Permit Information
Permit NumberBLD07-01561
StatusFinaled
Name COMPUTERS FOR KIDS
Site Address 8540 W ELISA ST
Project NameVictory Business Park-Bldg A
Customer Number 
ePlanReviewNo
Description
(COMPUTERS FOR KIDS INC - VICTORY BUSINESS PARK BLDG A) To remodel an existing 7147 sq.ft. tenant space for warehouse and office with a new 896 sq.ft. mezzanine to be used for office space per approved plans on file. Work to include, construction of masonry walls, concrete floor for new mezzanine area with guardrail and stairway, construciton of new interior nonbearing partitions to construct two new accessible restrooms, breakroom area, new office spaces and small storage rooms, installation of new roof top HVAC and related ducting, miscellaneous related interior finishes. This building is fully fire sprinkled any alterations to the sprinkler system shall be per NFPA #13 as regulated by the fire department. RmH
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  4/15/2011 DONE
left message w scott for molli to call me back regarding past due fees
Third Notice 3/4/20113/2/2011 DONE
Third Notice 2/9/20112/18/2011 DONE
DetailsTisha Gallop
faxed and mailed to tenant at project address
Second Notice 2/3/20112/4/2011 DONE
First Notice12/27/201012/27/20101/6/2011 DONE
DetailsMike Jordan
mailed to whitworth on the 6th - came back - mailed to computers for kids on the 12th
BLD-Conference12/27/201012/27/201012/27/2010PCANC
DetailsMike Jordan
BLD-Conference12/23/201012/27/201012/27/2010APASS
DetailsMike Jordan
tammy Phone #: ###-####
DOC - Permit Finaled12/27/201012/27/201012/27/2010PPASS
DetailsMike Jordan
All storage has been removed from mezzanine. Letter of compliance was issued.
BLD-Final12/17/201012/17/201012/17/2010PFAIL
DetailsMike Jordan
tammy Phone #: ###-####. Notedstorage on top of mezz. above vault, no storage allowed, engineered for office load only(156psf.) Needs to remove storage or provide engineering showing that mezz. is capable of storge loads per IBC.
FIRE-Final Inspection12/16/201012/16/201012/16/2010PPASS
DetailsTroy Cobbley
life safety passed.
FIRE-Conference12/2/201012/9/201012/9/2010ADONE
DetailsTroy Cobbley
Per Tammy things should be complete soon.
FIRE-Conference12/2/201012/2/201012/2/2010PDONE
DetailsTroy Cobbley
I stopped at the project and spoke to Tammy about the need to get the building permit and the project related fire sprinkler permit finaled. I left a correction notice stating the above and also let her know that possibly an extension could be granted by Jennifer but that ultimately if the inspections were not finished I would be forwarding the permit information to a supervisor as per the aging permit policy. A follow up inspection has been set up for next week.
BLD-Aging Inspection11/18/201011/18/201011/24/2010 PEND
DetailsMike Jordan
FIRE-Conference4/22/20104/23/20104/23/2010ADONE
DetailsTroy Cobbley
I stopped at the job site and found that the restroom has been installed and stairs have been installed to the mezzanine both are lacking sprinkler protection. I spoke to Molli and Tammy about getting the permit finished.
BLD-Conference6/24/20086/24/20086/24/2008APASS
DetailsMike Jordan
Called and spoke with Tammy to inquire status of job. Tammy noted that they are almost completed. They are waiting for items that are on back order, but hoped to be completed fairly soon.
BLD-Final12/4/200712/4/200712/4/2007PNR
DetailsMike Jordan
molly Phone #: ###-####
FIRE-Final Inspection12/4/200712/4/200712/4/2007PPART
DetailsTroy Cobbley
Fire approval for temporary occupancy was given with dave hannimans permission until the restroom in the vault is complete and the mezzanine is complete.
BLD-Energy code compliance10/24/200710/25/200710/25/2007APASS
DetailsMike Jordan
tammy - please call 1/2 hr prior to inspection Phone #: ###-####. ok to cover
BLD-Framing/Rough-in10/15/200710/15/200710/15/2007PPASS
DetailsMike Jordan
Molly or Tammy Phone #: ###-####framing for offices in warehouse only. ok to insul.
BLD-Foundation9/12/20079/12/20079/12/2007PPART
DetailsMike Jordan
Dan; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. wip. Needs to add stirups over doorway.
BLD-Footing9/5/20079/5/20079/5/2007PPASS
DetailsMike Jordan
Molly; Phone #: ###-#### Internet Inspection Request from: Hattie James
Telephone call  8/7/2007 DONE
left vm for thomas whitworth at ###-#### - permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  8/7/2007 DONE
Issue PAID IN FULL permit  8/7/2007 DONE
Case Summary (BLD)  8/6/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  8/6/2007 DONE
Inspection Record Card- Bld  8/6/2007 DONE
Plan assigned to (R_H)6/29/2007 8/6/2007 PASS
8/6/2007 10:29:40 RMH - activity updated through activity BLDA022 from case BLD07-01561.
Plan resubmittals received  8/3/2007  
Received 1 cover transmittal, 3 copies of sheets A2-2, E1-0, E2-1L, E2-1P and taken to Ron Hill
Routing - FIRE7/20/2007 7/24/2007 PASS
Attached IFC review comments to plans.
1st review completed  7/24/2007 PASS
Case Summary (BLD)  7/20/2007 DONE
Routing - PLAN CHECK7/5/2007 7/20/2007 PASS
Routing - PLANNING7/2/2007 7/5/2007 PASS
Sarah Schafer DRH06-00084 (verify additional square footage for mezzanine) - Application is approved per the DR and the Conditional Use permit which allows for 40% office per building or 75% of office per tenant. (Application is only at 33.5% if mezzanine space is used for office.)
Routing - PUBLIC WORKS6/29/2007 7/2/2007 PASS
Routing PW Sewer Rating7/2/2007 7/2/2007 PASS
Pending Assignment by MYS6/19/2007 6/29/2007 DONE
6/29/2007 12:02:24 MYS - activity updated through activity BLDA175 from case BLD07-01561.
Plans ACCEPTED BY PLAN TECH  6/18/2007 DONE
Waited for Architect to bring in restroom elevations and key plan before process permit application and plans
Recd Pcfee & Taken To Pln CK  6/15/2007 DONE
Application received  6/15/2007  
Routing - PLAN CHECK7/24/2007