Third Notice BLD | 10/30/2007 | 10/30/2007 | 3/12/2009 | | DONE |
Patricia Smith
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 10/1/2007 | 10/1/2007 | 10/30/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/20/2007 | 10/1/2007 | | DONE |
|
|
|
|
BLD-Final | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/19/2007 at 3:49:42 PM. Contact: ###-####. ok for perm occ
|
Permanent Occupancy UNPAID FEE | | | 9/20/2007 | | DONE |
|
|
|
|
BLD-Final | 9/18/2007 | 9/19/2007 | 9/19/2007 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/18/2007 at 12:28:13 PM. Contact: ###-####. Needs mech. final first.
|
FIRE-Final Inspection | 9/18/2007 | 9/18/2007 | 9/18/2007 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed, missing suite numbers to be installed per contractor agreement.
|
BLD-Framing/Rough-in | 9/5/2007 | 9/5/2007 | 9/5/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/5/2007 at 8:01:57 AM. Contact: ###-####.ceiling grid ok to cover after all other trades have oked
|
BLD-Energy code compliance | 8/7/2007 | 8/8/2007 | 8/8/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/7/2007 at 9:01:07 AM. Contact: ###-####.ok to cover
|
BLD-Energy code compliance | 8/3/2007 | 8/6/2007 | 8/7/2007 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/3/2007 at 10:46:28 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/3/2007 | 8/6/2007 | 8/7/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/3/2007 at 10:45:38 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 7/31/2007 | | |
|
|
|
|
Telephone call | | | 7/30/2007 | | DONE |
|
|
|
t/c w leeann at jordan-wilcomb const. ###-#### - gave her new fee amount after louise voided the sewer permit
|
Telephone call | | | 7/26/2007 | | DONE |
|
|
|
t/c w leeann at joran-wilcomb co. ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/26/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/23/2007 | | 7/25/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/25/2007 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 7/10/2007 | | 7/25/2007 | | PASS |
|
|
|
7/25/2007 10:22:58 RMH - activity updated through activity BLDA022 from case BLD07-01698.
|
Routing - FIRE | 7/19/2007 | | 7/23/2007 | | PASS |
|
|
|
Attached IFC Review comments to plans.
|
1st review completed | | | 7/23/2007 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/12/2007 | | 7/19/2007 | | PEND |
|
|
|
|
Case Summary (BLD) | | | 7/19/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/19/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/13/2007 | | |
|
|
|
Received cover transmittal and 3 copies of sheets A-1, P-1 and taken to Ron Hill
|
Routing - PLUMBING | 7/10/2007 | | 7/12/2007 | | N/A |
|
|
|
Per Tim Wilcomb they are removing sink, downgrading lab to an office. Plan removed from Plumbing by MSouthard and routed back to Ron Hill in Plan Review.
|
Telephone call | | | 7/12/2007 | | DONE |
|
|
|
Per Tim Wilcomb they are removing sink, downgrading lab to an office. Plan removed from Plumbing by MSouthard and routed back to Ron Hill in Plan Review. Tim W. to call architect to resubmit plans w/changes. Plans will then be hand carried by Ron Hill to PW Sewer Rating to change the fees. Marlene informed Tim W. that it would be acceptable for fire sprinkler and fire alarm plans to be submitted prior to permit issuance.
|
Routing PW Sewer Rating | 7/10/2007 | | 7/10/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/10/2007 | | 7/10/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 6/28/2007 | | 7/10/2007 | | DONE |
|
|
|
7/10/2007 08:22:10 MYS - activity updated through activity BLDA172 from case BLD07-01698.
|
Application received | | | 6/27/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/27/2007 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/27/2007 | | |
|
|
|
|