DOC - Permit Expired | 2/18/2011 | 2/18/2011 | 2/22/2011 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 2/18/2011 | 2/18/2011 | 2/18/2011 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 11/1/2010 | 11/1/2010 | 11/1/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 9/1/2010 | 9/1/2010 | 9/1/2010 | A | PASS |
Dave Hannah
|
|
|
work in progress
|
BLD-Aging Inspection | 9/1/2010 | 9/1/2010 | 9/1/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 7/1/2010 | 7/2/2010 | 7/2/2010 | P | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Aging Inspection | 5/5/2010 | 5/5/2010 | 5/5/2010 | | PASS |
Dave Hannah
|
|
|
work in progress
|
BLD-Aging Inspection | 3/1/2010 | 3/1/2010 | 3/1/2010 | | PASS |
Dave Hannah
|
|
|
work in progress
|
BLD-Aging Inspection | 12/28/2009 | 12/28/2009 | 12/28/2009 | | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 10/26/2009 | 10/27/2009 | 10/28/2009 | P | PART |
Dave Hannah
|
|
|
mike - between 1-3 if possible Phone #: ###-#### ok to insulate
|
BLD-Framing/Rough-in | 9/16/2009 | 9/17/2009 | 9/17/2009 | P | PART |
Dave Hannah
|
|
|
liza Phone #: ###-#### ok to start insulating up stairs but needs fire blocking and beam strapping also needs mec r/i
|
BLD-Framing/Rough-in | 8/13/2009 | 8/14/2009 | 8/14/2009 | A | FAIL |
Dave Hannah
|
|
|
michael Phone #: ###-#### needs seal package,truss engineering fire blocking straping on beams and short splice top plates
|
BLD-Energy code compliance | 7/23/2009 | 7/24/2009 | 7/24/2009 | P | CANC |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
BLD-Foundation | 5/5/2008 | 5/6/2008 | 5/6/2008 | A | PASS |
Dave Hannah
|
|
|
skip Phone #: ###-####
|
BLD-Footing | 4/28/2008 | 4/29/2008 | 4/29/2008 | A | PASS |
Dave Hannah
|
|
|
skip Phone #: ###-####
|
BLD-Footing | 4/24/2008 | 4/25/2008 | 4/25/2008 | A | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/24/2008 at 3:52:33 PM. Contact: ###-####. Left message at number provided. Noted NOT to place concrete in footings, No subgrade approval.
|
PubWorks Subgrade Approval | 4/25/2008 | 4/25/2008 | 4/25/2008 | | DONE |
Terry Records
|
|
|
Footing subgrade approved by the geotechnical engineer
|
BLD-Footing | 4/22/2008 | 4/23/2008 | 4/24/2008 | P | NR |
Dave Hannah
|
|
|
skip Phone #: ###-#### rebar ok but needs terrys signoff
|
Issue PAID IN FULL permit | | | 11/23/2007 | | DONE |
|
|
|
|
Telephone call | | | 11/6/2007 | | DONE |
|
|
|
left mess for john cook at ###-#### that permit is ready
|
Ready Permit EXTENDED | | | 9/26/2007 | | |
|
|
|
extend to 12/26/07
|
Case Summary (BLD) | | | 9/19/2007 | | |
|
|
|
|
Telephone call | | | 9/10/2007 | | DONE |
|
|
|
left mess for john cook at ###-#### that permit is ready
|
Plans ACCEPTED BY PLAN CHECK | | | 8/6/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/6/2007 | | DONE |
|
|
|
|
Telephone call | | | 8/6/2007 | | DONE |
|
|
|
tlk with perry and said not to worry about the $360 fee for the hillside from Terry
|
Telephone call | | | 8/6/2007 | | DONE |
|
|
|
t/c mike at ###-#### - permit ready and fees given - also need gc name and rce#
|
Permit Ready to Issue | | | 8/6/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/2/2007 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/2/2007 | | |
|
|
|
|
Routing - Erosion and Sediment | 6/27/2007 | | 6/28/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS GRADING | 6/27/2007 | | 6/27/2007 | | PASS |
|
|
|
Approved as Category 3
|
Routing Walk-In (Zoning) | 6/26/2007 | 6/26/2007 | 6/26/2007 | P | PASS |
|
|
|
|
Application received | | | 6/26/2007 | | |
|
|
|
|