PubWorks Occupancy Approval | 2/3/2010 | 2/3/2010 | 2/3/2010 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 4/23/2008 | 4/23/2008 | 4/24/2008 | P | PASS |
Tom Arcoraci
|
|
|
As per George Slane, letter from architect, landings are approved
|
Letter of compliance | | | 4/23/2008 | | DONE |
Cathy Weisshaupt
|
|
|
Letter of Compliance issued
|
Code Occupancy Approval | 3/21/2008 | 3/21/2008 | 3/25/2008 | P | PASS |
Scott M.Brown
|
|
|
PARKING AND LANDSCAPE IN AS REQUIRED OK FOR FINAL
|
Code Occupancy Approval | 3/25/2008 | 3/25/2008 | 3/25/2008 | P | PASS |
Scott M.Brown
|
|
|
PARKING LOT MARKED CASE CLOSED FINAL OK
|
BLD-Final | 3/19/2008 | 3/19/2008 | 3/19/2008 | P | FAIL |
Tom Arcoraci
|
|
|
dean Phone #: ###-#### needs landings at rear doors
|
FIRE-Final Inspection | 3/13/2008 | 3/13/2008 | 3/13/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 3/11/2008 | 3/13/2008 | 3/13/2008 | A | NR |
Tom Arcoraci
|
|
|
dean Phone #: ###-#### needs fire and code enf sign offs
|
FIRE-Conference | 3/3/2008 | 3/4/2008 | 3/4/2008 | A | FAIL |
Troy Cobbley
|
|
|
Provide address facing overland and the side street as discussed. Remove the short sample tubes in the duct smoke detectors and relocate the long tube to the lower position. Also provide the correct remote annunciators and test the duct smoke detectors.
|
BLD-Framing/Rough-in | 1/11/2008 | 1/11/2008 | 1/11/2008 | P | PASS |
Tom Arcoraci
|
|
|
dean Phone #: ###-####
|
BLD-Framing/Rough-in | 11/7/2007 | 11/8/2007 | 11/8/2007 | A | PASS |
Tom Arcoraci
|
|
|
Dean; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ext and roof ok
|
BLD-Framing/Rough-in | 10/23/2007 | 10/24/2007 | 10/24/2007 | A | PART |
Tom Arcoraci
|
|
|
dean Phone #: ###-####
|
BLD-Foundation | 9/13/2007 | 9/13/2007 | 9/13/2007 | P | PEND |
Jim Sly
|
|
|
donny - wall Phone #: ###-#### MTI Inspected footings.......Wall appears OK pending special insp (MTI) tests and approvals.
|
BLD-Footing | 9/11/2007 | 9/12/2007 | 9/12/2007 | A | NR |
Tom Arcoraci
|
|
|
don Phone #: ###-#### needs zoning
|
(F) Reprint permit | | | 9/7/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/6/2007 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 9/4/2007 | | 9/5/2007 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/5/2007 | | 9/5/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/5/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/5/2007 | | DONE |
|
|
|
left message w jennie for mike falash at ###-#### - permit ready and fees given - also need RP name
|
Permit Ready to Issue | | | 9/5/2007 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 6/12/2007 | | 9/5/2007 | | PASS |
|
|
|
9/5/2007 11:33:48 JCM - activity updated through activity BLDA022 from case BLD07-01506.
|
Routing PW Drainage | 6/13/2007 | | 9/5/2007 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 8/30/2007 | | 9/4/2007 | | |
|
|
|
|
Routing - FIRE | 8/27/2007 | | 8/30/2007 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Routing PW Solid Waste | 8/27/2007 | | 8/28/2007 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/28/2007 | | |
|
|
|
Recieved 3 copies of Storm Water Plan and 1 copy of Boundry Drainage and given to Brian Murphy///8/28/07 @ 11:12am BAS
|
Routing - PUBLIC WORKS | 8/14/2007 | | 8/27/2007 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 8/14/2007 | | PASS |
|
|
|
Reviewed and approved structural revisions. JCM
|
Routing - PLAN CHECK | 7/24/2007 | | 8/14/2007 | | |
|
|
|
|
Plan resubmittals received | | | 8/13/2007 | | |
|
|
|
received 1 letter,1 response,1 comments ,1 comments (fire),2 calcs , and 2 copys of sheets A1.01,S0.2,S3.1,S4.1,C2.11,C2.21,C2.22,C2.31,C2.32,C2.41,C2.43,C2.51 taken to John M
|
Routing - PLANNING | 7/20/2007 | | 7/24/2007 | | PASS |
|
|
|
Josh Johnson
Josh Wilson
|
Routing - PLANNING | 6/21/2007 | | 7/24/2007 | | PASS |
|
|
|
Routed to Plan Check
|
Routing - FIRE | 7/17/2007 | | 7/20/2007 | | FAIL |
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 7/20/2007 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 7/20/2007 | | 7/20/2007 | | PEND |
|
|
|
Pending approval by others.
|
Routing - PLANNING Land Div | 7/20/2007 | | 7/20/2007 | | PASS |
|
|
|
Joan Johnson- verification passed
|
Routing - PLAN CHECK | 7/11/2007 | | 7/17/2007 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 7/17/2007 | | PASS |
|
|
|
Plan approved with attached comment list.
|
Routing - PLANNING | 7/11/2007 | | 7/11/2007 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 7/11/2007 | | 7/11/2007 | | FAIL |
|
|
|
Site plan showing land division not approved or not according to recorded plat.
Joan spoke to Byron Folwell, ###-####, Architect regarding land division issues - either the site plan is to be reformatted to match existing lot lines and the approved CUP. or the formal land division process must be completed through the Boise City process, and recorded at Ada County.
|
Telephone call | | | 7/11/2007 | | |
Dave Abo
|
|
|
Joan spoke to Byron Folwell, ###-####, Architect regarding land division issues - either the site plan is to be reformatted to match existing lot lines and the approved CUP. or the formal land division process must be completed through the Boise City process, and recorded at Ada County.
|
Routing - PLAN CHECK | 7/2/2007 | | 7/11/2007 | | |
|
|
|
John M. - Returned plans to Land Division to verify legal lot situation. JCM
|
Routing - PLUMBING | 6/14/2007 | | 6/21/2007 | | PASS |
|
|
|
1) Increase FD-1 to 4' to recieve discharge from R.P. or install D.C.V.A for premise protection (BFP-1)
2) Use Boise City approved grease interceptor detail attached
J.J.
|
Routing Off Site - STRUCTURAL | 6/12/2007 | | 6/20/2007 | | FAIL |
|
|
|
Called Action Couriers for pick up - Received comment list from the consulting structural engineer requesting revisions.
|
Plan resubmittals requested | | | 6/20/2007 | | DONE |
|
|
|
Faxed the architect a copy of the structural plan review requesting revisions.
|
Routing - Erosion and Sediment | 6/14/2007 | | 6/15/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing PW Environmental | 6/15/2007 | | 6/15/2007 | | PASS |
|
|
|
Pretreatment review - shell and core shows GI with common grease line to all tenant spaces
|
Routing PW Solid Waste | 6/13/2007 | | 6/14/2007 | | FAIL |
|
|
|
Trash truck cannot approach enclosure from the south against one-way traffic. Angle the enclosure so trash truck has direct access coming from the east, or move enclosure to southeast planting strip and angle it so truck has direct access approaching from the east.
|
Routing - PUBLIC WORKS | 6/13/2007 | | 6/14/2007 | | FAIL |
|
|
|
|
Routing - PLANNING Land Div | 6/12/2007 | | 6/13/2007 | | PASS |
|
|
|
|
Routing PW Street Lights | 6/13/2007 | | 6/13/2007 | | PASS |
|
|
|
|
Application received | | | 6/12/2007 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/12/2007 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 6/12/2007 | | |
|
|
|
|
Routing PW Drainage | 8/28/2007 | | | | |
|
|
|
Recieved 3 copies of Storm Water Plan and 1 copy of Boundry Drainage and given to Brian Murphy///8/28/07 @ 11:12am BAS
|
Routing PW Drainage | 8/14/2007 | | | | |
|
|
|
|