Permit Information
Permit NumberBLD07-01972
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 12551 W EXECUTIVE DR
Project NameVAN AUKER WAREHOUSE
Customer Number 
ePlanReviewNo
Description
**(GEXPRO)**(VAN AUKER WAREHOUSE)** To remodel an eixsting 16,655 sq ft warehouse office space per approved plans. The remodel of the space will occur on the 3,100 sq ft mezzanine. And to add a 12 ' X 12' chain link trash enclosure on the exterior of building. Work will include, construction of nonbearing partitions to create an enclosed 504 sq ft office space and a 598 sq ft storage area, furr out exterior walls, insulate interior and exterior wall, install new HVAC Condensor and new ducting, installation of new lighting and switching, Miscellaneous related finishes. The building was constructed under BLD04-02121. The mezzanine was constructed under BLD05-00288. NO New racking over eight feet high shall be installed without a separate permit. This building is fully fire sprinklered ANY ALTERATIONS TO THE SPRINKLER SYSTEM WILL REQUIRE A SEPARATE PERMIT, and shall be installed and maintained per NFPA #13 as regulated by the fire department. RmH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD10/17/200710/17/200710/29/2007 DONE
First Notice has not been responded to.
First Notice 10/4/200710/17/2007 DONE
Permanent Occupancy UNPAID FEE  10/4/2007 DONE
BLD-Final10/2/200710/3/200710/3/2007PPASS
DetailsMike Jordan
jim Phone #: ###-####. ok for perm occ.
FIRE-Final Inspection9/28/200710/1/200710/1/2007APASS
DetailsTroy Cobbley
fire life safety passed
BLD-Energy code compliance9/14/20079/17/20079/17/2007PPASS
DetailsMike Jordan
jim Phone #: ###-####
BLD-Framing/Rough-in9/12/20079/13/20079/13/2007PPASS
DetailsMike Jordan
jim Phone #: ###-####. Interior framed walls on mezz. only.
Issue PAID IN FULL permit  8/31/2007 DONE
Permit Ready to Issue  8/30/2007 DONE
Telephone call  8/30/2007 DONE
Spoke with Gayle and told him that permit is ready & fees///8/30/07 @ 2:24pm BAS
Routing - PLAN CHECK8/9/2007 8/29/2007 PASS
1st review completed  8/29/2007  
Routing - FIRE8/29/2007 8/29/2007 PASS
Minor remodel / Field Verify
1st review completed  8/29/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  8/29/2007 DONE
Print Occupancy Form  8/29/2007 DONE
Plan assigned to (R_H)8/1/2007 8/29/2007 PASS
8/29/2007 08:57:38 RMH - activity updated through activity BLDA022 from case BLD07-01972.
Routing - PLAN CHECK8/9/2007 8/9/2007 PEND
Case Summary (BLD)  8/9/2007 DONE
Routing - Addressing8/9/2007 8/9/2007 PASS
Routing PW Sewer Rating8/9/2007 8/9/2007 PASS
Routing PW Solid Waste8/9/2007 8/9/2007 PASS
Routing - PUBLIC WORKS8/9/2007 8/9/2007 PASS
Pending Assignment by MYS7/30/2007 8/1/2007 DONE
8/1/2007 07:36:18 RMH - activity updated through activity BLDA175 from case BLD07-01972.
Plans ACCEPTED BY PLAN TECH  7/31/2007  
Application received  7/30/2007  
Recd Pcfee & Taken To Pln CK  7/30/2007