PubWorks Occupancy Approval | 2/13/2012 | 2/13/2012 | 2/13/2012 | | DONE |
Brian Murphy
|
|
|
|
FIRE-Final Inspection | 2/9/2012 | 2/10/2012 | 2/10/2012 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. A smoke alarm in unit 104 was repaired while I waited.
|
Print Occupancy Form | | | 2/10/2012 | | |
|
|
|
|
Permanent Occupancy | | | 2/10/2012 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Conference | 2/9/2012 | 2/9/2012 | 2/9/2012 | P | CANC |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 2/7/2012 | 2/7/2012 | 2/9/2012 | P | FAIL |
Troy Cobbley
|
|
|
ron Phone #: ###-#### Could not make contact with the builder and the place was locked. No inspection was performed
|
Zoning Approval | 2/7/2012 | 2/7/2012 | 2/7/2012 | | PASS |
Josh Wilson
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/7/2012 | | DONE |
|
|
|
finaled by mistake
|
BLD-Final | 1/19/2012 | 1/20/2012 | 1/20/2012 | A | PASS |
Jim Sly
|
|
|
lance Phone #: ###-#### Or Wayne ###-####
|
DOC - Permit Finaled | 1/20/2012 | 1/20/2012 | 1/20/2012 | P | PASS |
Jim Sly
|
|
|
|
Reopen Permit (ISS) | | | 1/18/2012 | | DONE |
Christina Prado
|
|
|
Per Bob A-- OK to reopen with 2hr admin fee
|
(F) Reprint permit | | | 1/18/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 12/12/2011 | | DONE |
Tisha Gallop
|
|
|
per Bob A. 2 hr admin fee to reopen building permit and 2 hr admin fee each to reopen all subcontractor permits.
|
BLD-Conference | 11/29/2010 | 11/30/2010 | 11/30/2010 | A | CANC |
Jim Sly
|
|
|
|
Case Summary (BLD) | | | 11/29/2010 | | DONE |
|
|
|
|
BLD-Final | 4/12/2010 | 4/13/2010 | 4/13/2010 | A | DONE |
Jim Sly
|
|
|
Ron phone No activity.....more than 180 days....Expired.
|
DOC - Permit Expired | 4/13/2010 | 4/13/2010 | 4/13/2010 | P | PASS |
Jim Sly
|
|
|
Ron phone
|
BLD-Final | 4/12/2010 | 4/12/2010 | 4/12/2010 | P | CANC |
Jim Sly
|
|
|
Ron phone Re-sched.....
|
(F) Reprint permit | | | 11/10/2008 | | DONE |
|
|
|
|
BLD-Other | 9/3/2008 | 9/3/2008 | 9/3/2008 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/3/2008 at 6:42:59 AM. Contact: ###-####.
|
BLD-Conference | 6/5/2008 | 6/5/2008 | 6/5/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 6/5/2008 | 6/5/2008 | 6/5/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 6/4/2008 | 6/5/2008 | 6/5/2008 | A | CANC |
Tom Arcoraci
|
|
|
Ron- call 10 mins prior to going Phone #: ###-####
|
BLD-Framing/Rough-in | 6/3/2008 | 6/4/2008 | 6/4/2008 | A | PART |
Jim Sly
|
|
|
ron Phone #: ###-####
|
BLD-Other | 4/23/2008 | 4/23/2008 | 4/23/2008 | P | CANC |
Jim Sly
|
|
|
ron Note: shear (like nylons Jim) Shear nailing OK
|
BLD-Foundation | 10/2/2007 | 10/3/2007 | 10/3/2007 | A | PASS |
Jim Sly
|
|
|
CLIFF NOTE: WALL Phone #: ###-####
|
BLD-Footing | 10/2/2007 | 10/2/2007 | 10/2/2007 | P | CANC |
Jim Sly
|
|
|
cliff Phone #: ###-#### Already approved footing.......Need foundation wall inspection.
|
BLD-Conference | 9/14/2007 | 9/14/2007 | 9/14/2007 | P | DONE |
Jim Sly
|
|
|
Stop Work order issued. Footing Ok'd....No wall poured W/O inspection......issues with setbacks from irrigation pipe.
|
BLD-Footing | 9/6/2007 | 9/6/2007 | 9/14/2007 | P | CANC |
Jim Sly
|
|
|
cliff Phone #: ###-####
|
BLD-Footing | 8/29/2007 | 8/30/2007 | 8/30/2007 | A | PASS |
Jim Sly
|
|
|
cliff Phone #: ###-####
|
BLD-Footing | 8/28/2007 | 8/29/2007 | 8/29/2007 | A | CANC |
Jim Sly
|
|
|
cliff Phone #: ###-#### Workers said....."not ready to do footing at lot 6"
|
Issue PAID IN FULL permit | | | 8/23/2007 | | DONE |
|
|
|
|
Telephone call | | | 8/22/2007 | | DONE |
|
|
|
t/c w chad slichter at ###-#### - permit ready and fees given - also need ACHD receipt
|
Permit Ready to Issue | | | 8/22/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/17/2007 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 7/10/2007 | 7/10/2007 | 8/16/2007 | | PASS |
|
|
|
8/16/2007 16:52:39 M_P - activity updated through activity BLDA022 from case BLD07-01363.
|
Routing - PLAN CHECK | 7/12/2007 | | 8/16/2007 | | |
|
|
|
Routing to P.W.
|
Routing - PUBLIC WORKS | 8/16/2007 | | 8/16/2007 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/16/2007 | | |
|
|
|
Received Sheet 1 for Public Works Trash Enclosure location, attached to plans and routed to PW///8/16/07 @ 9:20am BAS
|
Routing - PLAN CHECK | 8/16/2007 | | 8/16/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/16/2007 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/16/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/16/2007 | | DONE |
|
|
|
|
1st review completed | | | 7/12/2007 | | FAIL |
|
|
|
|
Routing - FIRE | 7/10/2007 | | 7/12/2007 | | PASS |
|
|
|
Attached review comments to plans.
|
Case Summary (BLD) | | | 7/10/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 6/27/2007 | | 7/10/2007 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Plan assigned to (M_P) | 5/25/2007 | 5/25/2007 | 6/29/2007 | | |
|
|
|
Assigned to Sam Zahorka.
|
Routing - PLAN CHECK | 6/22/2007 | | 6/27/2007 | | |
|
|
|
Mike Phillips
Routing to Planning.
|
Routing - PLANNING | 6/27/2007 | | 6/27/2007 | | PASS |
|
|
|
See redlines on plans
|
Routing - PLANNING | 6/20/2007 | | 6/22/2007 | | FAIL |
|
|
|
Drh06-00173 Josh Wilson; Cup05-00031 Cody R.
Passed Current Planning, however project fails to meet requiements of DR approval. J.Wilson to contact applicant.
|
Routing - PLUMBING | 6/12/2007 | | 6/19/2007 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 6/8/2007 | | 6/12/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions. Refer to ESC07-00661 as master ESC plan.
|
Routing - PUBLIC WORKS | 5/30/2007 | | 6/8/2007 | | FAIL |
|
|
|
|
Routing PW Solid Waste | 5/30/2007 | | 6/8/2007 | | PASS |
|
|
|
|
Routing PW Sewer Rating | 6/7/2007 | | 6/7/2007 | | PASS |
|
|
|
|
Routing PW Street Lights | 6/1/2007 | | 6/5/2007 | | PASS |
|
|
|
|
Routing PW Drainage | 6/5/2007 | | 6/5/2007 | | PASS |
|
|
|
|
Routing PW Sewer Design | 5/30/2007 | | 6/1/2007 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 5/25/2007 | | 5/29/2007 | | PEND |
|
|
|
Do not issue permit until final plat is recorded.
|
Plans ACCEPTED BY PLAN TECH | | | 5/25/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/25/2007 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 5/25/2007 | | |
|
|
|
|
Application received | | | 5/25/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 8/16/2007 | | | | |
|
|
|
|