Permit Information
Permit NumberBLD07-02653
StatusFinaled
Name STEED CONSTRUCTION
Site Address 673 E PARKCENTER
Project NameIdaho Banking Company
Customer Number 
ePlanReviewNo
Description
Idaho Banking Company - To construct a new 4,720 square foot, one story, wood framed bank building and related site improvements. The building consists of a 4,005 main bank building and a 715 square foot, covered drive-thru banking window area. All construction per the approved plans and attached comment list. JCM CUP06-00123
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  8/9/2016 DONE
Second Notice BLD8/11/20088/11/20089/11/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 7/23/20088/11/2008 DONE
Permanent Occupancy UNPAID FEE  7/23/2008 DONE
DetailsBarbara Stitt
BLD-Final7/21/20087/21/20087/21/2008ADONE
DetailsLori Flook
inspected per RAnderson 7/15/08
BLD-Final7/18/20087/18/20087/18/2008PPASS
DetailsJim Storey
#: ###-####
FIRE-Final Inspection7/17/20087/18/20087/18/2008APASS
DetailsForrest France
Corrections okayed, fire life safety finaled.--ok per Forrest France for no Fire Alarm permit///7-23-08 BAS
BLD-Final7/17/20087/18/20087/18/2008ADEFR
DetailsJim Storey
#: ###-#### to pm
FIRE-Final Inspection7/16/20087/17/20087/17/2008PNR
DetailsForrest France
Final pending repair of non-functional emergency lights.
BLD-Final7/16/20087/17/20087/17/2008PDEFR
DetailsJim Storey
tim Note: late aternoon - after forest inspection please Phone #: ###-#### to am
FIRE-Final Inspection7/17/20087/17/20087/17/2008AFAIL
DetailsForrest France
EM lights failed to function at three locations including the open office, womens RR, and east exit discharge. Fire lane marking is complete as required.
Code Occupancy Approval  7/17/2008 PASS
DetailsAndrea Tuning
FIRE-Final Inspection7/14/20087/15/20087/15/2008AFAIL
DetailsForrest France
Egress lights did not function, fire lanes were not marked.KR
BLD-Final7/14/20087/15/20087/15/2008PNR
DetailsTom Arcoraci
tim Note: please call 1/2 hr prior to inspection Phone #: ###-####
BLD-Framing/Rough-in6/4/20086/4/20086/5/2008PPART
DetailsDave Hannah
Tim- Call prior to going ceiling grid Phone #: ###-#### ok to cover ceiling
BLD-Energy code compliance5/5/20085/5/20085/5/2008PPASS
DetailsJim Storey
tim Note: please call 1/2 hr prior to inspection Phone #: ###-####
BLD-Framing/Rough-in4/30/20084/30/20084/30/2008PPASS
DetailsJim Storey
tim Note: please call 1/2 hr prior to inspection Phone #: ###-####
BLD-Framing/Rough-in4/24/20084/25/20084/25/2008APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/24/2008 at 5:16:52 PM. Contact: ###-####. four ply bearing/ brace over 10 ft ceilling/ comprstion webs west entry/ need hangers replaced over driven nailling.
BLD-Wall cover4/14/20084/15/20084/15/2008APASS
DetailsJim Storey
Tim please call 1/2 hr before going out Phone #: ###-#### sheer nailling ok for exterior walls.
BLD-Foundation3/14/20083/14/20083/14/2008PPASS
DetailsJim Storey
tim - need before 2:00 please Phone #: ###-#### placed with si over site pending report.
BLD-Footing3/12/20083/13/20083/13/2008APASS
DetailsJim Storey
Contact: ###-####.placed with si pending reports
BLD-Footing3/12/20083/12/20083/12/2008PCANC
DetailsJim Storey
tim Phone #: ###-####
(F) Reprint permit  12/27/2007  
Issue PAID IN FULL permit  12/21/2007 DONE
Print Occupancy Form  11/23/2007 DONE
Telephone call  11/23/2007 DONE
lft vm with dawna jenkins ###-#### that permit and fees are ready to be picked up but needs gc and achd
Permit Ready to Issue  11/23/2007 DONE
Routing - PLAN CHECK11/14/2007 11/21/2007 PASS
Plan Reviewer's activity  11/21/2007 PASS
Reviewed and approved structural and nonstructural revisions. JCM
PLANS/APPL TAKEN TO FRONT DESK  11/21/2007 DONE
Plan assigned to (JCM)10/9/2007 11/21/2007 PASS
11/21/2007 09:01:26 JCM - activity updated through activity BLDA022 from case BLD07-02653.
Plan resubmittals received  11/20/2007 DONE
received 1 comment letter, and 2 copies of sheets A-1,A-2,A-6,ID-1,ID-2,S-3,S-4,P-1,P-2,E-4,E-6 resubmittal inserted by Donna Jenkins with Larson Arch.
1st review completed  11/14/2007 FAIL
Routing - FIRE11/10/2007 11/14/2007 PASS
Attached IFC review comments to plans.
Routing - PLAN CHECK10/23/2007 11/10/2007 FAIL
John M.
Case Summary (BLD)  11/10/2007  
Plan Reviewer's activity  11/10/2007 PASS
Reviewed and approved structural revisions. JCM
Plan resubmittals requested  11/10/2007 DONE
E-mailed the architect a copy of the plan review requesting revisions. JCM
Plan resubmittals received  10/24/2007  
received comments from pinnacle engineers inc, & "3" sets of calculations (5 pages each). also "2" sets with each sheet of S-3, & S-4--plans taken to John Menard
Routing - PLANNING10/22/2007 10/23/2007 PASS
Routed to John Menard
Routing - PLUMBING10/18/2007 10/22/2007 PASS
per plans and 2003 upc
Plan resubmittals requested  10/19/2007 DONE
Faxed the architect a copy of the comment letter from consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL10/9/2007 10/18/2007 FAIL
Called Action Couriers for pick up - Received comment letter from consulting structural engineer requesting revisions.
Routing - Erosion and Sediment10/18/2007 10/18/2007 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS10/9/2007 10/18/2007 PASS
Routing PW Solid Waste  10/17/2007 PASS
Height of the drive through canopy must be a minimum of 14' from pavement. Per conversation with architect it will be exactly 14'.
Routing PW Drainage10/15/2007 10/16/2007 PASS
Routing PW Sewer Rating10/16/2007 10/16/2007 PASS
Routing PW Sewer Design10/13/2007 10/15/2007 PASS
Routing PW Street Lights10/12/2007 10/12/2007 PASS
Routing - PLANNING Land Div10/9/2007 10/11/2007 PASS
Application received  10/9/2007  
Plans ACCEPTED BY PLAN TECH  10/9/2007  
Plan routing begun/NEW & ADDTN  10/9/2007