Third Notice BLD | 12/22/2008 | 12/22/2008 | 3/5/2009 | | DONE |
Patricia Smith
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 9/22/2008 | 9/22/2008 | 12/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | 8/29/2008 | 8/29/2008 | 9/22/2008 | | DONE |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 8/29/2008 | 8/29/2008 | 8/29/2008 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 8/29/2008 | 8/29/2008 | 8/29/2008 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
FIRE-Final Inspection | 8/27/2008 | 8/28/2008 | 8/28/2008 | A | PASS |
Troy Cobbley
|
|
|
fire life safety passed
|
Telephone call | | | 8/28/2008 | | DONE |
Jason Blais
|
|
|
Linder Cockerham called to state the last tenant space had been completed and the Fire Inspection done. I told her to call in a Final Inspection for the Building Inspector so the permit could be finaled. When this is done, the Upgrade Agreement work will be complete.
|
FIRE-Final Inspection | 8/22/2008 | 8/22/2008 | 8/22/2008 | P | PART |
Troy Cobbley
|
|
|
The insulation in tenant space 10480 is complete
|
FIRE-Final Inspection | 8/20/2008 | 8/21/2008 | 8/21/2008 | A | FAIL |
Troy Cobbley
|
|
|
This inspection was for the tenant at 10480. The insulation has not been adequately secured to the deck and is blocking the upright sprinkler head coverage and is laying on the sprinkler piping.
|
FIRE-Final Inspection | 8/11/2008 | 8/11/2008 | 8/11/2008 | P | PART |
Troy Cobbley
|
|
|
The piping in American Family Insurance, 10494, is ok to cover.
|
FIRE-Final Inspection | 6/13/2008 | 6/16/2008 | 6/16/2008 | A | CANC |
Troy Cobbley
|
|
|
Matt- fire life saftey Phone #: ###-####
|
FIRE-Final Inspection | 5/19/2008 | 5/20/2008 | 5/20/2008 | A | PART |
Troy Cobbley
|
|
|
The insulation in tenant addresses 10442 and 10436 has been installed and can be covered.
|
FIRE-Final Inspection | 5/15/2008 | 5/15/2008 | 5/15/2008 | P | PART |
Troy Cobbley
|
|
|
The insulation in tenant 10436 has been completed and can be covered.
|
FIRE-Final Inspection | 3/11/2008 | 3/11/2008 | 3/11/2008 | P | PART |
Troy Cobbley
|
|
|
The insulation at tenant space 10370 is passed.
|
FIRE-Final Inspection | 2/13/2008 | 2/14/2008 | 2/14/2008 | A | PART |
Troy Cobbley
|
|
|
The insulation in tenant address 10354 is passed.
|
Case Summary (BLD) | | | 2/13/2008 | | |
|
|
|
|
FIRE-Final Inspection | 2/11/2008 | 2/12/2008 | 2/12/2008 | A | PART |
Troy Cobbley
|
|
|
The insulation at address 10476 is complete and can be covered.
|
FIRE-Final Inspection | 1/29/2008 | 1/29/2008 | 1/29/2008 | P | PART |
Troy Cobbley
|
|
|
The insulation at 10346 and 10352 has passed inspection.
|
FIRE-Final Inspection | 9/27/2007 | 9/27/2007 | 9/28/2007 | P | PASS |
Troy Cobbley
|
|
|
The insulation backing in tenant space 10390 has been completed
|
FIRE-Final Inspection | 8/30/2007 | 8/31/2007 | 8/31/2007 | A | PART |
Troy Cobbley
|
|
|
Tenant space 10464 is ok to cover. The second tenant space did not have all of the insulation backing held to the roof deck as agreed.
|
FIRE-Final Inspection | 8/7/2007 | 8/7/2007 | 8/8/2007 | P | PART |
Troy Cobbley
|
|
|
The new insulation backing has been installed in tenant spaces 10448, 10374 and 10366 and appears ok.
|
FIRE-Final Inspection | 6/28/2007 | 6/28/2007 | 6/29/2007 | P | PART |
Troy Cobbley
|
|
|
The insulation backing in the vacant tenant space next to the health food store has been installed and inspected.
|
FIRE-Final Inspection | 6/5/2007 | 6/6/2007 | 6/6/2007 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was only for the 10488 address. Insulation backing appeared to be mounted ok.
|
FIRE-Final Inspection | 5/31/2007 | 6/1/2007 | 6/1/2007 | A | FAIL |
Troy Cobbley
|
|
|
The new insulation backing is laying on the upright sprinklers deflectors in many location. Code requires 1" clearance.
|
Issue PAID IN FULL permit | | | 5/25/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2007 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 5/24/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/24/2007 | | DONE |
|
|
|
t/c w randy schultz at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/24/2007 | | |
|
|
|
|
Plan assigned to (JCB) | 5/16/2007 | | 5/24/2007 | | PASS |
|
|
|
5/24/2007 09:20:51 JCB - activity updated through activity BLDA022 from case BLD07-01201.
|
Routing - PLAN CHECK | 5/16/2007 | | 5/24/2007 | | PASS |
|
|
|
Changed/resubmitted plan reviewed and approved. Taken to front desk for permit issuance.
|
Plan resubmittals received | | | 5/21/2007 | | DONE |
|
|
|
Received 1 transmittal,and 3 copys of sheet BU-1 taken to Jason B.
|
Telephone call | | | 5/17/2007 | | DONE |
|
|
|
Scott Stom called and stated the tenant spaces with foil will also have to be addressed. The foil states "do not leave exposed" stamped right on the product. He will address and resubmit plans.
|
Telephone call | | | 5/16/2007 | | DONE |
|
|
|
Architect called to state more work was shown on the plan than what will actually be done. An updated/resubmitted plan will be provided. Pulled approved plans from the Permit Desk and they are back in plan review.
|
Plan assigned to (JCB) | 5/11/2007 | | 5/16/2007 | | PASS |
|
|
|
5/16/2007 13:24:48 JCB - activity updated through activity BLDA022 from case BLD07-01201.
|
Routing - PLAN CHECK | 5/11/2007 | | 5/16/2007 | | PASS |
|
|
|
Permit and plans approved. Discussed with Scott Arellano and plans do not need to route to Fire. He will add a note to field verify any Fire Code requirements.
|
Routing - FIRE | 5/16/2007 | | 5/16/2007 | | PASS |
|
|
|
No Fire review per Scott Arellano. Fire Code issues to be field verified by Fire Inspector.
|
1st review completed | | | 5/16/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2007 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 5/16/2007 | | |
|
|
|
|
Plan resubmittals received | | | 5/16/2007 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/11/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/11/2007 | | DONE |
|
|
|
|
Application received | | | 5/11/2007 | | |
|
|
|
|