Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD07-02372
StatusFinaled
Name CAFCO INC
Site Address 3604 S BANNER AVE
Project NameSTEVE CHRISTENSEN BLDG
Customer Number 
ePlanReviewNo
Description
Steven Christensen (Office/Warehouse Shell Building) - To construct a new 7,910 square foot, two story, wood framed office and warehouse shell building and related site improvements. This is shell permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. This building will be fully fire sprinkled to allow for single fire department accesses. All construction per the approved plans. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (FNL)  3/9/2009 DONE
DetailsBarbara Stitt
Letter of complaince issued 3-6-09 BAS
BLD-Final3/5/20093/6/20093/6/2009APART
DetailsTom Arcoraci
Daryl Phone #: ###-#### ok pending pz and pw
FIRE-Final Inspection3/5/20093/6/20093/6/2009APASS
DetailsTroy Cobbley
life safety passed
PubWorks Occupancy Approval3/6/20093/6/20093/6/2009 DONE
DetailsBarbara Stitt
Per phone call from Dan Erskine this is approved by him effective 3-6-09 no card on site for him to sign///3-6-09 @ 11:00am BAS
Zoning Approval3/6/20093/6/20093/6/2009 DONE
DetailsJosh Wilson
Inspection Record Card- Bld  3/6/2009 DONE
Letter of compliance  3/6/2009 DONE
DetailsBarbara Stitt
Override - People Holds  3/6/2009  
DetailsJosh Wilson
FIRE-Final Inspection2/27/20093/2/20093/2/2009APART
DetailsTroy Cobbley
A temporary occupancy was given with sams permission until the curb painting for the fire dept access has been done. It could not be done yet because the curbing needed to cure prior to painting. All other life safety items are ok.
Override - People Holds  2/27/2009  
DetailsTisha Gallop
FIRE-Final Inspection2/24/20092/25/20092/25/2009AFAIL
DetailsTroy Cobbley
See the correction notice left at the job site for items needing addressed.. Per a conversation with Scott the remote FDC and PIV arer not required. I measured the distance from the existing fire hydrant to the now wall mounted PIV and FDC and the distance is roughly 250'-0" which is ok with Scott.
Plan Reviewer's activity  2/17/2009 DONE
FD Road temporary access letter received.
PRINT Activities  2/5/2009 DONE
Meeting  2/4/2009 DONE
DetailsMark Senteno
Met w/GC Darryl. Discussed his request to allow a TOC w/Fire Dept access unpaved until batch plant reopens at the end of February 2009. Roadway needs to be maintained to provide a driveable surface that will support vehicle weight up to 75,000 pounds. He is to submit letter to me for signature to document this commitment prior to Fire approval for TOC.
2/17/2009 - Received letter dated 2/12/2009 from Steve Christensen, owner of building, committing to provide and maintain a non-paved fire department roadway surface capable of supporting the required 75,000 lb load and to have the roadway paved and ready for "final" inspection by 3/15/2009. Acceptable to allow this condition for a TOC. Letter attached under Doc's. M. Senteno.
BLD-Final1/23/20091/23/20091/23/2009ANR
DetailsJim Storey
need fire/pw/p&z/achd pending sign offs
BLD-Aging Inspection1/21/20091/21/20091/21/2009 PASS
DetailsJim Storey
finals by others in progress.
BLD-Energy code compliance10/30/200810/30/200810/30/2008PPASS
DetailsJim Storey
BLD-Framing/Rough-in10/30/200810/30/200810/30/2008PPASS
DetailsJim Storey
BLD-Aging Inspection8/27/20088/27/20088/27/2008 PART
DetailsJim Storey
need aproved plans.
CHANGE STATUS TO (ISS)  7/30/2008 DONE
DetailsMarsha Smylie
already issued previously- a plan mod
(F) Reprint permit  7/30/2008 DONE
DetailsMarsha Smylie
Telephone call  7/28/2008 DONE
Details
t/c w eileen davidson at ###-#### - permit ready and fees given
Permit Ready to Issue  7/28/2008 DONE
Details
Routing - PLAN CHECK7/21/2008 7/25/2008  
DetailsJohn Menard
Plan assigned to (JCM)4/16/2008 7/25/2008 PASS
DetailsJohn Menard
7/25/2008 14:07:04 JCM - activity updated through activity BLDA022 from case BLD07-02372.
Plan resubmittals received  7/25/2008 DONE
DetailsJohn Menard
Received faxed energy envelope compliance from the architect. Inserted into plans. JCM
Routing - PLANNING7/25/2008 7/25/2008 PASS
DetailsSarah Schafer
Routing - PLAN CHECK7/25/2008 7/25/2008 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  7/25/2008 DONE
DetailsJohn Menard
Inspection Record Card- Bld  7/25/2008 DONE
DetailsCathy Brown
Inspection Record Card- Bld  7/25/2008 DONE
DetailsCathy Brown
Routing - FIRE7/17/2008 7/21/2008 PASS
DetailsScott Arellano
Attached modified IFC comments to plans
Plan resubmittals requested  7/17/2008 DONE
E-mailed the architect a copy of the plans review requesting revisions. JCM
Routing Off Site - STRUCTURAL4/18/2008 4/25/2008 FAIL
DetailsJohn Menard
Called action Courier for pick up 4-18-08 @ 3:10pm BAS - Received comment list from the consulting structural engineer requesting revisions. JCM
Plan resubmittals requested  4/25/2008 DONE
DetailsJohn Menard
Faxed the contractor a copy of the structural reveiw requesting revisions. JCM
Plan Modification Accepted  4/17/2008  
DetailsMarsha Smylie
plan modification excepted for bld07-02372 for the redesign of c m c to stick frame- metal and stucco exterior on sheets A-1, A-2, A-3. routed to John Menard.
BLD-Foundation3/28/20083/28/20083/28/2008PPASS
DetailsJim Storey
daryl - wall Phone #: ###-####
BLD-Footing3/25/20083/26/20083/26/2008APASS
DetailsJim Storey
darrell Phone #: ###-####
(F) Reprint permit  3/26/2008  
Issue PAID IN FULL permit  3/25/2008 DONE
DetailsDarla L Downs
Ready Permit EXTENDED  2/21/2008  
Telephone call  2/19/2008 DONE
called Steve Christensen at ###-#### and told him permit is ready, fee and need ACHD & that the permit will expire & will apply for an extension
Routing - PLAN CHECK11/9/2007 12/14/2007  
Routing - PLUMBING12/14/2007 12/14/2007 PASS
grease and hazardous liquids interceptor shown on original submitted plans. interceptor detail shown on P0.2 but no interceptor or piping shown on resubmitted plans. did you delete this item from construction?
Routing - PLAN CHECK12/14/2007 12/14/2007 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/14/2007 DONE
Inspection Record Card- Bld  12/14/2007 DONE
Inspection Record Card- Bld  12/14/2007 DONE
Telephone call  12/14/2007 DONE
called Steve ###-#### and told him permit is ready, fee and need ACHD
Permit Ready to Issue  12/14/2007 DONE
Plan assigned to (JCM)9/4/2007 12/14/2007 PASS
12/14/2007 11:49:22 JCM - activity updated through activity BLDA022 from case BLD07-02372.
Plan resubmittals received  12/13/2007  
received 2 copies of sheets P1.0,C-1,C-2 inserted by Steve christensen Plans taken back to John M.
Routing - PLUMBING11/9/2007 11/9/2007 FAIL
Call architect and advised revised plans did not address requested revisions. GV
Plan resubmittals received  11/8/2007  
received 3 copies of sheet P1.0 inserted by Steven E Christsen and taken back to John M.
Routing - PLUMBING10/24/2007 10/25/2007 FAIL
Routing - FIRE10/22/2007 10/24/2007 PASS
Attached revised IFC review comments to plans. Faxed revised IFC review comments to architect.
Routing - PLAN CHECK10/17/2007 10/22/2007  
Plan resubmittals received  10/19/2007  
Received 1 cover transmittal and 2 copies of sheets A1.0 inserted into plans by Steve Christensen and taken back to john Menard///10/19/07 @ 12:59pm BAS
Routing - FIRE10/12/2007 10/17/2007 FAIL
Faxed updated resubmittal items to architect. Attached updated review comments to plans.
Routing - PUBLIC WORKS10/10/2007 10/12/2007 PASS
Routing PW Drainage10/9/2007 10/12/2007 PASS
Routing PW Sewer Rating10/12/2007 10/12/2007 PASS
Routing - PLAN CHECK10/9/2007 10/10/2007  
Plan resubmittals received  10/10/2007  
Received five copies of pages C-1, C-2, and three copies of drainage calculations; inserted by permit tech LEG and taken back to John Menard
Routing - PLAN CHECK9/20/2007 10/9/2007  
Plan Reviewer's activity  10/9/2007 PASS
Reviewed and approved structural revisions. JCM
Routing - FIRE10/9/2007 10/9/2007 FAIL
Faxed resubmittal items and updated review comments to architect.
Plan resubmittals received  10/8/2007 DONE
received 1 response to Scott Arellano , 1 united water sheet, 1 calc with ( 5 sheets) and 2 copys of sheets A-1.0,S2.1,S3.1 resubmittals inserted into plans by Eileen Davidson from Architecture Interior Design Landscape Planning and plans taken back to John M.
1st review completed  9/20/2007 FAIL
Routing - FIRE9/15/2007 9/20/2007 FAIL
Faxed resubmittal items to architect. Attached IFC comments to plans.
Plan resubmittals requested  9/19/2007 DONE
Faxed the architect a copy of the structural review requesting revisions. JCM
Routing Off Site - STRUCTURAL9/4/2007 9/18/2007 FAIL
Received comment list from consulting structural engineer requesting revisions. JCM
Plan Reviewer's activity  9/15/2007 PASS
Reviewed and approved with red lined notes and revised energy envelope calculation. JCM
Routing - PLAN CHECK9/13/2007 9/15/2007 PASS
John Menard
Routing - PLANNING9/11/2007 9/13/2007 PASS
Pass - approvals were in the County.
Routing - PLUMBING9/6/2007 9/11/2007 FAIL
vents fron sand and oil interceptor to vent seperate from sanitary sewer. provide location of septic tank and piping. sheet p1.0 indecates 2" C.W. to building, sheet c-2 shows 1" water service. if rpvb is to be used provide a floor drain at backflow location.
Routing - Erosion and Sediment9/5/2007 9/6/2007 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS9/4/2007 9/5/2007 FAIL
Routing PW Drainage9/4/2007 9/5/2007 FAIL
DetailsBrian Murphy
NOTES,PERC RATE, ROOF.
Routing PW Street Lights9/5/2007 9/5/2007 PASS
Routing PW Sewer Design9/5/2007 9/5/2007 PASS
Routing PW Sewer Rating9/5/2007 9/5/2007 PASS
Routing PW Solid Waste9/5/2007 9/5/2007 PASS
Plan routing begun/NEW & ADDTN  9/4/2007  
Routing - PLANNING Land Div9/4/2007 9/4/2007 PASS
King Industrial park sub
Plans ACCEPTED BY PLAN TECH  9/4/2007  
Pending Assignment by MYS8/30/2007 9/4/2007 DONE
9/4/2007 08:59:03 JCM - activity updated through activity BLDA166 from case BLD07-02372.
Telephone call  9/4/2007 DONE
called Action Couriers for pick up
Application received  8/30/2007  
Recd Pcfee & Taken To Pln CK  8/30/2007  
Plan resubmittals received     
DetailsJohn Menard
Received 2 copies of sheets A2.0 and A3.0 and inserted into plans then returned to John Menard's desk 7-24-08 @ 12:25pm BAS