Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD07-02491
StatusFinaled
Name THE MASTER'S CONSTRUCTION, INC
Site Address 6151 N DISCOVERY WAY
Project NamePARK POINTE CNTR II
Customer Number 
ePlanReviewNo
Description
(PURSUIT CHURCH - PARK POINTE CNTR II) To remodel 11,981 sq.ft. of area in an existing 32000 sq ft office building and convert area to a new church per approved plans and CUP07-00056. Work to include, construction of interior nonbearing partition, construction of new platform with accessible ramp, installation of new doors, miscellaneous related interior finishes. This building is fully fire sprinklered for area increase. Any alterations to the sprinkler system shall be per NFPA #13 as regulated by the fire department. RmH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  7/14/2008 DONE
lft vm with paul ###-#### regarding the final value
Telephone call  6/25/2008 DONE
DetailsCathy Brown
lft ms with secretary for Paul to call me Monday when he returns about the final value 11:00 am
Third Notice BLD6/6/20086/6/20086/9/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD4/23/20084/23/20086/6/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 3/5/20084/23/2008 DONE
BLD-Final3/4/20083/5/20083/5/2008PPASS
DetailsJim Sly
pj Phone #: ###-####
OK for Perm Occ. :)
Permanent Occupancy  3/5/2008 DONE
Case Summary (BLD)  2/29/2008 DONE
(F) Reprint permit  1/30/2008  
Case Summary (BLD)  1/24/2008 DONE
Case Summary (BLD)  1/22/2008 DONE
BLD-Final12/28/200712/28/200712/28/2007PCANC
DetailsJim Sly
Ivan (TEMP FINAL for C O ) Phone #: ###-####
OK for Temp Occ.
Temporary Occupancy UNPAID FEE  12/28/2007 DONE
BLD-Final12/26/200712/27/200712/27/2007PNR
DetailsJim Sly
ivan Phone #: ###-####
Need Plmbing final.
FIRE-Final Inspection12/26/200712/27/200712/27/2007APASS
DetailsTroy Cobbley
fire life life safety passed.KR
FIRE-Conference12/21/200712/21/200712/21/2007PDONE
DetailsTroy Cobbley
I issued a stop work order on 12/20/2007 after finding the fire alarm contractor installing the fire alarm system. Mike TImmerman made as entry through tidemark on the fire alarm permit history about work being in progress. The fire alarm plans were not issued until around noon on 12/21/2007. I stopped at the project the morning of 12/21/2007 to verify the the fire alarm contractor was still gone and while I was there I posted "Fire Dept Do Not Occupy" stickers on the east facing double doors and the south facing double doors. I notified Mark Sentenno with the Boise Fire Dept that its appears that the church wants to be open on sunday for services. I let mark know that the fire alarm plans were just issued today and no inspection had been called for. The fire sprinkler plans were just issued today and no inspection had been called for. And no inspection had been called for life safety.
BLD-Final12/20/200712/21/200712/21/2007ACANC
DetailsJim Sly
Ivan Phone #: ###-####
Canc by Contr.
Code Occupancy Approval12/20/200712/20/200712/20/2007PPASS
DetailsCarol Montgomery
Meets compliance with Special Exception (CUP07-00056). Pass.
Plan resubmittals received  12/12/2007  
received transmittal sheet and three copies of M0.0; per Ron H. submit plans to inspector; I spoke to Lee and put the plans on his desk
Issue PAID IN FULL permit  12/5/2007 DONE
Telephone call  12/4/2007 DONE
t/c w paul hatfield at ###-#### - permit ready and fees given
Permit Ready to Issue  12/4/2007 DONE
Routing - PLAN CHECK11/30/2007 12/3/2007 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/3/2007 DONE
Print Occupancy Form  12/3/2007 DONE
Plan assigned to (R_H)10/2/2007 12/3/2007 PASS
12/3/2007 09:25:09 RMH - activity updated through activity BLDA022 from case BLD07-02491.
Routing - FIRE11/29/2007 11/30/2007 PASS
DetailsScott Arellano
Attached IFC review comments to plans.
Routing - PLAN CHECK11/21/2007 11/29/2007 PASS
Plan resubmittals received  11/28/2007  
received platform specs (8) pages, "2" sets of structural calcs (8) pages each, & (3) sets of roof top unit relocation (2) pages each--paperwork taken to Ron Hill
Routing - PLAN CHECK10/25/2007 11/21/2007 PEND
Routing - PUBLIC WORKS11/21/2007 11/21/2007 PASS
Routing PW Sewer Rating11/21/2007 11/21/2007 PASS
Plan resubmittals received  11/19/2007  
received transmittal letter from simplex grinnell & letter to Ron Hill ( 2 pages)also "3" sets of plans including cover sheeet & A1.O, A2.O, ENO.O, MO.O, MO.1, MO.2, M1.O, M1.1, PO.O, PO.1, PO.2, P1.O, P1.1, EO.O, EO.1, E1.O, & E2.O--plans taken to Ron Hill
Routing - FIRE10/22/2007 10/25/2007 FAIL
Faxed and emailed resubmittal items to Rocky Towle. Attached IFC review comments to plans.
1st review completed  10/25/2007 FAIL
Routing - PLAN CHECK10/3/2007 10/22/2007 FAIL
faxed requirements to architect
Case Summary (BLD)  10/20/2007 DONE
Routing - PLANNING10/2/2007 10/3/2007 PASS
Susan Riggs CUP07-00056
Routing - PUBLIC WORKS10/2/2007 10/2/2007 PASS
Pending Assignment by MYS9/14/2007 10/2/2007 DONE
10/2/2007 09:37:28 MYS - activity updated through activity BLDA175 from case BLD07-02491.
Routing PW Sewer Rating10/2/2007 10/2/2007 PASS
Plans ACCEPTED BY PLAN TECH  9/18/2007  
Application received  9/14/2007  
Recd Pcfee & Taken To Pln CK  9/14/2007