First Notice | | 1/9/2009 | 1/29/2009 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/9/2009 | | DONE |
|
|
|
|
BLD-Final | 12/29/2008 | 12/29/2008 | 12/29/2008 | P | PASS |
Tom Arcoraci
|
|
|
jed Phone #: ###-####
|
FIRE-Final Inspection | 12/18/2008 | 12/18/2008 | 12/18/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 12/12/2008 | 12/15/2008 | 12/15/2008 | P | PART |
Mike Jordan
|
|
|
JED Phone #: ###-####. Temp occ. granted. Still need letter from special insp. agency and is waiting for the remainder of door hardware for double doors. Also recieved letter with employees signatures stating that they were briefed and trained on manual flush bolts.
|
FIRE-Final Inspection | 12/12/2008 | 12/15/2008 | 12/15/2008 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with sam rogers permission until the fire hydrant is active. United Water installed it today and it will be active as soon as the thrust block has set up.
|
Zoning Approval | 12/15/2008 | 12/15/2008 | 12/15/2008 | | PASS |
Josh Wilson
|
|
|
Pass- applicant will submit updated landscape plan which shows substitutions
|
Print Occupancy Form | | | 12/12/2008 | | DONE |
|
|
|
|
BLD-Other | 12/11/2008 | 12/11/2008 | 12/11/2008 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/11/2008 at 7:40:27 AM. Contact: ###-####. Note: Please call 1/2 hr prior to inspection no manuel flush bolts allowed on double doors
|
Plan Reviewer's activity | | | 12/9/2008 | | DONE |
John Menard
|
|
|
To comply with fire water flow requirements, I have reviewed the plans for compliance as Type IIIB construction. The plans appear to indicate close compliance with Type IIIB construction requirements for fire flow reduction purposes. I red lined the plans to indicate IIIB construction. JCM
|
Routing - FIRE | 12/9/2008 | | 12/9/2008 | | PASS |
Scott Arellano
|
|
|
Plans have been revised to indicate the building type of construction from V-B to III-B. This reduces the minimum required fire flow to 2500 gpm. A 3 hour fire wall installed in this building thereby eliminating the IBC requirement for fire sprinkler protection. IFC comments have been updated to reflect these changes.
|
FIRE-Conference | 12/8/2008 | 12/8/2008 | 12/8/2008 | P | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements for this project. It appears per the fire review comments that a fire hydrant was to be installed out front and fire sprinklers/alarm systems were to be installed as well. These items have not been installed. Scott and Sam have been contacted.
|
BLD-Energy code compliance | 11/6/2008 | 11/7/2008 | 11/7/2008 | A | PASS |
Tom Arcoraci
|
|
|
jed Phone #: ###-####
|
BLD-Framing/Rough-in | 11/5/2008 | 11/6/2008 | 11/6/2008 | A | PART |
Tom Arcoraci
|
|
|
jed Note: please call 1/2 hr prior to inspection to meet with Phone #: ###-#### wip ok 3 hr wall
|
BLD-Wall cover | 10/31/2008 | 10/31/2008 | 10/31/2008 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 10/31/2008 at 10:08:23 AM. Contact: ###-####. office areas only ok to cover
|
BLD-Framing/Rough-in | 10/31/2008 | 10/31/2008 | 10/31/2008 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 10/31/2008 at 10:07:52 AM. Contact: ###-####. office areas only ok to cover,, still need to inspect 3 hr wall
|
BLD-Framing/Rough-in | 10/28/2008 | 10/28/2008 | 10/28/2008 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/28/2008 at 8:49:58 AM. c/n need floor trusses repair for top chord ele and plm cuts/ foam seal top plate penatrations fr fire blk./ nail fool trusses at hanger at header in hall/ provide listing for fire stopping of 3 hr wall/ provide r-38 verifcation of roof insulation. ok to insulate office partions.
|
BLD-Wall cover | 10/28/2008 | 10/28/2008 | 10/28/2008 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/28/2008 at 8:50:32 AM. gyp progression on b sir ok screw sch ok. need fire stop at floor cavity.
|
BLD-Footing | 9/2/2008 | 9/2/2008 | 9/2/2008 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/2/2008 at 8:04:27 AM. Contact: ###-####. Verified 21' rebar UFER installed
|
BLD-Footing | 8/27/2008 | 8/28/2008 | 8/28/2008 | A | PART |
Mike Jordan
|
|
|
jay Phone #: ###-####. wip. Needs to complete install of remaining verts. Reviewed geotech report for subgrade, ok for conc. Noted to Jay that periodoc special insp. is required for verification of mix design and rebar insp.
|
BLD-Footing | 8/27/2008 | 8/27/2008 | 8/27/2008 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-####. wip on installing reinforcement. Called contractor to have him contact a Geotech engineer to verify the min. 2000 psf soil bearing for footings. Will reschedule additional insp. for the am.
|
CHANGE STATUS TO (ISS) | | | 8/25/2008 | | |
|
|
|
already issued - a plan mod
|
(F) Reprint permit | | | 8/25/2008 | | |
|
|
|
|
Print Occupancy Form | | | 8/22/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/22/2008 | | DONE |
Tisha Gallop
|
|
|
Called Rob and told him permit is ready and fees
|
Override - Parcel Holds | | | 8/22/2008 | | |
|
|
|
|
Permit Ready to Issue | | | 8/22/2008 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (JCM) | 6/23/2008 | 6/23/2008 | 8/21/2008 | | PASS |
John Menard
|
|
|
8/21/2008 16:24:26 JCM - activity updated through activity BLDA022 from case BLD07-02644.
|
Plan Reviewer's activity | | | 8/21/2008 | | PASS |
John Menard
|
|
|
Reviewed and approved final requested revisions. JCM
|
Routing - PLAN CHECK | 8/15/2008 | | 8/21/2008 | | PASS |
John Menard
|
|
|
|
Plan resubmittals received | | | 8/21/2008 | | DONE |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/2008 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 8/19/2008 | | DONE |
|
|
|
E-mailed the architect with a request for additional revisions. JCM
|
Plan resubmittals received | | | 8/18/2008 | | |
John Menard
|
|
|
Received transmittal, response letter, letter from Behlen Building Systems, three copies of Structural Calculations and sheets A1.0, 1 of 2, 2 of 2, EN-1, A2.0, A5.0, A6.0, S2.0; inserted by arch. rep. and taken back to John Menard
|
Routing - PLUMBING | 8/12/2008 | | 8/14/2008 | | PASS |
Bill VanDegrift
|
|
|
use boise city approved flammable liquids interceptor detail, attached. 3" flammable vapor vent. dont tie to downstream vent. interceptor vent must be 3" for cross sectional venting requirements.
|
Routing PW Environmental | 8/14/2008 | | 8/14/2008 | | PASS |
Walt Baumgartner
|
|
|
OK, inside wash pad w/ oil/sed interceptor.
|
Routing PW Sewer Rating | 8/14/2008 | | 8/14/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PLAN CHECK | 8/6/2008 | | 8/12/2008 | | |
|
|
|
|
Routing - FIRE | 8/4/2008 | | 8/6/2008 | | PASS |
Scott Arellano
|
|
|
Attached updated IFC comments to plans
|
Plan resubmittals requested | | | 8/4/2008 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions for the plans modification. JCM
|
Plan Reviewer's activity | | | 8/4/2008 | | PASS |
John Menard
|
|
|
Reviewed and approved structural revisions. JCM
|
Routing - PLAN CHECK | 7/1/2008 | | 8/4/2008 | | |
John Menard
|
|
|
|
Plan resubmittals received | | | 7/18/2008 | | |
John Menard
|
|
|
Received transmittal and three copies of foundation design and calculations; taken to John Menard
|
Plan resubmittals requested | | | 7/16/2008 | | DONE |
John Menard
|
|
|
E-mailed the applicant a copy of the structural review requesting revisions. JCM
|
Routing - PLANNING | 6/30/2008 | | 7/1/2008 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLAN CHECK | 6/24/2008 | | 6/30/2008 | | |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 6/24/2008 | | 6/27/2008 | | FAIL |
John Menard
|
|
|
|
Telephone call | | | 6/23/2008 | | DONE |
Tisha Gallop
|
|
|
called Action Courers for pick up of plan modification
|
Plan Modification Accepted | | | 6/23/2008 | | |
Tisha Gallop
|
|
|
Accepted Plan Modification for Bld07-02644 (Power Sports Planet) to change the structure from CMU to steel. Submitted sturctural calculations and sheets A1.0, civil sheets 1 of 2 and 2 of 2, A2.0, A3.0, A5.0, A6.0, EN-1, SN, esc and swpp plan sheet 1 of 1, S1.0, S2.0, S3.0, 10A, 10B, 10C, 10D, 10E, structural sheets 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22 of 22; routed to John Menard
|
(F) Reprint permit | | | 5/16/2008 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/15/2008 | | DONE |
|
|
|
|
Telephone call | | | 5/9/2008 | | |
Marsha Smylie
|
|
|
|
Print Occupancy Form | | | 4/11/2008 | | DONE |
|
|
|
|
Telephone call | | | 4/11/2008 | | DONE |
|
|
|
sent fax to Travis Burrows permit ready and fee given Also need ACHD before pick up /// DLD
|
CHANGE STATUS TO (RDY) | | | 4/11/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/2/2008 | | 4/10/2008 | | |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 4/10/2008 | | 4/10/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Environmental | 4/10/2008 | | 4/10/2008 | | PASS |
Walt Baumgartner
|
|
|
Resubmittal shows wash pad area inside building w/ flamm interceptor. OK
|
Routing - PLAN CHECK | 4/10/2008 | | 4/10/2008 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 4/10/2008 | | PASS |
John Menard
|
|
|
Reviewed and approved structural and nonstructural revisions with redlined notes and attached comment list. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2008 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 10/8/2007 | | 4/10/2008 | | PASS |
John Menard
|
|
|
4/10/2008 16:20:31 JCM - activity updated through activity BLDA022 from case BLD07-02644.
|
Plan resubmittals received | | | 4/9/2008 | | DONE |
|
|
|
received 1 explanation letter, and 2 copies of sheets 10A,10B inserted by Travis Burrows from Dave Evans Construction plans taken back to John M.
|
Routing - PUBLIC WORKS | 3/21/2008 | | 4/2/2008 | | FAIL |
Louise Waldorf
|
|
|
|
Routing PW Drainage | 4/2/2008 | | 4/2/2008 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Environmental | 4/2/2008 | | 4/2/2008 | | FAIL |
Walt Baumgartner
|
|
|
Owner to modify to include washpad area. Plumbing plan resubmitt necessary. Contacted Loyal Gibbons ###-#### and discussed.
|
Routing - PLAN CHECK | 3/10/2008 | | 3/21/2008 | | |
John Menard
|
|
|
|
Routing - FIRE | 3/7/2008 | | 3/10/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 11/13/2007 | | 3/7/2008 | | |
|
|
|
|
Plan resubmittals received | | | 3/6/2008 | | |
|
|
|
received 1 revision,1 review comment, and 2 copies of sheets A2.0,S0.1,S1.0,S3.0 inserted in plans by Travis Burrows from
Dave Evans Construction . Plans taken back to John M.
|
Telephone call | | | 12/14/2007 | | DONE |
|
|
|
Telcon from Will Winslow. He has been contacted to do the HMI; has a list of over 100 products. Mostly small quantities, most volume will be class IIIB's; some Class A brake cleaner, parts solvents, fuel stabilizers, carb clearners, etc. Agreed he will obtain MSDS Sheets from owner since these are required to be on site but will not need to list/classify all items on the list. He will focus on the Class I and aerosols; probably will be few II and IIIA liquids, okay to group all Class IIIB's in one total quantity; will also evaluate use and handling of solvents in maintenance and storage of aerosols.
|
Telephone call | | | 11/28/2007 | | DONE |
|
|
|
Emailed HMIS consultant list to Rob Powell.
|
Routing - FIRE | 11/9/2007 | | 11/13/2007 | | FAIL |
|
|
|
Emailed and faxed resubmittal requirements to architect.
|
1st review completed | | | 11/13/2007 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 11/9/2007 | | DONE |
John Menard
|
|
|
E-mailed the architect with a copy of the plan review requesting revisions. JCM
|
Routing - PLAN CHECK | 10/23/2007 | | 11/9/2007 | | FAIL |
John Menard
|
|
|
John M
|
Routing - PLANNING | 10/17/2007 | | 10/23/2007 | | PASS |
|
|
|
Redlines Sheet L1.0
|
Plan resubmittals requested | | | 10/19/2007 | | DONE |
John Menard
|
|
|
Faxed the applicant a copy of the comment letter from consulting structural engineer requesting revisions.
|
Routing - PLUMBING | 10/12/2007 | | 10/17/2007 | | PASS |
|
|
|
all water lines in the attic must be tented at the time of the rough in inspection.
|
Routing Off Site - STRUCTURAL | 10/8/2007 | | 10/17/2007 | | FAIL |
John Menard
|
|
|
Called Action Couriers for pick up Received comment letter from consulting structural engineer requesting revisions.
|
Routing - Erosion and Sediment | 10/11/2007 | | 10/12/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | | | 10/11/2007 | | FAIL |
|
|
|
|
Routing PW Drainage | | | 10/11/2007 | | FAIL |
Brian Murphy
|
|
|
needs o and m plan
|
Routing PW Solid Waste | | | 10/11/2007 | | PASS |
|
|
|
|
Routing PW Sewer Rating | 10/10/2007 | | 10/11/2007 | | PASS |
|
|
|
|
Routing PW Street Lights | 10/9/2007 | | 10/10/2007 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 10/8/2007 | | 10/9/2007 | | PASS |
|
|
|
Messmer Sub
Lot 3 & 4
|
Routing PW Sewer Design | 10/9/2007 | | 10/9/2007 | | PASS |
|
|
|
|
Application received | | | 10/8/2007 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/8/2007 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/8/2007 | | |
|
|
|
|
Plan resubmittals received | | | | | |
John Menard
|
|
|
Received 3 copies of sheets A2.0, A3.0, A5.0, A6.0 and inserted into plans by someone from Dave Evans Construction then taken back to John Menard's desk///8-21-08 @ 3:13pm BAS
|