Permit Information
Permit NumberBLD07-02644
StatusFinaled
Name DAVE EVANS CONSTRUCTION
Site Address 7126 W VICTORY RD
Project NamePower Sports Planet
Customer Number 
ePlanReviewNo
Description
Power Sports Planet - To construct a new 14,500 square foot, one story motorcycle retail sales and repair facility and related site improvements. This building will contain a retail sales showroom, office area, parts storage area and repair garage. This building is a pre-engineered metal building with steel stud and wood framed wall construction. This building is at maximum allowable area. This building may not be added onto unless the building is fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 1/9/20091/29/2009 DONE
Permanent Occupancy  1/9/2009 DONE
BLD-Final12/29/200812/29/200812/29/2008PPASS
DetailsTom Arcoraci
jed Phone #: ###-####
FIRE-Final Inspection12/18/200812/18/200812/18/2008PPASS
DetailsTroy Cobbley
Life safety passed.
BLD-Final12/12/200812/15/200812/15/2008PPART
DetailsMike Jordan
JED Phone #: ###-####. Temp occ. granted. Still need letter from special insp. agency and is waiting for the remainder of door hardware for double doors. Also recieved letter with employees signatures stating that they were briefed and trained on manual flush bolts.
FIRE-Final Inspection12/12/200812/15/200812/15/2008APART
DetailsTroy Cobbley
A temporary occupancy was given with sam rogers permission until the fire hydrant is active. United Water installed it today and it will be active as soon as the thrust block has set up.
Zoning Approval12/15/200812/15/200812/15/2008 PASS
DetailsJosh Wilson
Pass- applicant will submit updated landscape plan which shows substitutions
Print Occupancy Form  12/12/2008 DONE
BLD-Other12/11/200812/11/200812/11/2008PFAIL
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/11/2008 at 7:40:27 AM. Contact: ###-####. Note: Please call 1/2 hr prior to inspection no manuel flush bolts allowed on double doors
Plan Reviewer's activity  12/9/2008 DONE
DetailsJohn Menard
To comply with fire water flow requirements, I have reviewed the plans for compliance as Type IIIB construction. The plans appear to indicate close compliance with Type IIIB construction requirements for fire flow reduction purposes. I red lined the plans to indicate IIIB construction. JCM
Routing - FIRE12/9/2008 12/9/2008 PASS
DetailsScott Arellano
Plans have been revised to indicate the building type of construction from V-B to III-B. This reduces the minimum required fire flow to 2500 gpm. A 3 hour fire wall installed in this building thereby eliminating the IBC requirement for fire sprinkler protection. IFC comments have been updated to reflect these changes.
FIRE-Conference12/8/200812/8/200812/8/2008PDONE
DetailsTroy Cobbley
I went over life safety requirements for this project. It appears per the fire review comments that a fire hydrant was to be installed out front and fire sprinklers/alarm systems were to be installed as well. These items have not been installed. Scott and Sam have been contacted.
BLD-Energy code compliance11/6/200811/7/200811/7/2008APASS
DetailsTom Arcoraci
jed Phone #: ###-####
BLD-Framing/Rough-in11/5/200811/6/200811/6/2008APART
DetailsTom Arcoraci
jed Note: please call 1/2 hr prior to inspection to meet with Phone #: ###-#### wip ok 3 hr wall
BLD-Wall cover10/31/200810/31/200810/31/2008PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/31/2008 at 10:08:23 AM. Contact: ###-####.
office areas only ok to cover
BLD-Framing/Rough-in10/31/200810/31/200810/31/2008PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/31/2008 at 10:07:52 AM. Contact: ###-####.
office areas only ok to cover,, still need to inspect 3 hr wall
BLD-Framing/Rough-in10/28/200810/28/200810/28/2008PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/28/2008 at 8:49:58 AM. c/n need floor trusses repair for top chord ele and plm cuts/ foam seal top plate penatrations fr fire blk./ nail fool trusses at hanger at header in hall/ provide listing for fire stopping of 3 hr wall/ provide r-38 verifcation of roof insulation. ok to insulate office partions.
BLD-Wall cover10/28/200810/28/200810/28/2008PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/28/2008 at 8:50:32 AM. gyp progression on b sir ok screw sch ok. need fire stop at floor cavity.
BLD-Footing9/2/20089/2/20089/2/2008PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/2/2008 at 8:04:27 AM. Contact: ###-####.
Verified 21' rebar UFER installed
BLD-Footing8/27/20088/28/20088/28/2008APART
DetailsMike Jordan
jay Phone #: ###-####. wip. Needs to complete install of remaining verts. Reviewed geotech report for subgrade, ok for conc. Noted to Jay that periodoc special insp. is required for verification of mix design and rebar insp.
BLD-Footing8/27/20088/27/20088/27/2008PPART
DetailsMike Jordan
Phone #: ###-####. wip on installing reinforcement. Called contractor to have him contact a Geotech engineer to verify the min. 2000 psf soil bearing for footings. Will reschedule additional insp. for the am.
CHANGE STATUS TO (ISS)  8/25/2008  
already issued - a plan mod
(F) Reprint permit  8/25/2008  
Print Occupancy Form  8/22/2008 DONE
Details
Telephone call  8/22/2008 DONE
DetailsTisha Gallop
Called Rob and told him permit is ready and fees
Override - Parcel Holds  8/22/2008  
Permit Ready to Issue  8/22/2008 DONE
DetailsTisha Gallop
Plan assigned to (JCM)6/23/20086/23/20088/21/2008 PASS
DetailsJohn Menard
8/21/2008 16:24:26 JCM - activity updated through activity BLDA022 from case BLD07-02644.
Plan Reviewer's activity  8/21/2008 PASS
DetailsJohn Menard
Reviewed and approved final requested revisions. JCM
Routing - PLAN CHECK8/15/2008 8/21/2008 PASS
DetailsJohn Menard
Plan resubmittals received  8/21/2008 DONE
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  8/21/2008 DONE
Plan resubmittals requested  8/19/2008 DONE
E-mailed the architect with a request for additional revisions. JCM
Plan resubmittals received  8/18/2008  
DetailsJohn Menard
Received transmittal, response letter, letter from Behlen Building Systems, three copies of Structural Calculations and sheets A1.0, 1 of 2, 2 of 2, EN-1, A2.0, A5.0, A6.0, S2.0; inserted by arch. rep. and taken back to John Menard
Routing - PLUMBING8/12/2008 8/14/2008 PASS
DetailsBill VanDegrift
use boise city approved flammable liquids interceptor detail, attached. 3" flammable vapor vent. dont tie to downstream vent. interceptor vent must be 3" for cross sectional venting requirements.
Routing PW Environmental8/14/2008 8/14/2008 PASS
DetailsWalt Baumgartner
OK, inside wash pad w/ oil/sed interceptor.
Routing PW Sewer Rating8/14/2008 8/14/2008 PASS
DetailsLouise Waldorf
Routing - PLAN CHECK8/6/2008 8/12/2008  
Routing - FIRE8/4/2008 8/6/2008 PASS
DetailsScott Arellano
Attached updated IFC comments to plans
Plan resubmittals requested  8/4/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions for the plans modification. JCM
Plan Reviewer's activity  8/4/2008 PASS
DetailsJohn Menard
Reviewed and approved structural revisions. JCM
Routing - PLAN CHECK7/1/2008 8/4/2008  
DetailsJohn Menard
Plan resubmittals received  7/18/2008  
DetailsJohn Menard
Received transmittal and three copies of foundation design and calculations; taken to John Menard
Plan resubmittals requested  7/16/2008 DONE
DetailsJohn Menard
E-mailed the applicant a copy of the structural review requesting revisions. JCM
Routing - PLANNING6/30/2008 7/1/2008 PASS
DetailsJosh Wilson
Routing - PLAN CHECK6/24/2008 6/30/2008  
DetailsJohn Menard
Routing Off Site - STRUCTURAL6/24/2008 6/27/2008 FAIL
DetailsJohn Menard
Telephone call  6/23/2008 DONE
DetailsTisha Gallop
called Action Courers for pick up of plan modification
Plan Modification Accepted  6/23/2008  
DetailsTisha Gallop
Accepted Plan Modification for Bld07-02644 (Power Sports Planet) to change the structure from CMU to steel. Submitted sturctural calculations and sheets A1.0, civil sheets 1 of 2 and 2 of 2, A2.0, A3.0, A5.0, A6.0, EN-1, SN, esc and swpp plan sheet 1 of 1, S1.0, S2.0, S3.0, 10A, 10B, 10C, 10D, 10E, structural sheets 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22 of 22; routed to John Menard
(F) Reprint permit  5/16/2008  
Issue PAID IN FULL permit  5/15/2008 DONE
Telephone call  5/9/2008  
DetailsMarsha Smylie
Print Occupancy Form  4/11/2008 DONE
Telephone call  4/11/2008 DONE
sent fax to Travis Burrows permit ready and fee given Also need ACHD before pick up /// DLD
CHANGE STATUS TO (RDY)  4/11/2008 DONE
Routing - PLAN CHECK4/2/2008 4/10/2008  
DetailsJohn Menard
Routing - PUBLIC WORKS4/10/2008 4/10/2008 PASS
DetailsBeverly Hall
Routing PW Environmental4/10/2008 4/10/2008 PASS
DetailsWalt Baumgartner
Resubmittal shows wash pad area inside building w/ flamm interceptor. OK
Routing - PLAN CHECK4/10/2008 4/10/2008 PASS
DetailsJohn Menard
Plan Reviewer's activity  4/10/2008 PASS
DetailsJohn Menard
Reviewed and approved structural and nonstructural revisions with redlined notes and attached comment list. JCM
PLANS/APPL TAKEN TO FRONT DESK  4/10/2008 DONE
DetailsJohn Menard
Plan assigned to (JCM)10/8/2007 4/10/2008 PASS
DetailsJohn Menard
4/10/2008 16:20:31 JCM - activity updated through activity BLDA022 from case BLD07-02644.
Plan resubmittals received  4/9/2008 DONE
received 1 explanation letter, and 2 copies of sheets 10A,10B inserted by Travis Burrows from Dave Evans Construction plans taken back to John M.
Routing - PUBLIC WORKS3/21/2008 4/2/2008 FAIL
DetailsLouise Waldorf
Routing PW Drainage4/2/2008 4/2/2008 PASS
DetailsBrian Murphy
Routing PW Environmental4/2/2008 4/2/2008 FAIL
DetailsWalt Baumgartner
Owner to modify to include washpad area. Plumbing plan resubmitt necessary. Contacted Loyal Gibbons ###-#### and discussed.
Routing - PLAN CHECK3/10/2008 3/21/2008  
DetailsJohn Menard
Routing - FIRE3/7/2008 3/10/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
Routing - PLAN CHECK11/13/2007 3/7/2008  
Plan resubmittals received  3/6/2008  
received 1 revision,1 review comment, and 2 copies of sheets A2.0,S0.1,S1.0,S3.0 inserted in plans by Travis Burrows from
Dave Evans Construction . Plans taken back to John M.
Telephone call  12/14/2007 DONE
Telcon from Will Winslow. He has been contacted to do the HMI; has a list of over 100 products. Mostly small quantities, most volume will be class IIIB's; some Class A brake cleaner, parts solvents, fuel stabilizers, carb clearners, etc. Agreed he will obtain MSDS Sheets from owner since these are required to be on site but will not need to list/classify all items on the list. He will focus on the Class I and aerosols; probably will be few II and IIIA liquids, okay to group all Class IIIB's in one total quantity; will also evaluate use and handling of solvents in maintenance and storage of aerosols.
Telephone call  11/28/2007 DONE
Emailed HMIS consultant list to Rob Powell.
Routing - FIRE11/9/2007 11/13/2007 FAIL
Emailed and faxed resubmittal requirements to architect.
1st review completed  11/13/2007 FAIL
Plan resubmittals requested  11/9/2007 DONE
DetailsJohn Menard
E-mailed the architect with a copy of the plan review requesting revisions. JCM
Routing - PLAN CHECK10/23/2007 11/9/2007 FAIL
DetailsJohn Menard
John M
Routing - PLANNING10/17/2007 10/23/2007 PASS
Redlines Sheet L1.0
Plan resubmittals requested  10/19/2007 DONE
DetailsJohn Menard
Faxed the applicant a copy of the comment letter from consulting structural engineer requesting revisions.
Routing - PLUMBING10/12/2007 10/17/2007 PASS
all water lines in the attic must be tented at the time of the rough in inspection.
Routing Off Site - STRUCTURAL10/8/2007 10/17/2007 FAIL
DetailsJohn Menard
Called Action Couriers for pick up Received comment letter from consulting structural engineer requesting revisions.
Routing - Erosion and Sediment10/11/2007 10/12/2007 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS  10/11/2007 FAIL
Routing PW Drainage  10/11/2007 FAIL
DetailsBrian Murphy
needs o and m plan
Routing PW Solid Waste  10/11/2007 PASS
Routing PW Sewer Rating10/10/2007 10/11/2007 PASS
Routing PW Street Lights10/9/2007 10/10/2007 PASS
Routing - PLANNING Land Div10/8/2007 10/9/2007 PASS
Messmer Sub
Lot 3 & 4
Routing PW Sewer Design10/9/2007 10/9/2007 PASS
Application received  10/8/2007  
Plans ACCEPTED BY PLAN TECH  10/8/2007  
Plan routing begun/NEW & ADDTN  10/8/2007  
Plan resubmittals received     
DetailsJohn Menard
Received 3 copies of sheets A2.0, A3.0, A5.0, A6.0 and inserted into plans by someone from Dave Evans Construction then taken back to John Menard's desk///8-21-08 @ 3:13pm BAS