 | | |
|
|
|
talked to Dave Hannah & verified that all other permits are finaled- customer had no card available-per rita deyoung ok to issue
|
Permanent Occupancy | | | 10/21/2008 | | |
|
|
|
ok per Dave Hannah to issue permit-- customer had no occupancy card. all trades were signed off
|
Telephone call | | | 10/21/2008 | | DONE |
|
|
|
talked to nan hills with the achd that everything is good to go
|
BLD-Final | 10/17/2008 | 10/20/2008 | 10/20/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/17/2008 at 2:16:00 PM. Contact: ###-####. ok for perm occ
|
BLD-Final | 10/16/2008 | 10/17/2008 | 10/20/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled via mobile device. Phone #: 8711566
|
FIRE-Final Inspection | 10/16/2008 | 10/17/2008 | 10/17/2008 | A | PART |
Forrest France
|
|
|
Fire life safety completed acceptable, however project cannot be finaled until related fire alarm permit # FIR07-00807 is finaled.
|
BLD-Conference | 10/10/2008 | 10/10/2008 | 10/13/2008 | P | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### needs city approved plans and fire life saftey final
|
Telephone call | | | 8/8/2008 | | DONE |
Jason Blais
|
|
|
Jim Gambrel of the Rescue Mission stated construction of Phase II under this permit has started.
|
Plan Reviewer's activity | | | 5/13/2008 | | DONE |
Jason Blais
|
|
|
Permit-Occupancy extension approved until August 11th 2008 by Building Division Manager. Document attached to case.
|
BLD-Final | 11/16/2007 | 11/16/2007 | 11/16/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/13/2007 at 10:14:58 AM. Contact: ###-####. ok for temp occ one ph one need to complete ph two
|
FIRE-Final Inspection | 11/13/2007 | 11/16/2007 | 11/16/2007 | A | PART |
Forrest France
|
|
|
Corrections noted for phase one of the project per K. Roule have been completed, fire life safety is acceptable for the portion of permit work as indicated.
|
BLD-Final | 11/13/2007 | 11/15/2007 | 11/16/2007 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/13/2007 at 10:14:58 AM. Contact: ###-####.
|
FIRE-Final Inspection | 11/13/2007 | 11/14/2007 | 11/14/2007 | A | NR |
Forrest France
|
|
|
Need project related fire sprinkler and hood suppression system permits finaled prior to request for a life safety inspection.
|
BLD-Framing/Rough-in | 11/9/2007 | 11/13/2007 | 11/13/2007 | A | PART |
Dave Hannah
|
|
|
john - ceiling Phone #: ###-#### ok to cover ceiling
|
BLD-Wall cover | 10/31/2007 | 11/1/2007 | 11/1/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/31/2007 at 1:53:55 PM. Contact: ###-####. ceiling grid ok to cover dinning room area
|
Plan Reviewer's activity | | | 10/31/2007 | | DONE |
|
|
|
Alternate Approval accepted by Building Official and Fire Marshal to install fire sprinklers above the rated suspended ceiling in lieu of the 5/8" gyp. board on the roof deck. Alternate Approval document is attached to this case under "Documents".
|
Code Occupancy Approval | 10/25/2007 | 10/25/2007 | 10/25/2007 | P | CANC |
Michael Garner
|
|
|
site inspection complete - addition and landscaping completed according to approved plans and DRH conditions - PASS
|
Telephone call | | | 10/24/2007 | | DONE |
|
|
|
Called architect, Eileen Davidson, to discuss the inspection issues concerning the 1-hr rated roof-ceiling assembly not being constructed per the approved plans. She has discussed the issue and it sounds as if the contractor was not working off the City approved plans. (The location of the plans is unknown.) She will be looking at options or solutions to address the problem.
|
Telephone call | | | 10/24/2007 | | DONE |
|
|
|
Called Tammie Newman, Project Director with McAlvain Construction, concerning the inspection issues with the one-hour rated roof-ceiling assembly not being constructed per the City approved plans. She said they had changed superintendents several times on the project and did not have the City approved job site plans. It appears they have been working on an older preliminary set of plans. She needs to obtain an updated set of plans to compare to construction and discuss some options or solutions to the situation.
|
BLD-Footing | 6/21/2007 | 6/22/2007 | 6/25/2007 | P | PASS |
Dave Hannah
|
|
|
jose; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
Plan resubmittals received | | | 6/20/2007 | | DONE |
|
|
|
Resubmitted Site Plan provided showing addition setback to the east property line now at 3'-3". This changed was approved by Hal Simmons, the Planning Director. Plan sheet forwarded to John Menard for the Office Copy/Records plans.
|
Plan resubmittals received | | | 6/19/2007 | | |
|
|
|
Received 1 cover transmittal, 3 copies of sheet A-1.0 and taken to Jason B the Project Manager for this project///6/19/07 @ 1:46pm BAS
|
BLD-Conference | 6/12/2007 | 6/12/2007 | 6/13/2007 | P | PASS |
Dave Hannah
|
|
|
jose ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
Meeting | | | 6/13/2007 | | DONE |
|
|
|
Met with Hal Simmons and Cody Riddle concerning the new addition setback now at 3'-3" versus the approved 5'-3" to the east property line. It was determined by Hal that this change will still meet the requirements of the R-ODD Zoning for interior side setback. The proposed addition construction of a CMU wall with a 30" parapet and no openings complies with Building Code with this change of a reduced setback to property line.
|
(F) Reprint permit | | | 6/12/2007 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/11/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/25/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/25/2007 | | DONE |
|
|
|
t/c w randy jordan at mcalvain const. ###-#### - permit ready and fees given - also need ACHD receipt
|
Permit Ready to Issue | | | 5/25/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 5/8/2007 | | 5/24/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2007 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 4/19/2007 | | 5/24/2007 | | PASS |
|
|
|
5/24/2007 13:38:55 JCM - activity updated through activity BLDA022 from case BLD07-00954.
|
Plan resubmittals received | | | 5/23/2007 | | |
|
|
|
received plan review report for the project of boise rescue mission(5 pages). also everett street from architecture interior design (2) pages. comcheck for 2003 envelope compliance cert (11) pages. "3" sets of plans with each sheet of A-3.1, A-3.2, A-5.O, & M2.O--plans taken to John Menard
|
1st review completed | | | 5/8/2007 | | FAIL |
|
|
|
|
Routing - FIRE | 5/7/2007 | | 5/8/2007 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - PUBLIC WORKS | 5/4/2007 | | 5/7/2007 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 5/4/2007 | | DONE |
|
|
|
E-mailed the architect a copy of the plan review list requesting revisions. JCM
|
Routing PW Environmental | 5/4/2007 | | 5/4/2007 | | PASS |
|
|
|
Resubmittal plumbing sheets show all kitchen drainage to GI
|
Routing - PLAN CHECK | 5/3/2007 | | 5/4/2007 | | FAIL |
|
|
|
John Menard
|
Routing - PLANNING | 4/25/2007 | | 5/3/2007 | | PASS |
|
|
|
DRH07-00122 Josh Wilson; CUP07-00039 Cody Riddle-5/2/07
Construction and operation of facility must comply with the terms and conditions of the Conditional Use Permit.
|
Routing Off Site - STRUCTURAL | 4/19/2007 | | 4/30/2007 | | PASS |
|
|
|
Received letter from consulting structural engineer approving plans and calculations.
|
Routing - PLUMBING | 4/20/2007 | | 4/25/2007 | | PASS |
|
|
|
per plans and 2003 upc
|
Plan resubmittals received | | | 4/25/2007 | | |
|
|
|
Received 1 cover transmittal and 4 copies of sheet P2.0 and taken to
|
Telephone call | | | 4/24/2007 | | DONE |
|
|
|
Talked with Katie Reierson of McAlvain Construction and copies of resubmittal sheet P2.0 will be dropped off tomorrow.
|
Routing - PUBLIC WORKS | 4/20/2007 | | 4/20/2007 | | FAIL |
|
|
|
See rejection notes on 4-19-07 per Walt Baumgartner
|
Routing - Erosion and Sediment | 4/19/2007 | | 4/20/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 4/19/2007 | | 4/19/2007 | | FAIL |
|
|
|
Scullery area not routed to grease interceptor-correction required-resubmit P2.0 sheet.
Contact Walt Baumgartner @ ###-#### Environmental
|
Routing - PLANNING Land Div | 4/19/2007 | | 4/19/2007 | | PASS |
|
|
|
|
Telephone call | | | 4/19/2007 | | |
|
|
|
called Action Couriers for pick up to off-site engineering
|
Plans ACCEPTED BY PLAN TECH | | | 4/19/2007 | | |
|
|
|
|
Routing - Addressing | 4/19/2007 | | 4/19/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 4/17/2007 | | 4/19/2007 | | DONE |
|
|
|
4/19/2007 08:38:07 JCM - activity updated through activity BLDA166 from case BLD07-00954.
|
Recd Pcfee & Taken To Pln CK | | | 4/18/2007 | | DONE |
|
|
|
|
Application received | | | 4/17/2007 | | |
|
|
|
waiting for customer to come back to pay for plan check fee before process application and route plans
|