BLD-Final | 10/16/2009 | 10/21/2009 | 10/22/2009 | P | PASS |
Tony Young
|
|
|
PJ Smith ###-####
|
DOC - Permit Finaled | 10/22/2009 | 10/22/2009 | 10/22/2009 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Grading Inspection | 10/21/2009 | 10/21/2009 | 10/21/2009 | A | DONE |
Terry Records
|
|
|
Final grading and drainage approved.
|
Reopen Permit (ISS) | | | 10/16/2009 | | DONE |
Tisha Gallop
|
|
|
reopen permit, paid 2 hr. admin fee.
|
(F) Reprint permit | | | 10/16/2009 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/24/2009 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Energy code compliance | 10/8/2007 | 10/8/2007 | 10/8/2007 | P | PASS |
Tony Young
|
|
|
rob Phone #: ###-####
|
BLD-Framing/Rough-in | 10/1/2007 | 10/1/2007 | 10/1/2007 | P | PASS |
Jim Sly
|
|
|
rob Phone #: ###-####
|
Plan Reviewer's activity | | | 9/27/2007 | | DONE |
|
|
|
Applicant came in we changed a room designation from dinning room to den. Redlined the change and initialled next to it.
|
BLD-Framing/Rough-in | 8/29/2007 | 8/30/2007 | 8/30/2007 | A | PART |
Tony Young
|
|
|
sheer nail; Rob; Phone #: ###-#### Internet Inspection Request from: Hattie James exterior shear ok
|
BLD-Framing/Rough-in | 8/29/2007 | 8/29/2007 | 8/29/2007 | P | NR |
Jim Sly
|
|
|
sheer nail; Rob; Phone #: ###-#### Internet Inspection Request from: Hattie James Straps not nailed......missing lots of staples.
|
BLD-Footing | 8/1/2007 | 8/1/2007 | 8/1/2007 | P | PASS |
Tony Young
|
|
|
pat Phone #: ###-#### pump truck was plugged,, stayed w/ job to monitor concrete,, 1st truck started dumping 2 hrs after batched out
|
PubWorks Subgrade Approval | 8/1/2007 | 8/1/2007 | 8/1/2007 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer.
|
BLD-Footing | 7/31/2007 | 7/31/2007 | 7/31/2007 | P | NR |
Jim Sly
|
|
|
pat; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
Issue PAID IN FULL permit | | | 7/10/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/9/2007 | | DONE |
|
|
|
t/c w pj smith at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/9/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/8/2007 | | DONE |
|
|
|
|
Pending Assignment by SRZ | 4/19/2007 | | 5/7/2007 | | DONE |
|
|
|
5/7/2007 12:47:36 TLW - activity updated through activity BLDA185 from case BLD07-00985.
|
Routing - PLAN CHECK | | | 5/7/2007 | | PASS |
|
|
|
Fully engineered house, engineered by Timothy Johnson P.E. w/ Briggs Engineering.
|
Plan assigned to (TLW) | 5/7/2007 | | 5/7/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/7/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/7/2007 | | DONE |
|
|
|
|
Routing - FIRE | 4/20/2007 | | 4/24/2007 | | PASS |
|
|
|
No fire sprinklers required (Eyrie Sub #3)
|
Routing - Erosion and Sediment | 4/20/2007 | | 4/20/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 4/19/2007 | | 4/20/2007 | | PASS |
|
|
|
|
Routing - Addressing | 4/19/2007 | | 4/19/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/19/2007 | | 4/19/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 4/19/2007 | | 4/19/2007 | | PASS |
|
|
|
Approved as Category 3
|
Application received | | | 4/19/2007 | | |
|
|
|
|