Permit Information
Permit NumberBLD07-02964
StatusFinaled
Name HILL CONSTRUCTION CO
Site Address 4095 S GEKELER LN
Project Name 
Customer Number 
ePlanReviewNo
Description
**(Ace Co.)** To remodel an existing 22,760 sq ft manufacturing building per approved plans and engineering. Work to include, removal of approximately 18 lf of CMU wall, installation of structural support for new opening including new concrete footing, installation of new equipment, the opening for access to an existing 280 sq ft portion of this building to enlarge existing fabrication area, this building is fully fire sprinklered any alterations to the sprinkler system WILL REQUIRE A SEPARATE PERMIT, and shall be installed and maintained per NFPA #13 as regulated by the fire departement. RmH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD3/5/20083/5/20083/7/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD2/6/20082/6/20083/5/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice1/22/20081/22/20082/6/2008 DONE
DetailsJim Storey
BLD-Final1/18/20081/22/20081/22/2008APASS
DetailsJim Storey
everett Phone #: ###-####
DOC - Permit Finaled1/22/20081/22/20081/22/2008PPASS
DetailsJim Storey
FIRE-Final Inspection1/17/20081/18/20081/18/2008APASS
DetailsForrest France
No sprinkler work needed for this permit. Sprinklers were exsisting, no changes made.Life safety complete. KR
BLD-Final1/10/20081/10/20081/14/2008PNR
DetailsJim Storey
everett Note: Please call 1/2 hr to meet with Phone #: ###-#### pending fire.
BLD-Final1/7/20081/8/20081/8/2008APART
DetailsJim Storey
john Phone #: ###-#### Note pleae call 1/2 hr prior to inspection si final as well as re-engineering acepped and filled in archive.
BLD-Foundation1/4/20081/7/20081/7/2008ANR
DetailsJim Sly
john - please call 1/2 hr prior to inspection Phone #: ###-####
John wants final? John cannot meet me in 1/2 hr..........Told him to gather up report from MTI for Epoxy....and to provide Eng. for bolting, then recall for inspection.
BLD-Footing12/14/200712/17/200712/17/2007AFAIL
DetailsJim Storey
gary Phone #: ###-#### need si for epoxy and verifaction of 5 in. embedment/ need to verrify beam thru bolt or engineer aproval of as built .
Issue PAID IN FULL permit  11/29/2007  
Pending Assignment by MYS11/14/2007 11/20/2007 DONE
11/20/2007 07:39:36 RMH - activity updated through activity BLDA175 from case BLD07-02964.
Plan assigned to (R_H)11/20/2007 11/20/2007 PASS
11/20/2007 13:36:12 RMH - activity updated through activity BLDA022 from case BLD07-02964.
Routing - PLAN CHECK11/20/2007 11/20/2007 PASS
DetailsRon Hill
Routing - FIRE11/20/2007 11/20/2007 PASS
Minor remodel / Field Verify
Case Summary (BLD)  11/20/2007 DONE
Case Summary (BLD)  11/20/2007 DONE
1st review completed  11/20/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  11/20/2007 DONE
Inspection Record Card- Bld  11/20/2007 DONE
CHANGE STATUS TO (RDY)  11/20/2007 DONE
Telephone call  11/20/2007 DONE
Called left message for Keith Jones permit ready and fees given
Recd Pcfee & Taken To Pln CK  11/14/2007 DONE
Plans ACCEPTED BY PLAN TECH  11/14/2007  
Application received  11/14/2007