Second Notice | | 6/18/2010 | 6/8/2010 | | DONE |
|
|
|
|
Third Notice | | 6/13/2010 | 6/8/2010 | | DONE |
|
|
|
|
First Notice | | 6/11/2010 | 6/8/2010 | | DONE |
|
|
|
|
BLD-Final | 6/1/2010 | 6/1/2010 | 6/1/2010 | P | PASS |
Mike Jordan
|
|
|
call for access Inspection requested from web by: David Mortensen Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 6/1/2010 | 6/1/2010 | 6/1/2010 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 5/28/2010 | 6/1/2010 | 6/1/2010 | A | CANC |
Mike Jordan
|
|
|
call for access Inspection requested from web by: David Mortensen Phone #: ###-#### Inspection cancelled from web by: David Mortensen
|
Zoning Approval | 6/1/2010 | 6/1/2010 | 6/1/2010 | | PASS |
Josh Wilson
|
|
|
|
Permanent Occupancy | | | 6/1/2010 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 5/27/2010 | 5/28/2010 | 5/28/2010 | A | FAIL |
Troy Cobbley
|
|
|
Repair the two emergency lights and provide fire extinguishers with a current inspection tag.
|
BLD-Final | 5/27/2010 | 5/28/2010 | 5/28/2010 | A | NR |
Mike Jordan
|
|
|
Inspection requested from web by: David Mortensen Phone #: ###-####
|
BLD-Conference | 4/22/2010 | 4/22/2010 | 4/22/2010 | A | DONE |
Mike Jordan
|
|
|
Spoke to contractorabout requirements for handrails.
|
BLD-Framing/Rough-in | 4/13/2010 | 4/13/2010 | 4/13/2010 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 4/12/2010 | 4/12/2010 | 4/12/2010 | A | PASS |
Mike Jordan
|
|
|
Inspection requested from web by: David Mortensen Phone #: ###-####. framing ok. Also spoke to contractr regarding the shell and core permit that will also need to be finaled prior to occupncy being issued.
|
Telephone call | | | 4/8/2010 | | DONE |
|
|
|
left vm for chris at ###-#### - permit (plan mod) ready and fees given
|
Override - Parcel Holds | | | 4/8/2010 | | |
|
|
|
|
Permit Ready to Issue | | | 4/8/2010 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/8/2010 | | DONE |
Barbara Stitt
|
|
|
Plan modification approved
|
(F) Reprint permit | | | 4/8/2010 | | DONE |
Barbara Stitt
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 4/7/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Inspection Record Card- Bld | | | 4/7/2010 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 3/8/2010 | | 4/7/2010 | | PASS |
Tim L. Woodard
|
|
|
4/7/2010 14:57:09 TLW - activity updated through activity BLDA022 from case BLD07-02624.
|
Routing - PLAN CHECK | 3/23/2010 | | 4/7/2010 | | PASS |
Tim L. Woodard
|
|
|
Plan Modification approved. TLW
|
Routing - PLANNING Land Div | 4/1/2010 | | 4/1/2010 | | PASS |
Dave Abo
|
|
|
Condo amendments recorded.
|
Routing - PUBLIC WORKS | 3/22/2010 | | 3/23/2010 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 3/23/2010 | | 3/23/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 3/22/2010 | | 3/22/2010 | | PASS |
April Wing
|
|
|
|
Routing - PLANNING Land Div | 3/11/2010 | | 3/12/2010 | | FAIL |
Dave Abo
|
|
|
Dave has not been presented with anything to verify the condo line was removed or that the condo declarations ok it either, until this is verified Dave cannot approve plans. Applicant was informed of this via: phone call. TLW
|
Routing - PLAN CHECK | 3/8/2010 | | 3/11/2010 | | PASS |
Tim L. Woodard
|
|
|
Plan mod approved. TLW
|
Plan Modification Accepted | | | 3/8/2010 | | |
Tim L. Woodard
|
|
|
Rec'd plan mod to change tenant name, modify room names and remove one-way window. Add mop sink walls and door. Add sink to craft room and urnal to one bathroom. Make minor electrical rivisions and modify interior finishes - sheets C.0; A.1; A.2; E.1; P.1
|
BLD-Framing/Rough-in | 3/2/2010 | 3/3/2010 | 3/3/2010 | A | CANC |
Mike Jordan
|
|
|
chris Phone #: ###-#### - please call 1/2 hr prior
|
BLD-Conference | 3/3/2010 | 3/3/2010 | 3/3/2010 | A | PASS |
Mike Jordan
|
|
|
chris Phone #: ###-#### - please call 1/2 hr prior . Spoke to contractor regarding this permit. Contracted noted that they would be resubmitting plans with some minor changes. Contractor noted that owner has a buyer for bldg. and is now ready to proceed and complete remainder of work.
|
BLD-Framing/Rough-in | 9/1/2009 | 9/2/2009 | 9/2/2009 | A | DONE |
Mike Jordan
|
|
|
marty Phone #: ###-####. Framing insp already completed by #316. Left message with Marty to see what he needed. No call back as of 12:52pm.
|
Case Summary (BLD) | | | 7/31/2009 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Framing/Rough-in | 3/5/2009 | 3/6/2009 | 3/6/2009 | P | PASS |
Jim Sly
|
|
|
Andrew Phone #: ###-####
|
BLD-Aging Inspection | 1/1/2009 | 1/1/2009 | 1/5/2009 | | PASS |
Mike Jordan
|
|
|
|
Issue PAID IN FULL permit | | | 10/2/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/22/2008 | | DONE |
|
|
|
left mess for jason at ###-#### that permit is ready & will expire on 10-4-08
|
Telephone call | | | 6/10/2008 | | |
|
|
|
talked to chris laraway at ###-#### - permit ready
|
Ready Permit EXTENDED | | | 3/11/2008 | | |
Marsha Smylie
|
|
|
Extended to 10-11-08
|
Inspection Record Card- Bld | | | 11/15/2007 | | DONE |
|
|
|
|
Telephone call | | | 11/15/2007 | | DONE |
|
|
|
left vm for chris laraway at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 11/15/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/5/2007 | | 11/14/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2007 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/14/2007 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 10/18/2007 | | 11/14/2007 | | PASS |
|
|
|
11/14/2007 13:26:46 TLW - activity updated through activity BLDA022 from case BLD07-02624.
|
Routing - FIRE | 11/1/2007 | | 11/5/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
1st review completed | | | 11/5/2007 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 11/1/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/19/2007 | | 11/1/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/18/2007 | | 10/19/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 10/5/2007 | | 10/18/2007 | | DONE |
|
|
|
10/18/2007 08:21:45 MYS - activity updated through activity BLDA185 from case BLD07-02624.
|
Routing PW Sewer Rating | 10/18/2007 | | 10/18/2007 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/5/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/4/2007 | | |
|
|
|
|
Application received | | | 10/4/2007 | | |
|
|
|
|
Routing - FRONT DESK | 3/8/2010 | | | | |
Tim L. Woodard
|
|
|
|