Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD07-02290
StatusFinaled
Name ROBERT C BIVIN
Site Address 3507 N MAPLE GROVE RD
Project NameRobert Bivin 4 plex
Customer Number 
ePlanReviewNo
Description
(Bob Bivin Four Plex) To construct a new 3,700 sq.ft. two story, four unit apartment building, each unit is two bedrooms, has a separate entry, and is two stories. The Type "B" units have one option "B" bathroom and a half bath. They are 925 sq.ft. and located at grade level. The two up-stair units are not required to be accessible and are also 925 sq.ft.the. All construction per the approved plans and attached comment list. Section 4-02-31 of Boise City Code was used to determine compliance with fire sprinkler requirements. **TLW**DRH07-00196-Sarah Shafer CUP06-00120-Greg Johnson
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  4/14/2009 DONE
Zoning Approval4/9/20094/9/20094/9/2009 PASS
DetailsJosh Wilson
Landscaping is complete and bond can be released.
BLD-Final2/27/20093/2/20093/2/2009ADONE
DetailsJim Sly
Bob Phone #: ###-####
Previously parted.
BLD-Final2/27/20092/27/20092/27/2009PPART
DetailsJim Sly
OK for Temp Occ. OK for Perm Occ when Zoning and ESC Perms (bond for Landscaping).
FIRE-Final Inspection2/27/20092/27/20092/27/2009PPASS
DetailsTroy Cobbley
life safety passed
Temporary Occupancy2/27/20095/28/20092/27/2009 DONE
DetailsTisha Gallop
FIRE-Final Inspection2/26/20092/26/20092/26/2009PFAIL
DetailsTroy Cobbley
The door hardware was not completely installed and the door were locked to the apartments. The contractor was not on site. No inspection was performed.
FIRE-Final Inspection2/23/20092/23/20092/23/2009PFAIL
DetailsTroy Cobbley
Provide self closing exit doors to the common exit doors and provide the apartment numbers.
PubWorks Occupancy Approval2/24/20092/24/20092/23/2009 DONE
Final PW sign off by R. Rokovitz.
Zoning Approval Temp2/17/20092/17/20092/17/2009 PASS
DetailsJosh Wilson
Ok for temporary occupancy- $7,150.00 bond for landscaping is in place- BND09-00014
BLD-Energy code compliance11/4/200811/5/200811/5/2008APASS
DetailsJim Sly
bob Phone #: ###-####
BLD-Conference10/31/200810/31/200810/31/2008PDONE
DetailsJim Sly
Kelly Phone #: ###-####
C/N Architect to provide detail for stairs and all components.
BLD-Framing/Rough-in10/28/200810/28/200810/28/2008PPASS
DetailsJim Sly
bob Phone #: ###-####
BLD-Conference10/3/200810/3/200810/3/2008PDONE
DetailsJim Sly
bob- ###-####
Met with Bob......Went over firestopping issues.
BLD-Conference8/28/20089/2/20089/2/2008ADONE
DetailsJim Sly
bob Phone #: ###-####
BLD-Conference8/21/20088/22/20088/22/2008ADONE
DetailsJim Sly
joe Phone #: ###-####
BLD-Foundation7/30/20087/31/20087/31/2008APASS
DetailsJim Sly
Mr. Bivins Note: pour at noon - be ready early Phone #: ###-####
BLD-Footing7/28/20087/29/20087/29/2008APASS
DetailsMike Jordan
richard Phone #: ###-####. perimeter and interior footings ok. Need additional info on straps and interior column pad footings.
Issue PAID IN FULL permit  7/21/2008 DONE
Telephone call  6/5/2008  
bob bivins at ###-#### - permit ready and fees given -
(F) Reprint permit  2/25/2008  
Ready Permit EXTENDED  2/5/2008  
Routing - PLAN CHECK1/2/2008 1/3/2008 PASS
DetailsTim L. Woodard
Passed per redlines, approved plans, and plan review report. TLW
PLANS/APPL TAKEN TO FRONT DESK  1/3/2008 DONE
Print Occupancy Form  1/3/2008 DONE
Telephone call  1/3/2008 DONE
bob bivins at ###-#### - permit ready and fees given -
Permit Ready to Issue  1/3/2008 DONE
Plan assigned to (TLW)9/6/2007 1/3/2008 DONE
DetailsTim L. Woodard
Corrections sent to architect @ rchd_llc@hotmail.com 9-17-07 tlw.
Routing - FIRE12/27/2007 1/2/2008 PASS
DetailsScott Arellano
Attached updated IFC comments to plans
Routing PW Drainage12/3/2007 12/19/2007 PASS
Routing - PUBLIC WORKS12/19/2007 12/19/2007 PASS
Plan resubmittals received  11/30/2007  
Received response letter and five copies of civil pages 1,2, 3, 4,; inserted by arch rep and taken back to Tim W.
Routing - FIRE10/16/2007 10/19/2007 FAIL
Emailed and faxed resubmittal item to architect. Attached revised IFC comments to plans.
Routing - PLAN CHECK9/20/2007 10/16/2007 FAIL
Corrections 15 and 16 not addressed on plans. TLW
Plan resubmittals received  10/12/2007  
Received response letter to Scott A., response letter to Tim W., United Water flow sheet, and two copies of pages A0.5, A0.7, A2.0, A2.1, A2.2, A4.1, A4.2, M1.0; inserted by arch rep and plans taken back to Tim W.
1st review completed  9/20/2007 FAIL
Routing - FIRE9/17/2007 9/20/2007 FAIL
Faxed and emailed resubmittal items to architect.
Routing - PLAN CHECK9/11/2007 9/17/2007 FAIL
Corrections sent to architect @ rchd_llc@hotmail.com
Case Summary (BLD)  9/17/2007 DONE
Routing - PLANNING  9/11/2007 PASS
DRH07-00196-Sarah Shafer
CUP06-00120-Greg Johnson
Plan assigned to (M_P)8/23/2007 9/6/2007 DONE
Routing - PLUMBING8/29/2007 9/5/2007 PASS
Provide pan drains where required, adjust 4" waste to accomidate(only 3 water closets on 3" waste line, Provide cleanouts at base of stacks and wherever required., Provide accessable shutoff valve for water service at each unit.
Routing - Erosion and Sediment8/28/2007 8/29/2007 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS8/23/2007 8/28/2007 FAIL
Routing PW Sewer Design8/24/2007 8/28/2007 PASS
Routing PW Street Lights8/28/2007 8/28/2007 PASS
Routing PW Sewer Rating8/24/2007 8/28/2007 PASS
Routing PW Solid Waste8/24/2007 8/28/2007 PASS
Pass with the condition that trash is brought to Maple Grove for collection (residential service).
Additional plans submitted  8/28/2007 DONE
Recieved Gas line plans. I placed them in Mike P. cubicle and date stamped them. Waiting for plans to be routed to me to insert. (SRZ)
Routing PW Drainage8/24/2007 8/27/2007 FAIL
DetailsBrian Murphy
1/2 of roof drainage needs to be accounted for.
(F) Reprint permit  8/23/2007  
Routing - PLANNING Land Div8/23/2007 8/23/2007 PASS
Sub- Randall Acres No 10
Application received  8/22/2007  
Recd Pcfee & Taken To Pln CK  8/22/2007 DONE
Plans ACCEPTED BY PLAN TECH  8/22/2007  
Plan routing begun/NEW & ADDTN  8/22/2007  
First Notice 4/14/2009