Third Notice BLD | 10/30/2007 | 10/30/2007 | 11/6/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Third Notice BLD | 10/30/2007 | 10/30/2007 | 11/6/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 10/17/2007 | 10/17/2007 | 10/30/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
Second Notice BLD | 10/17/2007 | 10/17/2007 | 10/30/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 10/1/2007 | 10/17/2007 | | DONE |
|
|
|
|
First Notice | | 10/1/2007 | 10/17/2007 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/1/2007 | | |
|
|
|
|
BLD-Framing/Rough-in | 9/20/2007 | 9/21/2007 | 9/21/2007 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/20/2007 at 12:10:31 PM. Contact: ###-####.
|
BLD-Final | 9/21/2007 | 9/21/2007 | 9/21/2007 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/20/2007 at 12:10:31 PM. Contact: ###-####. OK for Perm Occ.
|
FIRE-Conference | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | CANC |
Troy Cobbley
|
|
|
Wrong inspection type called in.
|
BLD-Framing/Rough-in | 9/19/2007 | 9/20/2007 | 9/20/2007 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/19/2007 at 2:03:13 PM. Contact: ###-####.
|
BLD-Final | 9/20/2007 | 9/20/2007 | 9/20/2007 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/19/2007 at 2:03:13 PM. Contact: ###-####. OK for Temp Occ. Need to see angle iron on West stairway.
|
FIRE-Final Inspection | 9/20/2007 | 9/20/2007 | 9/20/2007 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Framing/Rough-in | 9/18/2007 | 9/19/2007 | 9/19/2007 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/18/2007 at 1:45:15 PM. Contact: ###-####.
|
FIRE-Alarm Testing | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | FAIL |
Troy Cobbley
|
|
|
Provide signage at the area of refuge and provide verification of emergency lighting. The intercom test ok and a active phone has been installed as well.
|
FIRE-Final Inspection | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | FAIL |
Troy Cobbley
|
|
|
Provide signage at the area of refuge and provide verification of emergency lighting. The intercom test ok and a active phone has been installed as well.
|
BLD-Framing/Rough-in | 9/10/2007 | 9/10/2007 | 9/10/2007 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/10/2007 at 9:06:31 AM. Contact: ###-####. Rated ceiling at West stairway OK
|
BLD-Framing/Rough-in | 9/7/2007 | 9/10/2007 | 9/10/2007 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/7/2007 at 3:25:58 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 9/5/2007 | 9/6/2007 | 9/6/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/5/2007 at 11:17:39 AM. Contact: ###-####. New wall at West stairway OK.
|
BLD-Framing/Rough-in | 8/21/2007 | 8/22/2007 | 8/22/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/21/2007 at 2:38:17 PM. Contact: ###-####. Top layer of 1hr ceiling at corridor and stairway OK
|
BLD-Framing/Rough-in | 8/20/2007 | 8/21/2007 | 8/21/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/20/2007 at 10:43:34 AM. East stairway walls OK 1hr.
|
BLD-Framing/Rough-in | 8/20/2007 | 8/20/2007 | 8/20/2007 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/20/2007 at 8:20:12 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Aug 20 2007 10:11AM.
|
BLD-Wall cover | 8/10/2007 | 8/13/2007 | 8/13/2007 | A | DONE |
Jim Sly
|
|
|
Richard, follow up Phone #: ###-#### Met with Contr to discuss 1hr rating at walls/ceilings
|
BLD-Conference | 8/3/2007 | 8/6/2007 | 8/6/2007 | A | DONE |
Jim Sly
|
|
|
richard Phone #: ###-#### Need 1hr assemblies for walls and ceiling at stairways from Architect of record.
|
BLD-Framing/Rough-in | 7/23/2007 | 7/23/2007 | 7/23/2007 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/23/2007 at 9:16:11 AM. Contact: ###-####. office walls ok
|
Issue PAID IN FULL permit | | | 7/2/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/30/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/30/2007 | | DONE |
|
|
|
t/c w ben jansen at ###-#### - permit ready and fees given - also need gc name and rce#
|
Permit Ready to Issue | | | 5/30/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 5/9/2007 | | 5/29/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2007 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/29/2007 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 5/2/2007 | | 5/29/2007 | | PASS |
|
|
|
5/29/2007 14:09:37 M_P - activity updated through activity BLDA022 from case BLD07-01008.
|
Plan resubmittals received | | | 5/25/2007 | | DONE |
|
|
|
received 1 transmittal,2 plan review responses,2 plan review report,2 letters, 2 structural calcs and 2 copys of sheets G-1,A-1,M-1,EC2 taken to Mike P.
|
1st review completed | | | 5/9/2007 | | FAIL |
|
|
|
|
Routing - FIRE | 5/8/2007 | | 5/9/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
Case Summary (BLD) | | | 5/8/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 5/3/2007 | | 5/8/2007 | | FAIL |
|
|
|
Plan review completed, sent correction report to the architect requesting additional information to be submitted for further review prior to issuing permit.
|
Routing - PUBLIC WORKS | 5/2/2007 | | 5/3/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 4/20/2007 | | 5/2/2007 | | DONE |
|
|
|
5/2/2007 11:46:46 MYS - activity updated through activity BLDA170 from case BLD07-01008.
|
Plans ACCEPTED BY PLAN TECH | | | 4/23/2007 | | |
|
|
|
|
Application received | | | 4/20/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/20/2007 | | |
|
|
|
|