Third Notice BLD | 9/22/2008 | 9/22/2008 | 3/18/2009 | | DONE |
Patricia Smith
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 8/11/2008 | 8/11/2008 | 9/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/10/2008 | 8/11/2008 | | DONE |
|
|
|
|
BLD-Final | 6/9/2008 | 6/10/2008 | 6/10/2008 | P | PASS |
Dave Hannah
|
|
|
Greg Phone #: ###-#### ok for perm occ
|
Permanent Occupancy | | | 6/10/2008 | | |
|
|
|
|
BLD-Final | 6/5/2008 | 6/5/2008 | 6/6/2008 | P | PART |
Dave Hannah
|
|
|
Greg Phone #: ###-#### ok for temp but needs to fix ada restroom
|
FIRE-Final Inspection | 6/4/2008 | 6/5/2008 | 6/5/2008 | A | PASS |
Forrest France
|
|
|
Life safety inspection completed acceptable, noted security chain at the Jefferson street side entrance door to be removed prior to structural final as agreed.
|
CHANGE STATUS TO (ISS) | | | 5/29/2008 | | DONE |
|
|
|
Changed back to issue as wrong key was hit by mistake ///dld
|
Code Occupancy Approval | | | 5/29/2008 | | PASS |
Wm. Michael Meloy
|
|
|
Compliance met.
|
BLD-Framing/Rough-in | 4/15/2008 | 4/16/2008 | 4/16/2008 | A | PASS |
Dave Hannah
|
|
|
greg - please call 1/2 hr prior to inspection Phone #: ###-####
|
BLD-Conference | 2/27/2008 | 2/28/2008 | 2/28/2008 | A | PASS |
Dave Hannah
|
|
|
greg Phone #: ###-#### Note: please call him approx 1/2 hr prior to conference
|
Issue PAID IN FULL permit | | | 1/9/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2007 | | PASS |
|
|
|
|
Print Occupancy Form | | | 12/14/2007 | | DONE |
|
|
|
|
Telephone call | | | 12/14/2007 | | DONE |
|
|
|
t/c w brad marczuk at ###-#### - permit ready and fees given - also need rce# and ACHD receipt
|
Permit Ready to Issue | | | 12/14/2007 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 9/18/2007 | | 12/14/2007 | | PASS |
|
|
|
12/14/2007 07:01:30 DRS - activity updated through activity BLDA022 from case BLD07-02331.
|
Routing - PLAN CHECK | 11/1/2007 | | 12/14/2007 | | PASS |
|
|
|
New Sheet 'S1" with dimensioned layout for concrete pads and columns provided and inserted into plans. Plans to permit desk to issue.
|
Plan resubmittals received | | | 12/13/2007 | | |
|
|
|
received response letter and two copies of page S1; taken to Dan Stuart
|
Telephone call | | | 12/10/2007 | | DONE |
|
|
|
Call to Eric wolfe concerning dimensioning of plans showing placement requirements of footings, columns, beams etc. for correct layout. Said he scaled plans submitted by architect.
|
Telephone call | | | 12/10/2007 | | DONE |
|
|
|
Called Brad Marczuk concerning dimensioning of plans. Left voice message of question and ask him to return my call.
|
Plan resubmittals received | | | 12/6/2007 | | |
|
|
|
Received response letter three copies of structural calculations and pages G1.1 (cover sheet), G1.1 (exiting & code), L-1, SP-1, A1, A3, A5, S0, S1, S2; taken to Dan S.
|
1st review completed | | | 11/2/2007 | | FAIL |
|
|
|
|
Routing - FIRE | 11/1/2007 | | 11/2/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
Routing PW Solid Waste | | | 11/1/2007 | | PASS |
|
|
|
was passed on 9-21-07 by solid waste. computer sign off was skipped; lw
|
Routing - PLANNING | 10/31/2007 | | 11/1/2007 | | PASS |
|
|
|
Sarah Schafer DRH06-00482 Approved per the DR.
|
Routing - PLAN CHECK | 9/25/2007 | | 10/31/2007 | | FAIL |
|
|
|
Resubmittals required. Plan review e-mailed to architect. plans routed to fire code analyst for review.
|
Plan resubmittals requested | | | 10/31/2007 | | DONE |
|
|
|
Architect e-mailed copy of plan review.
|
Routing - Erosion and Sediment | 9/24/2007 | | 9/25/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 9/18/2007 | | 9/24/2007 | | PASS |
|
|
|
|
Routing PW Drainage | 9/19/2007 | | 9/21/2007 | | PASS |
|
|
|
|
Routing PW Street Lights | 9/22/2007 | | 9/21/2007 | | PASS |
|
|
|
|
Routing PW Sewer Rating | 9/22/2007 | | 9/21/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 8/29/2007 | | 9/18/2007 | | DONE |
|
|
|
9/18/2007 15:56:13 MYS - activity updated through activity BLDA168 from case BLD07-02331.
|
Plans ACCEPTED BY PLAN TECH | | | 8/29/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/29/2007 | | |
|
|
|
|
Application received | | | 8/27/2007 | | |
|
|
|
|