Code Occupancy Approval | 11/9/2007 | 11/9/2007 | 11/9/2007 | P | PASS |
Dena Gambrel
|
|
|
|
BLD-Final | 11/9/2007 | 11/9/2007 | 11/9/2007 | P | PASS |
Tom Arcoraci
|
|
|
todd Phone #: ###-####
|
DOC - Permit Finaled | 11/9/2007 | 11/9/2007 | 11/9/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
Code Occupancy Approval | 9/12/2007 | 9/12/2007 | 9/12/2007 | P | FAIL |
Dena Gambrel
|
|
|
9-12-07 Not ready for Landscape Inspection at this time.
|
BLD-Energy code compliance | 9/12/2007 | 9/12/2007 | 9/12/2007 | P | PASS |
Tom Arcoraci
|
|
|
todd Phone #: ###-####
|
BLD-Final | 9/10/2007 | 9/11/2007 | 9/11/2007 | A | CANC |
Tom Arcoraci
|
|
|
TODD Phone #: ###-####
|
BLD-Framing/Rough-in | 9/7/2007 | 9/7/2007 | 9/7/2007 | P | PASS |
Tom Arcoraci
|
|
|
todd Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/13/2007 | | DONE |
|
|
|
|
Telephone call | | | 7/11/2007 | | DONE |
|
|
|
t/c w todd at wood river builders ###-#### - permit ready and fees given - also need RP name
|
Permit Ready to Issue | | | 7/11/2007 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 7/9/2007 | | 7/10/2007 | | PASS |
|
|
|
7/10/2007 15:21:07 TLW - activity updated through activity BLDA022 from case BLD07-01550.
|
Plan resubmittals received | | | 7/10/2007 | | |
|
|
|
Received two copies of page 4 (roof framing and eage detail); taken to Tim W.
|
Routing - PLAN CHECK | 7/10/2007 | | 7/10/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2007 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/10/2007 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 7/3/2007 | | 7/9/2007 | | PASS |
|
|
|
7/9/2007 15:06:49 TLW - activity updated through activity BLDA022 from case BLD07-01550.
|
Plan resubmittals received | | | 7/9/2007 | | |
|
|
|
received new set of plans with revised truss detail and calcs; taken to Tim W.
|
Routing - PLAN CHECK | 7/9/2007 | | 7/9/2007 | | FAIL |
|
|
|
Fire rated eve detail still not correct went and got back from front desk 7-9-07
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/9/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/9/2007 | | DONE |
|
|
|
|
Pending Assignment by SRZ | 6/15/2007 | | 7/3/2007 | | DONE |
|
|
|
7/3/2007 14:31:50 TLW - activity updated through activity BLDA185 from case BLD07-01550.
|
Routing - PLAN CHECK | 6/19/2007 | | 7/3/2007 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 7/3/2007 | | DONE |
|
|
|
Called Paul at Media One and requested he resubmit roof framing plan showing locations and a detail of his fire-rated eves.
|
Routing - PUBLIC WORKS | 6/18/2007 | | 6/19/2007 | | PASS |
|
|
|
|
Routing - PLANNING | 6/18/2007 | | 6/18/2007 | | PASS |
|
|
|
Routed to Josh Wilson DRH07-00250 6/18/07
|
Routing - Addressing | 6/15/2007 | | 6/18/2007 | | PASS |
|
|
|
|
Application received | | | 6/15/2007 | | |
|
|
|
|