Permit Information
Permit NumberBLD07-02393
StatusFinaled
Name EKC INC
Site Address 542 W McGREGOR DR
Project NameUS MIRROR AND GLASS
Customer Number 
ePlanReviewNo
Description
US Mirror and Glass - To construct a new 6,970 square foot, one story with mezzanine fabrication and office building and related site improvements. The mezzanine is a 1,250 square foot, office area. This building is constructed of a pre-engineered metal building (Butler). All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD9/22/20089/22/200812/16/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD8/11/20088/11/20089/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 6/5/20088/11/2008 DONE
BLD-Final6/4/20086/5/20086/5/2008APASS
DetailsJim Storey
Permanent Occupancy UNPAID FEE  6/5/2008 DONE
DetailsTisha Gallop
BLD-Final6/3/20086/4/20086/4/2008APART
DetailsJim Storey
dale Phone #: ###-####
Code Occupancy Approval6/3/20086/3/20086/3/2008PPASS
DetailsJoe R Venneman
FIRE-Final Inspection5/29/20085/30/20085/30/2008APASS
DetailsForrest France
Fire life safety inspection passed with the exception of missing building address numbers-contractor to post today per agreement-to be verified at structural final prior to building occupancy.
PubWorks Occupancy Approval6/2/20086/2/20085/29/2008 DONE
Signed occupancy, R. Rokovitz 05/29/08.
BLD-Framing/Rough-in4/17/20084/18/20084/18/2008APASS
DetailsJim Storey
Dale, early a.m. if possible; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
BLD-Framing/Rough-in3/18/20083/18/20083/18/2008PPART
DetailsJim Storey
Dale Phone #: ###-####wip
BLD-Framing/Rough-in2/25/20082/26/20082/26/2008APASS
DetailsJim Storey
dale - first thing if possible Phone #: ###-#### ok to sheet exterior
BLD-Foundation12/12/200712/13/200712/13/2007APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/12/2007 at 3:27:58 PM. Contact: ###-####.
Print Occupancy Form  12/12/2007 DONE
BLD-Footing12/5/200712/6/200712/6/2007APART
DetailsJim Storey
Dale; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
(F) Reprint permit  10/29/2007  
Print Occupancy Form  10/26/2007 DONE
Telephone call  10/26/2007 DONE
t/c w eric anderson at ###-#### - permit ready and fees given - also need ACHD receipt
Permit Ready to Issue  10/26/2007 DONE
Issue PAID IN FULL permit  10/26/2007 DONE
Plan assigned to (JCM)9/4/2007 10/25/2007 PASS
10/25/2007 13:37:02 JCM - activity updated through activity BLDA022 from case BLD07-02393.
Routing - PUBLIC WORKS9/4/2007 10/25/2007 PASS
Routing - PUBLIC WORKS10/24/2007 10/25/2007 PASS
Routing - PUBLIC WORKS GRADING10/25/2007 10/25/2007 PASS
Routing - PLAN CHECK10/25/2007 10/25/2007 PASS
PLANS/APPL TAKEN TO FRONT DESK  10/25/2007 DONE
Routing PW Environmental10/24/2007 10/24/2007 PASS
Must use approved Boise City sediment interceptor design, 1500 gal minimum. Design cut sheet sent to BRS architects
Routing - PLAN CHECK10/22/2007 10/24/2007  
Routing - FIRE10/18/2007 10/22/2007 PASS
Attached revised IFC review comments to plans.
Routing - PLANNING10/11/2007 10/18/2007 PASS
Plan resubmittals received  10/18/2007  
Received transmittal sheet, response letter, and five copies of page C2.0; inserted into plans by permit tech (LEG) and taken back to Matt H.
Plan Reviewer's activity  10/11/2007 PASS
Reviewed and approved structural and nonstructural revisions. JCM
Routing - PLAN CHECK9/27/2007 10/11/2007 PASS
Plan resubmittals received  10/1/2007  
Received two copies of pages C2.0, C3.0; inserted into plans by LEG and taken back to John Menard
1st review completed  9/27/2007 FAIL
Routing - FIRE9/24/2007 9/27/2007 FAIL
Faxed and emailed resubmittal items to architect.
Plan resubmittals received  9/25/2007  
received 1 response,2 comments,2 copys of sheets S5.1,LS-2,E3.1,LS-1,E1.1 AND 3 copys of sheets SD1.1,SD1.2,A7.1,A7.2 (BRS ARCHITECTS INSERTED SHEETS AND RETURNED TO FIRE ///DLD)
Plan resubmittals requested  9/24/2007 DONE
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PLAN CHECK9/14/2007 9/24/2007 FAIL
John Menard
Routing Off Site - STRUCTURAL9/4/2007 9/19/2007 FAIL
Received a comment list from the consulting structural engineer requesting revisions.
Plan resubmittals requested  9/19/2007 DONE
Faxed the architect a copy of the structural review requesting revisions. JCM
Routing - PLANNING9/11/2007 9/14/2007 FAIL
DRH07-00367 Matt Halitsky

Plans do not meet the conditions of the DR approval. Letter sent to applicant 9/14/2007.
Routing - PLUMBING9/11/2007 9/11/2007 PASS
venting must meet crosssectional area equivilent, sewer side vent of interceptor cannot connect to flamable vapor vent.
Routing - Erosion and Sediment9/10/2007 9/11/2007 PASS
ESC plan approved with attached conditions.
Routing PW Sewer Rating9/7/2007 9/10/2007 PASS
Routing PW Solid Waste9/10/2007 9/10/2007 PASS
Routing PW Drainage  9/7/2007 FAIL
DetailsBrian Murphy
SLOPES, PERC RATE, 10 FOOT SEPERATION.
Routing PW Sewer Design9/5/2007 9/5/2007 PASS
Routing PW Street Lights  9/5/2007 PASS
Plans ACCEPTED BY PLAN TECH  9/4/2007  
Plan routing begun/NEW & ADDTN  9/4/2007  
Routing - PLANNING Land Div9/4/2007 9/4/2007 PASS
Telephone call  9/4/2007 DONE
called Action Couriers for pick up
Application received  9/4/2007  
Pending Assignment by MYS9/4/2007 9/4/2007 DONE
9/4/2007 13:29:39 JCM - activity updated through activity BLDA166 from case BLD07-02393.
Recd Pcfee & Taken To Pln CK  9/4/2007