Permit Information
Permit NumberBLD07-02060
StatusExpired
Name STEED CONSTRUCTION
Site Address 10369 W EMERALD ST
Project NameEmerald Tech Bldg #11
Customer Number 
ePlanReviewNo
Description
(RS HOSAC - EMERALD TECH CENTER BLDG #11) This building is fire sprinklered. To construct a 3,792 square foot office (2,462 square feet) and storage (1,330 square feet) tenant space. Work is to include 2 restrooms accessible to the disabled, interior nonbearing walls, suspended acoustical ceilings, suspended gypsum board ceilings, interior doors and windows, storefront doors and windows, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection12/10/200912/10/200912/10/2009PDONE
DetailsMike Jordan
Barbara-please let me know the status of this project is it to be expired???? Phone #: ###-####
BLD-Aging Inspection12/4/200912/7/200912/7/2009ACANC
DetailsMike Jordan
Should this be expired? Barbara Phone #: ###-####
BLD-Conference1/22/20081/23/20081/23/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 1/22/2008 at 4:28:57 PM. Contact: ###-####.
BLD-Energy code compliance1/15/20081/16/20081/16/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 1/15/2008 at 2:51:58 PM. Contact: ###-####.
BLD-Framing/Rough-in1/11/20081/14/20081/14/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 1/11/2008 at 1:05:21 PM. Contact: ###-####. ok to rock interior walls only.
Issue PAID IN FULL permit  11/26/2007  
Telephone call  11/6/2007 DONE
left message w teresa for bob hosac at ###-#### - permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  11/6/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  11/5/2007 DONE
Print Occupancy Form  11/5/2007 DONE
Routing - PLAN CHECK10/11/2007 11/5/2007 PASS
(10-19-07) Completed the resubmittal review. Further plan revisions were required. See the 2nd plan review report. (11-5-07) Completed the 2nd resubmittal review. Drawings approved with "red lines". CJW
Plan assigned to (CJW)8/25/2007 11/5/2007 PASS
11/5/2007 15:50:58 CJW - activity updated through activity BLDA022 from case BLD07-02060.
Plan resubmittals received  10/31/2007  
received document transmittal from habitec & "2" sets of plans with each sheet A2.1 & A3.1- plans taken to Carl Westfall
Plan resubmittals received  10/15/2007  
received 1 teansmittal , and 2 copys of sheets A2.1,A3.1 taken to Carl W.
1st review completed  10/11/2007 FAIL
Routing - FIRE10/9/2007 10/11/2007 PASS
Attached IFC review comments to plans.
Routing - PLAN CHECK8/29/2007 10/9/2007 FAIL
The IBC plan review was started on October 8, 2007 and was finished the next day. Revised drawings were required. See the plan review report.
Routing - PLANNING8/27/2007 8/29/2007 PASS
Sarah Schafer. Office use in M-1D zone. Routed to Josh Wilson for Compliance with CUP06-00101. 8/27/07
Routing - PUBLIC WORKS8/25/2007 8/27/2007 PASS
Routing PW Sewer Rating8/27/2007 8/27/2007 PASS
Pending Assignment by MYS8/8/2007 8/25/2007 DONE
8/25/2007 13:32:54 MYS - activity updated through activity BLDA172 from case BLD07-02060.
Plans ACCEPTED BY PLAN TECH  8/8/2007  
Recd Pcfee & Taken To Pln CK  8/8/2007 DONE
Application received  8/7/2007