Permanent Occupancy | | | 2/1/2011 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Aging Inspection | 10/14/2010 | 10/14/2010 | 10/14/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 7/26/2010 | 7/26/2010 | 7/26/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 5/27/2009 | 5/28/2009 | 5/28/2009 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/27/2009 at 3:03:46 PM. Contact: ###-####.
|
FIRE-Alarm Testing | 5/27/2009 | 5/28/2009 | 5/28/2009 | A | PASS |
Forrest France
|
|
|
Final fire life safety walkthrough completed satisfactory, C/N items are finished, project related fire alarm and sprinkler permits are finaled, mag lock interconnections tested per fire alarm final by K. Roule, inspection passed. NOTE: inspection type is BLD- fire final.
|
FIRE-Final Inspection | 12/2/2008 | 12/2/2008 | 12/3/2008 | P | PART |
Forrest France
|
|
|
Okayed patient rooms 4024 thru 4028 with the exception of 4025 (missing door), also noted some missing ceiling tile, one SD at the fire doors to be adjusted to the centerline of the doors, missing smoke seal at the consultation room door (also repair door hardware), two missing escutcheons to be replaced.
|
BLD-Final | 12/2/2008 | 12/2/2008 | 12/2/2008 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/2/2008 at 6:47:06 AM. Contact: ###-####.
|
BLD-Wall cover | 10/22/2008 | 10/23/2008 | 10/23/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/22/2008 at 2:55:30 PM. Contact: ###-####.ok to cover ceiling
|
BLD-Wall cover | 9/22/2008 | 9/23/2008 | 9/23/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/22/2008 at 9:09:18 AM. Contact: ###-####. soffits in corradors first phase ok to cover
|
BLD-Wall cover | 7/14/2008 | 7/15/2008 | 7/15/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/14/2008 at 10:58:58 AM. Contact: ###-####.north side ok to cover all but plumbing walls
|
BLD-Wall cover | 6/17/2008 | 6/18/2008 | 6/18/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/17/2008 at 8:58:11 AM. Contact: ###-####. ok to cover south corridor wall after other trades ok
|
BLD-Wall cover | 4/18/2008 | 4/21/2008 | 4/21/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/18/2008 at 11:06:48 AM. Contact: ###-####. ceiling grid locker room area ok
|
BLD-Aging Inspection | 3/19/2008 | 3/19/2008 | 3/20/2008 | | PART |
Dave Hannah
|
|
|
exps on 6/10
|
(F) Reprint permit | | | 12/18/2007 | | DONE |
|
|
|
|
Issue & PRINT to be Invoiced | | | 12/13/2007 | | |
|
|
|
|
Telephone call | | | 12/12/2007 | | DONE |
|
|
|
t/c w tom zabala at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 12/12/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/11/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/10/2007 | | PASS |
|
|
|
Approved with attached conditions.
|
Routing - PLAN CHECK | 12/3/2007 | | 12/10/2007 | | PASS |
|
|
|
Resubmittals entered into original plan submittal set. Plan review clarification conditions are attached to plans for verification in the field by appropriate dicipline field inspectors.
|
Plan assigned to (DRS) | 9/18/2007 | | 12/10/2007 | | PASS |
|
|
|
12/10/2007 18:00:44 DRS - activity updated through activity BLDA022 from case BLD07-02419.
|
Plan resubmittals received | | | 12/7/2007 | | |
|
|
|
received transmittal, response letter, two copies of pages A-101, A-102, A-203, A-502, A-601; taken to Dan Stuart
|
1st review completed | | | 12/3/2007 | | FAIL |
|
|
|
Failed plan check.
|
Routing - FIRE | 11/30/2007 | | 12/3/2007 | | PASS |
Scott Arellano
|
|
|
Attached IFC review comments to plans.
|
Routing - PLAN CHECK | 10/4/2007 | | 11/30/2007 | | FAIL |
|
|
|
Resubmittals required. Plan review e-mailed to Tom zabala ZGA. routing plans to fire code analyst.
|
Plan resubmittals requested | | | 11/30/2007 | | DONE |
|
|
|
E-mailed plan review correction report to Tom Zabala ZGA.
|
Routing - PLUMBING | 9/19/2007 | | 10/4/2007 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 9/18/2007 | | 9/19/2007 | | PASS |
|
|
|
|
Routing PW Sewer Rating | 9/19/2007 | | 9/19/2007 | | PASS |
|
|
|
|
Routing - Addressing | 9/18/2007 | | 9/18/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 9/6/2007 | | 9/18/2007 | | DONE |
|
|
|
9/18/2007 16:39:26 MYS - activity updated through activity BLDA168 from case BLD07-02419.
|
Plans ACCEPTED BY PLAN TECH | | | 9/7/2007 | | |
|
|
|
|
Application received | | | 9/6/2007 | | |
|
|
|
|