BLD-Final | 9/11/2007 | 9/11/2007 | 9/11/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/11/2007 at 9:34:10 AM. Contact: ###-####.
|
DOC - Permit Finaled | 9/11/2007 | 9/11/2007 | 9/11/2007 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 9/7/2007 | 9/10/2007 | 9/7/2007 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/7/2007 at 11:26:13 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Sep 7 2007 11:40AM.
|
BLD-Framing/Rough-in | 8/10/2007 | 8/10/2007 | 8/10/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/10/2007 at 9:57:32 AM.All framing issues resolved. Energy code ok.
|
BLD-Framing/Rough-in | 8/9/2007 | 8/9/2007 | 8/9/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/9/2007 at 8:20:46 AM. ok to insul. Needs to add strongback to gable end and add straps.
|
BLD-Framing/Rough-in | 8/8/2007 | 8/8/2007 | 8/8/2007 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/8/2007 at 8:55:33 AM. Need truss engineering to complete framing insp. Add studs under 2 ply girder truss. Add support to handstack to existing roof. Provide proper perm value for vapor barrier. Provide straps from new addition to existing.
|
BLD-Framing/Rough-in | 8/7/2007 | 8/7/2007 | 8/7/2007 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/7/2007 at 8:36:45 AM. Contact: ###-####. Needs to remove insul, complete airseal package prior to framing insp.
|
BLD-Framing/Rough-in | 7/31/2007 | 7/31/2007 | 7/31/2007 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/31/2007 at 10:24:14 AM. Contact: ###-####.
|
BLD-Footing | 7/31/2007 | 7/31/2007 | 7/31/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/31/2007 at 10:24:14 AM. Contact: ###-####.
|
BLD-Footing | 7/16/2007 | 7/16/2007 | 7/16/2007 | A | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/16/2007 at 7:19:11 AM. wip. not far enough along for insp.
|
Issue PAID IN FULL permit | | | 7/11/2007 | | |
|
|
|
|
Routing Walk-In (Zoning) | 7/10/2007 | 7/10/2007 | 7/10/2007 | P | DONE |
|
|
|
7/10/2007 15:02:56 DEM - activity updated through activity BLDI252 from case BLD07-01812.
|
Routing Walk-In (BLD) | 7/10/2007 | 7/10/2007 | 7/10/2007 | P | DONE |
|
|
|
7/10/2007 16:09:35 TLW - activity updated through activity BLDA022 from case BLD07-01812.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/10/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/10/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/10/2007 | | DONE |
|
|
|
|
Application received | | | 7/10/2007 | | |
|
|
|
|