Permit Information
Permit NumberBLD07-02067
StatusFinaled
Name BIG D BUILDERS
Site Address 6418 W GOWEN RD
Project NameCATE EQUIPMENT
Customer Number 
ePlanReviewNo
Description
Cate Equipment - To construct a new 14,715 square foot, two story, pre-engineered metal heavy equipment repair garage and related site improvements. This building contains a heavy equipment repair garage, parts storage area, equipment storage, administrative office areas and an outside wash bay area. This building is fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD9/22/20089/22/200812/22/2008 DONE
DetailsCathy Brown
This permit finaled on the web by Danielle Groat
Second Notice BLD8/11/20088/11/20089/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 6/10/20088/11/2008 DONE
Meeting  7/23/2008 DONE
Meeting with Jay Lungren, GM, Cate Idaho Equipment, (###-####) regarding proposed storage on racks. they will eliminate the top horizontal rack beam so highest beam will be at below 8', to eliminate seisic design requirements. Overall storage height to be maintained at less than 12' high, with signs posted at top of rack uprigts (12' high) indicating "No storage above this level"; to eliminate HP storage requirements. Sprinkler system is reportedly designed for OH 2, 0.20gpm/sf/over 1500sf area.
Permanent Occupancy UNPAID FEE  6/10/2008  
BLD-Final6/4/20086/5/20086/5/2008PPASS
DetailsJim Storey
Kevin Phone #: ###-#### final ok
FIRE-Final Inspection6/4/20086/5/20086/5/2008APASS
DetailsTroy Cobbley
fire life saftey passed
FIRE-Final Inspection6/3/20086/4/20086/4/2008PFAIL
DetailsTroy Cobbley
Needs the project related fire alarm and fire sprinkler permits finaled prior to this inspection. Contractor and I discussed the fire dept access requirements.
BLD-Conference6/2/20086/3/20086/3/2008APART
DetailsJim Storey
kevin Phone #: ###-#### only one locking door at entry/ remove flush bolts on office inactive leaf/ sink must be 34 max height/ protect trap under sink.
PubWorks Occupancy Approval6/6/20086/6/20086/3/2008 DONE
Signed final occupancy 06/03/08 R. Rokovitz.
Code Occupancy Approval6/2/20086/2/20086/2/2008PPASS
DetailsWm. Michael Meloy
Compliance met
FIRE-Final Inspection5/30/20086/2/20086/2/2008PCANC
DetailsTroy Cobbley
kevin - fire life safety Phone #: ###-#### Inspection cancelled from web by: Patricia Smith
BLD-Framing/Rough-in4/24/20084/25/20084/25/2008PPASS
DetailsJim Storey
ceiling grid Phone #: ###-####
BLD-Energy code compliance3/26/20083/27/20083/27/2008APASS
DetailsJim Storey
kevin Phone #: ###-####
BLD-Framing/Rough-in3/20/20083/21/20083/21/2008PPART
DetailsTom Arcoraci
kevin - call if you are going to be later than 3:30 Phone #: ###-#### west side ok
Plan resubmittals received  3/21/2008  
Received 1 cover transmittal and 2 copies of sheets C1.0 & C2.0 and taken to Scott Arellano 3-21-08 @ 9:34am BAS
Telephone call  3/21/2008 DONE
Left voice message for Dennis Montgomery at Treasure Valley Engineers that stamped and approved set of plans need picked up///3-21-08 @ 12:25pm BAS
Plan resubmittals received  3/21/2008 DONE
Received plan modification reflecting the removal of the FD vehicle turnaround from plan sheet C1.0 & C2.0. Delivered one set of plan sheet C1.0 and C2.0 to records; issued the field set to Treasure Valley Engineers.
Meeting  3/20/2008 DONE
Met with Mark Senteno regarding the removal of the required FD vehicle access turnaround. Captain Senteno has determined that the combination of ample yard space with compact gravel surfacing material able to support the fire apparatus and the initial driveway turnaround will satisy Fire Department concerns.
BLD-Other3/5/20083/5/20083/6/2008PPASS
DetailsJim Storey
rick Note: cover Phone #: ###-#### exterior sheathing ok to cover.
BLD-Aging Inspection2/14/20082/14/20082/14/2008 PASS
DetailsJim Storey
foundiation and steel ereaction completed with si at this time pending review of the reports at framing insp to be requisted when ready.
(F) Reprint permit  11/16/2007  
Issue PAID IN FULL permit  11/15/2007 DONE
Print Occupancy Form  11/14/2007 DONE
Telephone call  11/14/2007 DONE
left message w sandy for rick bugatsch at ###-#### - permit ready and fees given - also need ACHD receipt
Permit Ready to Issue  11/14/2007 DONE
Plan resubmittals received  11/13/2007  
Received 1 cover letter, 1 response letter from Rick Bugatsch dated 11/13/07, 2 copies of sheets A1 & A3 inserted into plans by Houston Bugatsch office and taken back to John Menard///11/13/07 @ 1:31pm BAS
Plan Reviewer's activity  11/13/2007 PASS
Reviewed and approved nonstructural revisions. JCM
PLANS/APPL TAKEN TO FRONT DESK  11/13/2007 DONE
Routing - PLAN CHECK10/17/2007 11/13/2007 PASS
Plan assigned to (JCM)8/13/2007 11/13/2007 PASS
11/13/2007 14:38:41 JCM - activity updated through activity BLDA022 from case BLD07-02067.
Plan resubmittals received  11/5/2007  
Received 1 cover transmittal, 1 plan review responce letter dated 11/1/07 from Rick Bugatsch, 2 copies of the following sheets- A1, A2,A3, A5, M3.0, M3.1, E2.0, E3.0 and inserted into plans by Joshua Houston from the Architects office on 11/5/07 @ 8:21am and taken back to John's desk
Plan Reviewer's activity  11/5/2007 PASS
Reviewed and approved structural responses. JCM
Plan resubmittals requested  11/5/2007 DONE
Routing - FIRE10/15/2007 10/17/2007 PASS
Attached updated IFC review comments to plans.
Routing - PUBLIC WORKS10/9/2007 10/15/2007 PASS
Routing PW Drainage10/10/2007 10/15/2007 PASS
Routing - PLAN CHECK9/19/2007 10/9/2007  
Plan resubmittals received  10/5/2007  
received transmittal letter from treasure valley engineers & united water map, (8) pages of fire code review---also "2" sheets each of C1.OC1.1, C2.O, C3.O--plans taken back to John Menard
1st review completed  9/19/2007 FAIL
Routing - FIRE9/14/2007 9/19/2007 FAIL
Faxed and emailed review resubmittal items to architect.
Routing - PLAN CHECK8/27/2007 9/14/2007 FAIL
John Menard
Plan resubmittals requested  9/14/2007 DONE
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PLANNING8/21/2007 8/24/2007 PASS
Approved per DRH07-00078 and routed to Diane Perkins for review for teh associated CU. ANT
CUP07-00065 - PASS - DCP, routed to plan check 8/24/07
Routing Off Site - STRUCTURAL8/14/2007 8/23/2007 FAIL
Received comment list from the consulting structural engineer requesting revisions. JCM
Plan resubmittals requested  8/23/2007 DONE
Faxed the architect a copy of the structural plan review requesting revisions.
Routing - PLUMBING8/21/2007 8/21/2007 PASS
water piping to P-8s in the garage and the make up water to the boiler must be protected by an r.p..
Routing - Erosion and Sediment8/20/2007 8/21/2007 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS8/14/2007 8/20/2007 FAIL
Routing PW Drainage8/14/2007 8/20/2007 FAIL
DetailsBrian Murphy
WASH PAD CONNECTED TO STORMWATER SYSTEM
Routing PW Sewer Rating8/14/2007 8/20/2007 PASS
Routing PW Solid Waste8/14/2007 8/20/2007 PASS
Routing PW Sewer Design8/14/2007 8/16/2007 PASS
Routing PW Street Lights8/14/2007 8/16/2007 PASS
Routing - PLANNING Land Div8/14/2007 8/14/2007 PASS
Plans ACCEPTED BY PLAN TECH  8/14/2007  
Plan routing begun/NEW & ADDTN  8/14/2007  
Pending Assignment by MYS8/8/2007 8/13/2007 DONE
8/13/2007 08:17:44 JCM - activity updated through activity BLDA166 from case BLD07-02067.
Recd Pcfee & Taken To Pln CK  8/8/2007 DONE
Application received  8/8/2007