Permit Information
Permit NumberBLD07-01372
StatusFinaled
Name THE CHRISTENSEN CORP
Site Address 2626 S GEKELER LN
Project NameLAKEWOOD MONTESORRI SCHOOL
Customer Number 
ePlanReviewNo
Description
(LAKEWOOD MONTESSORI SCHOOL) To remodel the existing 13,693 sq.ft. Montessori School Child Care Facility (established under MIS04-00176, C.O. #10272) by removing existing offices, kitchen and meeting areas; too create two new classrooms and support areas; reconfigure bathrooms to serve new classrooms; add new exterior doors such that all classrooms have exits directly to exterior; create two new office areas, an Art Room and Library; change the use of the sanctuary into an indoor exercise area. Scope of work will not increase existing buidling area or occupancy use group per the original certificate of occupancy of 8/31/04, but it will change the total occupant load. All per approved plans, zoning ordinance, central district health and licensing requirements of Boise City Clerk. Project reviewed as a Non-Separated Mixed Use Occupancy, the "B" occupancy used as allowable area control. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  6/20/2011 DONE
Third Notice BLD9/22/20089/22/20089/30/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to. Filed for Bankruptcy
Second Notice BLD8/11/20088/11/20089/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice7/30/20087/30/20088/11/2008 DONE
DetailsJim Storey
BLD-Final7/30/20087/30/20087/30/2008PPASS
DetailsJim Storey
Tucker Phone #: ###-####
DOC - Permit Finaled7/30/20087/30/20087/30/2008PPASS
DetailsJim Storey
BLD-Aging Inspection6/16/20086/16/20086/16/2008 PART
DetailsJim Storey
gate hardware being addressed.
BLD-Final4/14/20084/15/20084/15/2008AFAIL
DetailsJim Storey
Mike; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt need panic on outside gate.
FIRE-Final Inspection4/11/20084/14/20084/14/2008APASS
DetailsForrest France
Verified items on correction notice are complete, fire life safety passed. NOTE: no signature card available on site at the time of inspection.
FIRE-Final Inspection4/9/20084/10/20084/11/2008AFAIL
DetailsForrest France
See inspection notes completed 4/11.
FIRE-Final Inspection4/10/20084/11/20084/11/2008AFAIL
DetailsForrest France
Repair exit sign at the SE classroom, provide lever hardware at the second marked exit door from the art room, noted exit doors are blocked or covered by curtains at five areas-see approved plans for locations-exit doors are to be maintained free from obstructions at all times per IFC and IBC requirements.
BLD-Aging Inspection2/12/20082/12/20082/12/2008 DEFR
DetailsJim Storey
to fire
BLD-Framing/Rough-in8/17/20078/17/20078/17/2007PPASS
DetailsTony Young
Phone #: ###-#### Internet Inspection Request from:
Telephone call  7/25/2007 DONE
left vm for j tucker anderson at ###-#### - permit ready and fees given - also need receipt for CDHD
Permit Ready to Issue  7/25/2007 DONE
Issue PAID IN FULL permit  7/25/2007 DONE
Routing - PLAN CHECK7/19/2007 7/24/2007 PASS
Plan review complete. Red-line notes on plans and all attached plan reviews of all agencies are part of the reviewed plans requiring compliance for final inspections.
PLANS/APPL TAKEN TO FRONT DESK  7/24/2007 PASS
Approved as noted on and attached plan review conditions. To permit desk to issue.
Print Occupancy Form  7/24/2007 DONE
Plan assigned to (DRS)6/8/2007 7/24/2007 PASS
7/24/2007 15:18:04 DRS - activity updated through activity BLDA022 from case BLD07-01372.
Routing - PLANNING7/17/2007 7/19/2007 PASS
Routing - PLAN CHECK7/13/2007 7/17/2007 PEND
Resubmittals received and attached to original plans. Routing plans back to Planning, Cody Riddle for re-review.
Plan resubmittals received  7/13/2007  
Received transmittal, 5pg. response letter, CDHD Plan Review and Approval Form, 2pgs. of calcs, and three copies of pages G-00, G-101, A-101, A-102, A-103, A-104; taken to Dan Stuart
1st review completed  7/13/2007 FAIL
Routing - FIRE7/9/2007 7/13/2007 PASS
Attached review comments to plans.
Plan resubmittals requested  7/9/2007 DONE
E-mailed copy of plan review to Tucker Anderston, Architecture H2A.
Print Pending Permit.LaserJet4  7/9/2007  
Case Summary (BLD)  7/9/2007  
Routing - PLAN CHECK6/27/2007 7/9/2007 FAIL
Resubmittals required. Copy of plan review e-mailed to architect, Tucker Anderson. Plans routed to fire code analyst for review.
Routing - PLUMBING6/13/2007 6/27/2007 PASS
As per plan & 2003 U.P.C./J.J.
Routing - PLANNING6/13/2007 6/13/2007 FAIL
A staff-level modification will be required for the conversion of office and meeting space into classrooms. Left a message with applicant at 2:15 p.m. today.
Routing - PUBLIC WORKS6/8/2007 6/13/2007 PASS
Pending Assignment by MYS5/29/2007 6/8/2007 DONE
6/8/2007 11:43:43 MYS - activity updated through activity BLDA168 from case BLD07-01372.
Routing - Addressing6/8/2007 6/8/2007 PASS
Routing PW Sewer Rating6/8/2007 6/8/2007 PASS
Plans ACCEPTED BY PLAN TECH  5/29/2007  
Application received  5/25/2007  
Recd Pcfee & Taken To Pln CK  5/25/2007