BLD-Final | 5/14/2013 | 5/14/2013 | 5/14/2013 | A | PASS |
Jim Storey
|
|
|
Structural repairs and engineers final letter of completion under BLD11-01031.
|
DOC - Permit Finaled | | | 5/14/2013 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/7/2013 | | DONE |
Tim L. Woodard
|
|
|
A conference was held between Jason Blais, Jim Storey, and myself to evaluate Scott Soule's Final Structural Letter (Attached to BLD11-01031) we will accept it with the understanding that Scott Soule's instructions of continual maintenance will be followed through with. If we come to find that maintenance is not be done and the issues begin to reappear we will reevaluate this decision and possibly pull the Certificate of Occupancy. TLW
|
BLD-Aging Inspection | 2/21/2013 | 2/21/2013 | 2/27/2013 | | DEFR |
Jim Storey
|
|
|
pending action from planreview for l/c. insp. is compliant for aproval
|
BLD-Aging Inspection | 11/13/2012 | 11/13/2012 | 11/14/2012 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 8/14/2012 | 8/14/2012 | 8/17/2012 | | PASS |
Jim Storey
|
|
|
wip/ letter on file w BO and planreview.
|
BLD-Aging Inspection | 5/14/2012 | 5/14/2012 | 5/16/2012 | | PEND |
Jim Storey
|
|
|
no requist to insp.
|
BLD-Aging Inspection | 2/13/2012 | 2/13/2012 | 2/17/2012 | | PASS |
Jim Storey
|
|
|
letter recieved and fab of material is in progress for beam repairs. letter on file and with b.o.
|
BLD-Framing/Rough-in | 11/14/2011 | 11/15/2011 | 11/15/2011 | A | CANC |
Jim Storey
|
|
|
9:30 apt.
|
BLD-Framing/Rough-in | 11/14/2011 | 11/14/2011 | 11/14/2011 | P | PASS |
Jim Storey
|
|
|
dan Phone #: ###-####
|
BLD-Aging Inspection | 9/21/2011 | 9/21/2011 | 9/26/2011 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 6/21/2011 | 6/21/2011 | 6/22/2011 | | PART |
Jim Storey
|
|
|
reviewed joist ledger aplaction need engineer on site review to remove shoring.
|
BLD-Conference | 3/16/2011 | 3/16/2011 | 3/16/2011 | P | PASS |
Jim Storey
|
|
|
doug ###-#### aptt. 3:00 will have walkthru w arch/engineer/contractor tue 3:00 pm
|
BLD-Aging Inspection | 2/28/2011 | 2/28/2011 | 3/3/2011 | | PEND |
Tony Young
|
|
|
|
Plan resubmittals received | | | 2/3/2011 | | DONE |
Jason Blais
|
|
|
Received updated structural plans, updated structural calculations, and engineer visual inspection letter via email. All attached to this case and will be provided to Records. Forwarded the documents to the building plan reviewer.
|
Meeting | | | 1/4/2011 | | DONE |
Jason Blais
|
|
|
On site meeting - attending were owner Ken Howell, Property Manager Doug Bolen, Structural Engineer Riley Mahaffey, contractor, Building Official Jason Blais, Building Inspection Supervisor Bob Archibald, Building Inspector Jim Storey, and Plans Examiner Tim Woodard. The group walked the underground parking garage and discussed structural issues and water remediation needing to occur. See 1/19/11 letter attached to this case for action needed to be taken by owner.
|
BLD-Aging Inspection | 12/28/2010 | 12/28/2010 | 12/28/2010 | | PASS |
Jim Storey
|
|
|
Re-open per Jason BLais & Bob Archibald Final inspection and structural engineer verification needed
|
Reopen Permit (ISS) | | | 12/27/2010 | | DONE |
Barbara Stitt
|
|
|
Re-open per Jason BLais & Bob Archibald Final inspection and structural engineer verification needed
|
Case Summary (BLD) | | | 12/20/2010 | | DONE |
Barbara Stitt
|
|
|
|
DOC - Permit Expired | 7/30/2010 | 8/4/2010 | 8/9/2010 | A | PASS |
Jim Storey
|
|
|
R105.5 Expiration. Every permit issued shall become invalid unless the work authorized by such permit is commenced within 180 days after its issuance, or if the work authorized by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each. The extension shall be requested in writing and justifiable cause demonstrated.
R105.8 Responsibility. It shall be the duty of every person who performs work for the installation or repair of building, structure, electrical, gas, mechanical or plumbing systems, for which this code is applicable, to comply with this code.
|
BLD-Aging Inspection | 7/30/2010 | 7/30/2010 | 7/30/2010 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 5/10/2010 | 5/10/2010 | 5/10/2010 | | PEND |
Tony Young
|
|
|
|
Case Summary (BLD) | | | 5/15/2009 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 5/12/2009 | 5/12/2009 | 5/12/2009 | P | PASS |
Jim Storey
|
|
|
Andrew Phone #: ###-####
|
BLD-Framing/Rough-in | 5/14/2008 | 5/15/2008 | 5/15/2008 | A | PART |
Jim Storey
|
|
|
p.j. - please call 1/2 hr prior to inspection Phone #: ###-#### s-2 #4 wall aproved for cover.
|
BLD-Footing | 4/17/2008 | 4/18/2008 | 4/18/2008 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/17/2008 at 3:05:09 PM. Contact: ###-####. rebar ok need engineer to adress epoxy not insp. by si at instaltion/ pending concrete report by strata.
|
BLD-Conference | 2/22/2008 | 2/26/2008 | 2/26/2008 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/22/2008 at 8:20:22 AM. Contact: ###-####. meet with engineer/ken howl/ and contractor/ have investagation demo in progress will reconven when ready.
|
BLD-Aging Inspection | 2/1/2008 | 2/1/2008 | 2/6/2008 | | NR |
Jim Storey
|
|
|
talked with contractor office. they said they would call back as to if they where going to proceed with the work or not. owner of building had a hold on the project was the understanding that i recieved and did not get a return call to confirm.
|
Telephone call | | | 10/30/2007 | | DONE |
|
|
|
Recieved phone call from Ken Hall about plan review report. He offered infromation about the history of the building. He claims They have had problems with the water infiltration since day one, he stated they have conducted several projects to patch the leaks in the rubber membrain, he also said he realized there was more leaks and is still making efforts to repair them. He was calling about the disagreement of the extent of the damages. He believes the damages are isolated and does not feel it is neccissary to remove all the sheet rock from the cieling. I explained I don't feel comfortable with that and am adimate about removing all the sheet rock to examain the full extent of damages. I directed him to George Slain with any further questions.(Oct 30, 2007 @ 9:15a.m.)
|
Telephone call | | | 10/29/2007 | | DONE |
|
|
|
Recieved call from Ken Hall(oct 26, 2007 @ 4:32 pm. Return phone call at 9:45 am on oct 29, 2007. Left message that building was not declared a dangerous building. It was defined as one for plan review purposes. Also informed him to call with any additional questions or concerns.
|
Issue PAID IN FULL permit | | | 10/24/2007 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 9/28/2007 | | 10/22/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/22/2007 | | 10/22/2007 | | PASS |
|
|
|
Passed with conditions/ notice of dangerous building attached to front of plans and within plan review report.
|
Print Pending Permit.LaserJet4 | | | 10/22/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/22/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/22/2007 | | DONE |
|
|
|
|
Telephone call | | | 10/22/2007 | | DONE |
|
|
|
t/c w mark sanders at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/22/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/28/2007 | | 10/18/2007 | | FAIL |
|
|
|
|
1st review completed | | | 10/18/2007 | | FAIL |
|
|
|
|
Pending Assignment by MYS | 9/14/2007 | | 9/28/2007 | | DONE |
|
|
|
9/28/2007 12:03:18 MYS - activity updated through activity BLDA185 from case BLD07-02488.
|
Plans ACCEPTED BY PLAN TECH | | | 9/17/2007 | | |
|
|
|
|
Application received | | | 9/14/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/14/2007 | | DONE |
|
|
|
|