Third Notice BLD | 3/5/2008 | 3/5/2008 | 3/11/2008 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 2/6/2008 | 2/6/2008 | 3/5/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 1/14/2008 | 2/6/2008 | | DONE |
|
|
|
|
BLD-Final | 1/11/2008 | 1/14/2008 | 1/14/2008 | P | PASS |
Dave Hannah
|
|
|
brock Phone #: ###-#### ok for perm occ
|
BLD-Final | 1/9/2008 | 1/10/2008 | 1/14/2008 | P | NR |
Dave Hannah
|
|
|
brock Phone #: ###-####
|
FIRE-Final Inspection | 1/11/2008 | 1/14/2008 | 1/14/2008 | A | PASS |
Forrest France
|
|
|
Items on previous c/n are finished, one exit sign repaired while on site, fire life safety passed.
|
Permanent Occupancy | | | 1/14/2008 | | DONE |
|
|
|
|
BLD-Final | 1/10/2008 | 1/11/2008 | 1/11/2008 | P | NR |
Jim Sly
|
|
|
brock Phone #: ###-#### Need ACHD and fire finals
|
FIRE-Final Inspection | 1/10/2008 | 1/11/2008 | 1/11/2008 | A | FAIL |
Forrest France
|
|
|
Need to provide missing exit signs at three locations per plan annotations sheet E100, remove tape and paper covering at the FACP SD, need project related fire sprinkler and BLD shell permit finals.
|
Code Occupancy Approval | 1/11/2008 | 1/11/2008 | 1/11/2008 | P | PASS |
Joe R Venneman
|
|
|
|
Code Occupancy Approval | | | 1/11/2008 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/10/2008 | 1/10/2008 | 1/10/2008 | P | NR |
Forrest France
|
|
|
brock - fire life safety Phone #: ###-####
|
BLD-Final | 1/8/2008 | 1/9/2008 | 1/9/2008 | P | CANC |
Dave Hannah
|
|
|
brock Phone #: ###-#### needs other trades finaled first
|
FIRE-Conference | 1/7/2008 | 1/8/2008 | 1/8/2008 | A | DONE |
Forrest France
|
|
|
On site visit regarding fire alarm work and project fire life safety requirements, also discussed inspection scheduling.
|
BLD-Framing/Rough-in | 12/13/2007 | 12/14/2007 | 12/14/2007 | P | PART |
Dave Hannah
|
|
|
tim Note: part framing/supsended dry wall ceiling insp/t-bar ceiling inspecting Phone #: ###-#### front show case area and hard lid ok to cover
|
BLD-Framing/Rough-in | 12/7/2007 | 12/7/2007 | 12/10/2007 | P | PART |
Dave Hannah
|
|
|
brock Phone #: ###-#### small inter wall ne corner
|
BLD-Framing/Rough-in | 11/21/2007 | 11/21/2007 | 11/21/2007 | P | PART |
Tom Arcoraci
|
|
|
brock Phone #: ###-#### dressing room wall ok entry soffiet ok and west concealed space ok for cover
|
BLD-Framing/Rough-in | 11/13/2007 | 11/13/2007 | 11/14/2007 | P | PART |
Dave Hannah
|
|
|
Brock; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok to cover walls
|
BLD-Framing/Rough-in | 10/29/2007 | 10/29/2007 | 10/29/2007 | P | PART |
Dave Hannah
|
|
|
brock-- ###-#### ok to cover west wall
|
Issue PAID IN FULL permit | | | 10/29/2007 | | DONE |
|
|
|
|
Telephone call | | | 10/16/2007 | | DONE |
|
|
|
t/c w sara at ###-#### - permit ready and fees given - also need rp name and ACHD receipt
|
Permit Ready to Issue | | | 10/16/2007 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/9/2007 | | 10/15/2007 | | PASS |
|
|
|
10/15/2007 15:19:46 CJW - activity updated through activity BLDA022 from case BLD07-02015.
|
Routing - PLAN CHECK | 10/8/2007 | | 10/15/2007 | | PASS |
|
|
|
Drawings approved after the resubmittal review.
|
Routing - PUBLIC WORKS | 10/15/2007 | | 10/15/2007 | | DONE |
|
|
|
Sent back for drinking fountain sewer fees.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/15/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/10/2007 | | |
|
|
|
received 1 transmittal,and 2 copies of sheets A100,A103,A104,A200,A202,A403,A404,A405,A700,A800,P100,P101,P200,P400,M100,M101,M200,E100,E200 taken to Carl W.
|
Routing - FIRE | 10/2/2007 | | 10/8/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
1st review completed | | | 10/8/2007 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/14/2007 | | 10/2/2007 | | FAIL |
|
|
|
The IBC plan review was started on September 25, 2007 and finished on October 2, 2007. Revised drawings were required. See the plan review report.
|
Plan resubmittals received | | | 9/11/2007 | | |
|
|
|
Received revised cert of value to break out demo into seperate permit Bld07-02453; taken to Carl W.
|
Routing - PLANNING | 8/13/2007 | | 8/14/2007 | | PASS |
|
|
|
Sarah Schafer DRH07-00321Approved per the DR.
|
Routing - Erosion and Sediment | 8/10/2007 | | 8/13/2007 | | PASS |
|
|
|
ESC wavier request approved with attached conditions.
|
Routing - PUBLIC WORKS | 8/9/2007 | | 8/10/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 8/3/2007 | | 8/9/2007 | | DONE |
|
|
|
8/9/2007 08:33:03 MYS - activity updated through activity BLDA172 from case BLD07-02015.
|
Routing - Addressing | 8/9/2007 | | 8/9/2007 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/3/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/3/2007 | | DONE |
|
|
|
|
Application received | | | 8/2/2007 | | |
|
|
|
|