BLD-Final | 10/19/2007 | 10/22/2007 | 10/22/2007 | P | PASS |
Dave Hannah
|
|
|
john Phone #: ###-####
|
DOC - Permit Finaled | 10/22/2007 | 10/22/2007 | 10/22/2007 | P | PASS |
Dave Hannah
|
|
|
|
Code Occupancy Approval | 10/22/2007 | 10/22/2007 | 10/22/2007 | P | PASS |
Michael Garner
|
|
|
site inspection complete - construction completed according to approved plans - only task left is the attachment of columns - Mr. Tillman showed me the ordered columns, including receipt for purchase - they are on back order - PASS
|
BLD-Framing/Rough-in | 8/28/2007 | 8/28/2007 | 8/28/2007 | P | PASS |
Mike Jordan
|
|
|
John; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt.
|
BLD-Framing/Rough-in | 8/23/2007 | 8/24/2007 | 8/24/2007 | A | PART |
Jim Sly
|
|
|
john - post hole depth - please call 1/2 hr prior to inspection Phone #: ###-#### Footings...OK
|
Routing Walk-In (Zoning) | 8/15/2007 | 8/15/2007 | 8/15/2007 | A | DONE |
|
|
|
8/15/2007 10:02:54 JGW - activity updated through activity BLDI252 from case BLD07-02146.
|
Routing Walk-In (BLD) | 8/15/2007 | 8/15/2007 | 8/15/2007 | A | DONE |
|
|
|
8/15/2007 12:09:02 PEP - activity updated through activity BLDA022 from case BLD07-02146.
|
Case Summary (BLD) | | | 8/15/2007 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/15/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2007 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/15/2007 | | DONE |
|
|
|
|
Application received | | | 8/15/2007 | | |
|
|
|
|