Case Summary (BLD) | | | 11/6/2015 | | DONE |
|
|
|
|
Third Notice BLD | 6/6/2008 | 6/6/2008 | 9/30/2008 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.Filed for Bankruptcy
|
Second Notice BLD | 4/23/2008 | 4/23/2008 | 6/6/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 2/22/2008 | 4/23/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/22/2008 | | DONE |
|
|
|
|
BLD-Final | 1/31/2008 | 1/31/2008 | 1/31/2008 | P | PASS |
Dave Hannah
|
|
|
tucker Phone #: ###-#### ok for perm occ
|
FIRE-Final Inspection | 1/29/2008 | 1/30/2008 | 1/31/2008 | P | PASS |
Forrest France
|
|
|
Fire life safety is satisfactory, fire alarm final inspection completed in conjunction with site visit.
|
BLD-Framing/Rough-in | 1/23/2008 | 1/24/2008 | 1/24/2008 | A | PASS |
Jim Storey
|
|
|
mario Phone #: ###-#### walls and ceilling ok
|
BLD-Framing/Rough-in | 11/27/2007 | 11/28/2007 | 11/28/2007 | A | PASS |
Dave Hannah
|
|
|
mario Phone #: ###-#### door framing ok to cover
|
(F) Reprint permit | | | 11/8/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/6/2007 | | DONE |
|
|
|
|
Plan assigned to (425) | 11/2/2007 | 11/2/2007 | 11/2/2007 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 11/2/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/2/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/2/2007 | | DONE |
|
|
|
|
1st review completed | | | 11/2/2007 | | DONE |
|
|
|
|
Application received | | | 10/30/2007 | | |
|
|
|
This is a fast track permit approved by Carl Westfall to take in and assign to Dave Hannah.///10/30/07 LEG
|
Routing - PUBLIC WORKS | 10/30/2007 | | 10/30/2007 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/30/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/30/2007 | | DONE |
|
|
|
|
Routing PW Sewer Rating | 10/30/2007 | | 10/30/2007 | | PASS |
|
|
|
|
Routing - FRONT DESK | 10/30/2007 | | | | |
|
|
|
|