Second Notice BLD | 10/1/2007 | 10/1/2007 | 10/11/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
Routing - PLANNING | 6/19/2007 | | 10/11/2007 | | PASS |
|
|
|
|
First Notice | | 9/21/2007 | 10/1/2007 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/21/2007 | | DONE |
|
|
|
|
BLD-Final | 9/19/2007 | 9/20/2007 | 9/20/2007 | P | PASS |
Tom Arcoraci
|
|
|
ivan Phone #: ###-####
|
Code Occupancy Approval | 8/24/2007 | 8/24/2007 | 8/24/2007 | P | PASS |
Dena Gambrel
|
|
|
|
FIRE-Final Inspection | 8/23/2007 | 8/23/2007 | 8/23/2007 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
BLD-Conference | 8/22/2007 | 8/23/2007 | 8/23/2007 | A | PASS |
Tom Arcoraci
|
|
|
Ivan; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok to move in supplys
|
FIRE-Final Inspection | 8/21/2007 | 8/22/2007 | 8/22/2007 | A | FAIL |
Troy Cobbley
|
|
|
Remove the thumbturn and provide approved hardware on the rear exit door.
|
BLD-Other | 8/8/2007 | 8/9/2007 | 8/9/2007 | P | PASS |
Jim Sly
|
|
|
IVAN nOTE: CEILING GRID Phone #: ###-####
|
BLD-Framing/Rough-in | 7/17/2007 | 7/18/2007 | 7/18/2007 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/17/2007 at 5:12:12 PM. Contact: ###-####.
|
Telephone call | | | 6/20/2007 | | |
|
|
|
left vm for dana kauffman at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/20/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/20/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/19/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/19/2007 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/15/2007 | | 6/19/2007 | | PASS |
|
|
|
ESC waiver request approved with attached conditions.
|
Print Occupancy Form | | | 6/15/2007 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 6/15/2007 | | |
|
|
|
this plan needs to go to ESC
|
Routing - PLAN CHECK | 6/12/2007 | | 6/14/2007 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/14/2007 | | |
|
|
|
received letter from insight arch & a transmittal letter. also "2" sheets of AO.1, & "2"sheets of A1.O, plans taken to Mike Phillips
|
Print Pending Permit.LaserJet4 | | | 6/14/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/14/2007 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 5/10/2007 | | 6/14/2007 | | PASS |
|
|
|
6/14/2007 16:36:24 M_P - activity updated through activity BLDA022 from case BLD07-01123.
|
Routing - PLAN CHECK | 6/6/2007 | | 6/12/2007 | | FAIL |
|
|
|
Second review complete. Sent correction report to the architect requesting additional information to be submitted for further review prior to issuing permit.
|
Routing - FIRE | 5/31/2007 | | 6/6/2007 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 6/6/2007 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/5/2007 | | |
|
|
|
Received transmittal, response letter, and two copies of pages A0.1 & A1.0; taken to Mike Phillips
|
Case Summary (BLD) | | | 5/31/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 5/11/2007 | | 5/31/2007 | | FAIL |
|
|
|
Plan review completed, sent correction report to the architect. Additional information is required to be submitted for further review prior to issuing permit.
|
Routing - PUBLIC WORKS | 5/10/2007 | | 5/11/2007 | | PASS |
|
|
|
|
Routing - PLANNING | 5/11/2007 | | 5/11/2007 | | PASS |
|
|
|
Sarah Schafer CZC07-00110 - Approved per CZC07-00110
|
Pending Assignment by MYS | 5/4/2007 | | 5/10/2007 | | DONE |
|
|
|
5/10/2007 10:47:29 MYS - activity updated through activity BLDA170 from case BLD07-01123.
|
Recd Pcfee & Taken To Pln CK | | | 5/4/2007 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/4/2007 | | |
|
|
|
|
Application received | | | 5/4/2007 | | |
|
|
|
|