First Notice | | 8/5/2008 | 8/5/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 8/5/2008 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 7/30/2008 | 7/31/2008 | 7/31/2008 | A | PASS |
Tom Arcoraci
|
|
|
steve Phone #: ###-####
|
FIRE-Final Inspection | 7/30/2008 | 7/30/2008 | 7/30/2008 | P | PASS |
Troy Cobbley
|
|
|
fire life safety passed
|
FIRE-Final Inspection | 7/28/2008 | 7/28/2008 | 7/29/2008 | P | FAIL |
Troy Cobbley
|
|
|
No approved plans on site. I went ahead and tested the smoke alarms and verified the placement of the fire extinguishers. Besides needing the approved plans on site the contractor needs to provide a building address on the street side of the building.
|
BLD-Final | 7/25/2008 | 7/28/2008 | 7/28/2008 | A | NR |
Tom Arcoraci
|
|
|
Steve Phone #: ###-####
|
PubWorks Occupancy Approval | 8/4/2008 | 8/4/2008 | 7/25/2008 | | DONE |
|
|
|
Inspection completed by R. Anderson
|
BLD-Aging Inspection | 7/24/2008 | 7/24/2008 | 7/24/2008 | | PASS |
Tom Arcoraci
|
|
|
|
Code Occupancy Approval | | | 7/24/2008 | | PASS |
|
|
|
Meets and exceeds compliance with CUP06-00019. Pass.
|
BLD-Energy code compliance | 2/29/2008 | 2/29/2008 | 2/29/2008 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/29/2008 at 8:56:32 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/27/2008 | 2/27/2008 | 2/27/2008 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/27/2008 at 10:36:29 AM. Contact: ###-####.
|
BLD-Wall cover | 1/14/2008 | 1/15/2008 | 1/15/2008 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/14/2008 at 2:34:22 PM. Contact: ###-####.
|
BLD-Footing | 12/18/2007 | 12/18/2007 | 12/18/2007 | P | PASS |
Tom Arcoraci
|
|
|
paul Phone #: ###-####
|
BLD-Foundation | 10/3/2007 | 10/3/2007 | 10/3/2007 | P | PASS |
Tom Arcoraci
|
|
|
blue board insulation inspection for the foundation//Paul; Phone #: ###-#### Internet Inspection Request from: Letitia Gallop
|
BLD-Foundation | 9/21/2007 | 9/24/2007 | 9/24/2007 | P | PASS |
Tom Arcoraci
|
|
|
matt Phone #: ###-####
|
BLD-Footing | 9/20/2007 | 9/21/2007 | 9/21/2007 | P | PASS |
Tom Arcoraci
|
|
|
matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/19/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/17/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/17/2007 | | DONE |
|
|
|
faxed to Eldorado steve ###-#### 1:40 pm
|
Permit Ready to Issue | | | 9/17/2007 | | |
|
|
|
|
Plan assigned to (SRZ) | 8/24/2007 | 8/24/2007 | 9/13/2007 | | PASS |
|
|
|
9/13/2007 14:08:16 SRZ - activity updated through activity BLDA022 from case BLD07-02280.
|
Routing - Erosion and Sediment | 9/13/2007 | | 9/13/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLAN CHECK | 9/13/2007 | | 9/13/2007 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/13/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/13/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/12/2007 | | |
|
|
|
Received 2 copies of A3 and inserted into plans and plans given to back to Sam Zahorka////9/12/07 BAS
|
Routing PW Solid Waste | 9/12/2007 | | 9/12/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/12/2007 | | 9/12/2007 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/11/2007 | | 9/12/2007 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 9/11/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 9/6/2007 | | 9/11/2007 | | PEND |
|
|
|
Waiting for others to pass. (SRZ)
|
1st review completed | | | 9/6/2007 | | FAIL |
|
|
|
|
Routing - FIRE | 9/4/2007 | | 9/6/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
Routing - PLANNING | 8/30/2007 | | 9/4/2007 | | PASS |
|
|
|
Susan R. cup06-00019
|
Routing - PLUMBING | 8/29/2007 | | 8/30/2007 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - Erosion and Sediment | 8/28/2007 | | 8/29/2007 | | PASS |
|
|
|
ESC plan failed. No full size set of ESC drawings included with submittal. Contacted PD.
|
Routing - PUBLIC WORKS | 8/27/2007 | | 8/28/2007 | | FAIL |
|
|
|
|
Routing PW Drainage | 8/27/2007 | | 8/28/2007 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 8/27/2007 | | 8/28/2007 | | PASS |
|
|
|
|
Routing PW Sewer Rating | 8/27/2007 | | 8/28/2007 | | PASS |
|
|
|
|
Routing PW Solid Waste | 8/27/2007 | | 8/28/2007 | | FAIL |
|
|
|
No access for front loading truck to trash containers in alley.
Peter McCullough ###-####
|
Routing - PLANNING Land Div | 8/23/2007 | | 8/27/2007 | | PASS |
|
|
|
|
Plan assigned to (M_P) | 8/22/2007 | 8/22/2007 | 8/24/2007 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/22/2007 | | |
|
|
|
|
Application received | | | 8/22/2007 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/22/2007 | | |
|
|
|
|