Third Notice BLD | 10/1/2007 | 10/1/2007 | 10/9/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 9/13/2007 | 9/13/2007 | 10/1/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 8/28/2007 | 9/13/2007 | | DONE |
|
|
|
|
BLD-Final | 8/28/2007 | 8/28/2007 | 8/28/2007 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/28/2007 at 9:12:14 AM. Contact: ###-####.
|
Permanent Occupancy | | | 8/28/2007 | | DONE |
|
|
|
|
BLD-Final | 8/23/2007 | 8/24/2007 | 8/27/2007 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/23/2007 at 8:28:40 PM. Contact: ###-####. Need fire.....
|
FIRE-Final Inspection | 8/27/2007 | 8/27/2007 | 8/27/2007 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
FIRE-Sprinkler Rough-in | 8/7/2007 | 8/8/2007 | 8/8/2007 | A | FAIL |
Forrest France
|
|
|
Inspection to be requested under the FIR permit for related work, noted two overspaced heads-locations indicated on approved plans.
|
BLD-Other | 8/3/2007 | 8/6/2007 | 8/7/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/3/2007 at 5:01:12 PM. Contact: ###-####. ok to cover after other trades ok above ceiling and add a wire to mec fixtures
|
BLD-Energy code compliance | 7/16/2007 | 7/17/2007 | 7/17/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/16/2007 at 2:59:15 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/13/2007 | 7/16/2007 | 7/16/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/13/2007 at 3:35:51 PM. Contact: ###-####. ok to cover int walls ok to insulate ext walls
|
Print Occupancy Form | | | 6/26/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/26/2007 | | DONE |
|
|
|
|
Telephone call | | | 6/26/2007 | | DONE |
|
|
|
t/c w jonathan seel at ###-#### - permit ready and fees given - also faxed the fees to him at ###-#### - also called dawna jenkins at ###-#### and let her know the permit was ready and the fee amount and told her that jonathan called for same
|
Permit Ready to Issue | | | 6/26/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/26/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/19/2007 | | 6/25/2007 | | PASS |
|
|
|
Drawings approved after the resubmittal review.
|
Plan assigned to (CJW) | 5/25/2007 | | 6/25/2007 | | PASS |
|
|
|
6/25/2007 14:26:48 CJW - activity updated through activity BLDA022 from case BLD07-01364.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/21/2007 | | |
|
|
|
Received response letter from Larson Architects, response letter from Musgrove Eng., and two copies of pages A-1, A-2, M-3; taken to Carl Westfall
|
1st review completed | | | 6/19/2007 | | FAIL |
|
|
|
|
Routing - FIRE | 6/18/2007 | | 6/19/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
Routing - PLAN CHECK | 5/29/2007 | | 6/18/2007 | | FAIL |
|
|
|
The IBC plan review was started on June 15, 2007 and was finished on June 18, 2007. Revised drawings were required. See the plan review report.
|
Plan resubmittals received | | | 6/5/2007 | | |
|
|
|
received letter from larson arch & "3" sets of plans with each sheet A-1, M-1, M-2, M-3, E1, & E2--plans taken to Carl Westfall
|
Routing - PUBLIC WORKS | 5/25/2007 | | 5/29/2007 | | PASS |
|
|
|
|
Routing PW Sewer Rating | 5/29/2007 | | 5/29/2007 | | PASS |
|
|
|
|
Application received | | | 5/25/2007 | | |
|
|
|
|
Pending Assignment by MYS | 5/25/2007 | | 5/25/2007 | | DONE |
|
|
|
5/25/2007 15:51:39 MYS - activity updated through activity BLDA172 from case BLD07-01364.
|
Recd Pcfee & Taken To Pln CK | | | 5/25/2007 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/25/2007 | | |
|
|
|
|