Permit Information
Permit NumberBLD07-01973
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 11575 W PRESIDENT DR
Project NameScafco Corporation
Customer Number 
ePlanReviewNo
Description
Scafco Corporation (Shell Only) - To construct a new 61,000 square foot, one story warehouse shell building and related site improvements. The building will be constructed of concrete tilt-up exterior walls, interior steel columns and steel roof joists. This building is fully fire sprinkled. The sprinklers are used for area increase. This is a shell permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD9/22/20089/22/20083/12/2009 DONE
DetailsAlexandra L. DeYoung
Second Notice has not been responded to.
Second Notice BLD8/11/20088/11/20089/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice4/18/20084/18/20088/11/2008 DONE
DetailsJim Sly
BLD-Final4/16/20084/18/20084/18/2008APASS
DetailsJim Sly
jim Phone #: ###-####
C/C issued
DOC - Permit Finaled4/18/20084/18/20084/18/2008PPASS
DetailsJim Sly
Code Occupancy Approval  4/18/2008 DONE
FIRE-Final Inspection4/10/20084/11/20084/11/2008APASS
DetailsTroy Cobbley
fire life safety passed
Code Occupancy Approval4/9/20084/9/20084/9/2008PPASS
DetailsJoe R Venneman
The shell meets requirements under BLD07-01973
BLD-Other12/27/200712/28/200712/28/2007APART
DetailsMike Jordan
jim Note: welding midmorning please Phone #: ###-####. wip on welding, will have special insp. also. Reviewed all special insp. reports to date.
BLD-Other11/30/200711/30/200711/30/2007PPART
DetailsMike Jordan
jim Note: welding Phone #: ###-####. welding on panel to footing connections. All welding will also have special insp.
BLD-Footing11/20/200711/21/200711/21/2007APART
DetailsMike Jordan
Jim Phone #: ###-####. wip, east perimeter footing.
BLD-Footing11/15/200711/16/200711/16/2007APASS
DetailsMike Jordan
jim Phone #: ###-####. perimeter footings, west side.
BLD-Framing/Rough-in11/13/200711/13/200711/13/2007PCANC
DetailsMike Jordan
Rebar inspection; Jim at ###-####
BLD-Footing11/8/200711/13/200711/13/2007APART
DetailsMike Jordan
jim Phone #: ###-####. loading dock wall, will have special insp on panels, All non conformances on last insp, were repaired as noted on special insp. report.
BLD-Footing11/8/200711/9/200711/9/2007APART
DetailsMike Jordan
jim Phone #: ###-####. rebar for tilt panels 1 to 12 and 20. Special insp. will document repairs on non conformances on report.
BLD-Footing11/8/200711/8/200711/8/2007PPASS
DetailsMike Jordan
jim Phone #: ###-####. Footings for loading dock.
BLD-Footing10/9/200710/10/200710/10/2007APART
DetailsMike Jordan
jim Phone #: ###-#### - as late as possible. wip on interior column pad footings. Noted that their will be special insp. Noted to contractor to get copies of all special insp. reports to date for review on next insp.
(F) Reprint permit  9/28/2007  
Issue PAID IN FULL permit  9/27/2007 DONE
(F) Reprint permit  9/20/2007 DONE
Telephone call  9/19/2007 DONE
t/c w jeff hull at ###-#### - permit ready and fees given
Permit Ready to Issue  9/19/2007 DONE
Routing - PLAN CHECK9/18/2007 9/18/2007 PASS
PLANS/APPL TAKEN TO FRONT DESK  9/18/2007 DONE
Inspection Record Card- Bld  9/18/2007 DONE
Routing - PUBLIC WORKS9/10/2007 9/18/2007 PASS
Plan assigned to (JCM)7/30/2007 9/18/2007 PASS
9/18/2007 13:19:39 JCM - activity updated through activity BLDA022 from case BLD07-01973.
Routing PW Drainage9/10/2007 9/17/2007 PASS
Routing PW Drainage8/1/2007 9/14/2007 PASS
DetailsBrian Murphy
Plan resubmittals received  9/12/2007  
Received transmittal, two copies of drainage calculations, and five copies of pages C-1, C-2, C-3, C-4, C-5, C-6; inserted into plans and taken back to Brian Murphy
Routing - PLANNING9/7/2007 9/10/2007 PASS
Routing - PLAN CHECK9/10/2007 9/10/2007  
Routing - FIRE9/5/2007 9/7/2007 PASS
Attached updated review comments to plans.
Plan Reviewer's activity  9/5/2007 PASS
Reviewed and approved structural and nonstructural revisions. JCM
Routing - PLAN CHECK8/13/2007 9/5/2007 PASS
Plan resubmittals received  8/23/2007  
received 1 letter of transmittal, 1 copy of sheet EN0.0 and 2 copys of sheets SP-1,S-1,C-5,S-1,S-1.1,S-2,S-4 taken to John M.
Meeting  8/20/2007 DONE
Visited site today and determined that because there are seven existing fire hydrants within resonable proximity to the proposed building; no new fire hydrant installation will be required. Contacted Gayle Jensen.
Routing PW Sewer Design  8/20/2007 PASS
Telephone call  8/17/2007 DONE
Spoke with Gayle Jensen regarding locations of new fire hydrants.
Plan resubmittals requested  8/14/2007 DONE
E-mailed the applicant with a copy of the structural plan review requesting revisioins. JCM
Routing Off Site - STRUCTURAL8/8/2007 8/14/2007 FAIL
CALLED ACTION COURIERS FOR PICK UP - Received comment list from consulting structural engineer requesting revisions.
1st review completed  8/13/2007 FAIL
Routing - FIRE8/8/2007 8/13/2007 FAIL
Faxed and emailed resubmittal items to design professional.
Routing - PLANNING8/8/2007 8/8/2007 FAIL
The applicant has not provided staff with documentation showing that the parcel is configured as one parcel.

The applicant should also submit a revised set of drawings to be inserted into the Design Review file.
Routing - PLUMBING8/3/2007 8/8/2007 PASS
Routing - PLAN CHECK8/8/2007 8/8/2007 FAIL
Plan resubmittals requested  8/8/2007 DONE
E-mailed the applicant and architect a copy of the plan review requesting revisions.
Routing PW Sewer Rating8/1/2007 8/3/2007 PASS
Routing PW Solid Waste8/1/2007 8/3/2007 PASS
Spoke with Gail Jensen (###-####) he will resolve issues.
Routing - Erosion and Sediment8/3/2007 8/3/2007 PASS
Routing - PUBLIC WORKS7/31/2007 8/3/2007 FAIL
Routing PW Sewer Rating8/3/2007 8/3/2007 PASS
Routing PW Sewer Design8/1/2007 8/2/2007 PASS
Routing PW Street Lights8/2/2007 8/2/2007 PASS
Plan Reviewer's activity  8/1/2007 FAIL
Reviewed plans and created plan review comment list. Waiting for plans to be routed to me to verify special inspections before sending list to the architect.
Routing - PLANNING Land Div7/31/2007 7/31/2007 PASS
Plans ACCEPTED BY PLAN TECH  7/31/2007  
Plan routing begun/NEW & ADDTN  7/31/2007  
Application received  7/30/2007