Override - Parcel Holds | | | 1/28/2008 | | |
|
|
|
|
Letter of compliance | | | 1/28/2008 | | DONE |
|
|
|
|
BLD-Final | 1/25/2008 | 1/25/2008 | 1/25/2008 | P | PASS |
Tom Arcoraci
|
|
|
rich Phone #: ###-####
|
Override - Parcel Holds | 1/25/2008 | 1/1/1900 | 1/25/2008 | | |
|
|
|
final for canopy
|
BLD-Final | 1/24/2008 | 1/24/2008 | 1/24/2008 | P | CANC |
Jim Sly
|
|
|
rich Phone #: ###-#### Canceled by Contr.
|
Override - Parcel Holds | 1/24/2008 | 1/1/1900 | 1/24/2008 | | |
|
|
|
need a fn insp
|
Code Occupancy Approval | 1/14/2008 | 1/14/2008 | 1/14/2008 | P | PASS |
Scott M.Brown
|
|
|
OK FOR FINAL
|
FIRE-Final Inspection | 1/14/2008 | 1/14/2008 | 1/14/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Conference | 1/9/2008 | 1/10/2008 | 1/10/2008 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 10/10/2007 | 10/10/2007 | 10/10/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 9/13/2007 | 9/13/2007 | 9/13/2007 | | PASS |
Tom Arcoraci
|
|
|
|
Issue PAID IN FULL permit | | | 6/14/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/22/2007 | | 6/5/2007 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 6/5/2007 | | PASS |
|
|
|
Reviewed and approved structural and nonstructural resubmittals.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/5/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/5/2007 | | DONE |
|
|
|
|
Telephone call | | | 6/5/2007 | | |
|
|
|
called Jeff Cramer, contact for architect at ###-#### and left voice message that permit is ready, fee, need RCE and RP
|
Plan assigned to (JCM) | 4/30/2007 | | 6/5/2007 | | PASS |
|
|
|
6/5/2007 07:58:19 JCM - activity updated through activity BLDA022 from case BLD07-01074.
|
Plan resubmittals received | | | 6/1/2007 | | |
|
|
|
Received response letter and two copies of pages 101-AB-4, A-803-4, S-101AB; taken to John Menard
|
Plan resubmittals received | | | 5/24/2007 | | |
|
|
|
Received two copies of 1pg. response letter, and three copies of pages S-001AB, S-514, S-515; taken to John Menard
|
1st review completed | | | 5/22/2007 | | FAIL |
|
|
|
failed plan check.
|
Routing - FIRE | 5/21/2007 | | 5/22/2007 | | PASS |
|
|
|
Attached fire review comments to plans.
|
Routing - PLAN CHECK | 5/15/2007 | | 5/21/2007 | | FAIL |
|
|
|
John Menard
|
Plan resubmittals requested | | | 5/21/2007 | | DONE |
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing - PLANNING | 5/15/2007 | | 5/15/2007 | | PASS |
|
|
|
DRH07-00203 unassigned
Approved per DRH07-00203.
|
Routing - PLUMBING | 5/3/2007 | | 5/15/2007 | | PASS |
|
|
|
min. horitontal rain water piping is 3".
|
Plan resubmittals requested | | | 5/15/2007 | | DONE |
|
|
|
Faxed the architect a copy of the plan review comment list from the consulting structural engineer requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 4/30/2007 | | 5/14/2007 | | FAIL |
|
|
|
Received comment letter from the consulting structural engineer requesting revisions. JCM
|
Routing - Erosion and Sediment | | | 5/3/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing PW Drainage | 5/1/2007 | | 5/1/2007 | | PASS |
|
|
|
|
Routing PW Sewer Rating | 5/1/2007 | | 5/1/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/1/2007 | | 5/1/2007 | | PASS |
|
|
|
|
Telephone call | | | 4/30/2007 | | DONE |
|
|
|
called Action Couriers for pick up to off site engineering
|
Routing - PLANNING Land Div | 4/30/2007 | | 4/30/2007 | | PASS |
|
|
|
|
Application received | | | 4/30/2007 | | |
|
|
|
|
Pending Assignment by MYS | 4/30/2007 | | 4/30/2007 | | DONE |
|
|
|
4/30/2007 13:31:46 JCM - activity updated through activity BLDA166 from case BLD07-01074.
|
(F) Reprint permit | | | 4/30/2007 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 4/30/2007 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/30/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/30/2007 | | |
|
|
|
|