BLD-Aging Inspection | 11/25/2009 | 11/25/2009 | 11/30/2009 | P | PASS |
Dave Hannah
|
|
|
Terry Records is wanting to know the status on this- Thanks Barb Phone #: ###-####
|
DOC - Permit Expired | 11/30/2009 | 11/30/2009 | 11/30/2009 | P | PASS |
Dave Hannah
|
|
|
Terry Records is wanting to know the status on this- Thanks Barb Phone #: ###-#### This project is not going to be built
|
Extend Permit 180 days | | 5/13/2008 | 6/18/2008 | | DONE |
Jenifer Gilliland
|
|
|
Extended permit. Received request for extension. Permit OK for another 180 days beginning 5-13-2008. jlg.
|
Telephone call | | | 6/6/2008 | | DONE |
Jason Blais
|
|
|
Discussed the expiration of the permit with Tom Zabala. Tom said he will provide a letter to the Building Division Manager requesting the permit be extended.
|
DOC-Permit Expired | 5/13/2008 | 5/13/2008 | 5/13/2008 | | DONE |
Dave Hannah
|
|
|
Permit expired by limitations.
|
BLD-Aging Inspection | 2/7/2008 | 2/7/2008 | 2/7/2008 | | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 2/7/2008 | 2/7/2008 | 2/7/2008 | P | PASS |
Dave Hannah
|
|
|
work will start in spring
|
Issue & PRINT to be Invoiced | | | 11/8/2007 | | DONE |
|
|
|
|
Telephone call | | | 11/5/2007 | | DONE |
|
|
|
left mess for curtis w. at ###-#### that permit is ready
|
Inspection Record Card- Bld | | | 10/2/2007 | | DONE |
|
|
|
|
Telephone call | | | 10/2/2007 | | DONE |
|
|
|
t/c w lowell at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/2/2007 | | DONE |
|
|
|
|
Routing - FIRE | 9/27/2007 | | 10/1/2007 | | PASS |
|
|
|
Attached updated IFC review comments to building plans.
|
Routing - PLAN CHECK | 10/1/2007 | | 10/1/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2007 | | DONE |
|
|
|
|
Plan assigned to (MYS) | 9/21/2007 | | 10/1/2007 | | PASS |
|
|
|
10/1/2007 15:55:23 MYS - activity updated through activity BLDA022 from case BLD07-02127.
|
Routing PW Sewer Rating | 9/26/2007 | | 9/27/2007 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/27/2007 | | 9/27/2007 | | PEND |
|
|
|
Resubmittal sheets C-100 inserted and plans to route back to Fire for review.
|
1st review completed | | | 9/26/2007 | | FAIL |
|
|
|
|
Routing PW Drainage | 9/26/2007 | | 9/26/2007 | | PASS |
|
|
|
|
Routing - FIRE | 9/21/2007 | | 9/26/2007 | | FAIL |
|
|
|
Emailed and faxed resubmittal item to Tom Zabala.
|
Pending Assignment by MYS | 8/14/2007 | | 9/21/2007 | | DONE |
|
|
|
9/21/2007 08:51:37 MYS - activity updated through activity BLDA165 from case BLD07-02127.
|
Routing - PLAN CHECK | 9/6/2007 | | 9/21/2007 | | PEND |
|
|
|
9/21/2007 - Reviewed and passed for building code compliance. Routed to Fire. Upon approval from others, permit can be issued.
|
Routing - PLANNING | 8/30/2007 | | 9/6/2007 | | PASS |
|
|
|
Grading and Drainage ONLY!
Approved per DRH07-00164.
|
Routing - Erosion and Sediment | 8/28/2007 | | 8/29/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLUMBING | 8/29/2007 | | 8/29/2007 | | PASS |
|
|
|
site work per plans and 2003 upc
|
Plan resubmittals received | | | 8/28/2007 | | |
|
|
|
received letter of transmittal from zga & shoring calculations (26) sheets. also "1" set of plans including C-OO1, C-OO2, C-100, C-101, C-2OO, C-2O1, C-3OO, C-4OO, C-5OO, C-6OO, C-6O1, LO.1, L1.O, ES-OO1, SH-1O1, SH-1O2, & SH-1O3- plans taken to Jason Blais
|
Routing PW Sewer Design | 8/16/2007 | | 8/28/2007 | | PASS |
|
|
|
|
Routing PW Street Lights | 8/28/2007 | | 8/28/2007 | | PASS |
|
|
|
|
Routing PW Sewer Rating | 8/16/2007 | | 8/28/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/16/2007 | | 8/28/2007 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 8/24/2007 | | |
|
|
|
Received transmittal, two copies of shoreing calcs, and two copies of pages C-001, C-101, SH-101, SH-102, SH-103; taken to Jason Blais per his request
|
Routing PW Drainage | 8/16/2007 | | 8/17/2007 | | FAIL |
Brian Murphy
|
|
|
Are drywells seepage beds?
|
Routing - PLANNING Land Div | 8/16/2007 | | 8/16/2007 | | PASS |
|
|
|
Grading and drainage only permit
|
Plans ACCEPTED BY PLAN TECH | | | 8/16/2007 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/16/2007 | | |
|
|
|
|
Application received | | | 8/14/2007 | | |
|
|
|
|