Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD07-03063
StatusFinaled
Name FMG LLC
Site Address 520 W McGREGOR DR
Project NameFERRANTI FRESH PASTA
Customer Number 
ePlanReviewNo
Description
(FERRANTI FRESH PASTA) Permit to construct a new 1,609 square foot factory/mercantile building. Non-separated uses section 302.3.2 of the IBC was used and the most restrictive was the "F" occupancy. Mercantile space encompasses 431 square feet and the factory makes up 953 square feet. The additional square footage is two accessible to the disabled restrooms. Scope of work includes: a new foundation, construction of fully grouted CMU exterior walls, construction of a wood truss roof system, installation of two skylights, [installation of interior non bearing walls to create two restrooms, a locker room, a sales area, and the production area], installation of a roof top mechanical unit w/ related ducts and diffusers, installation of interior finishes, installation of plumbing and related fixtures, and installation of electrical and related fixtures. This building is not sprinklered.**TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD12/22/200812/22/20083/12/2009 DONE
DetailsAlexandra L. DeYoung
Second Notice has not been responded to.
Third Notice BLD12/22/200812/22/20083/12/2009 DONE
DetailsAlexandra L. DeYoung
Second Notice has not been responded to.
Second Notice BLD11/7/200811/7/200812/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
Second Notice BLD11/7/200811/7/200812/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
Routing PW Sewer Design12/3/2007 12/7/2008 FAIL
Sanitary sewer easement requred.

Jim Pardy - ###-####
First Notice 9/15/200811/7/2008 DONE
First Notice 9/15/200811/7/2008 DONE
BLD-Final9/12/20089/15/20089/15/2008PPASS
DetailsJim Storey
Permanent Occupancy UNPAID FEE  9/15/2008  
Permanent Occupancy UNPAID FEE  9/15/2008  
BLD-Final9/12/20089/12/20089/12/2008PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/12/2008 at 10:27:25 AM. Contact: ###-####.
PubWorks Occupancy Approval9/2/20089/2/20088/26/2008 DONE
Final inspection completed 08/26/08 by R. Rokovitz
FIRE-Final Inspection8/22/20088/25/20088/25/2008APASS
DetailsForrest France
Three exit signs repaired while on site, contractor to replace the fire extinguisher with one tagged/certified extinguisher per discussion and code review notes, remainder of life safety items tested okay, inspection passed.
BLD-Final8/22/20088/25/20088/25/2008PCANC
DetailsJim Storey
zane Phone #: ###-#### Disp set to [CANC] by a contractor via Hello! on Aug 25 2008 9:46AM.
Code Occupancy Approval  8/25/2008 DONE
BLD-Other7/7/20087/7/20087/7/2008PPASS
DetailsJim Storey
Zane- ceiling Phone #: ###-####
BLD-Wall cover5/19/20085/20/20085/20/2008PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/19/2008 at 11:53:53 AM. Contact: ###-####. framing and insulation ok
BLD-Wall cover5/16/20085/19/20085/19/2008APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/16/2008 at 12:47:52 PM. Contact: ###-####. need fire blks at retail arch. off sets at ceilling line. all other framing isues ok
BLD-Framing/Rough-in5/14/20085/16/20085/16/2008AFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/14/2008 at 1:52:54 PM. Contact: ###-####. no access to aproved plans
BLD-Framing/Rough-in5/2/20085/5/20085/5/2008APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 5/2/2008 at 1:24:56 PM. Contact: ###-####. ok to cover roof
BLD-Other4/15/20084/16/20084/16/2008APART
DetailsJim Storey
Wall bar or rebar-zane Phone #: ###-####first lift ok si.
BLD-Footing3/25/20083/27/20083/27/2008APART
DetailsMike Jordan
zane Note: rebar Phone #: ###-####. perimeter footing. Did note that special insp. is required, contractor informed me that Strata will be doing special insp. did note some clearance issues at bottom of footing. Noted to contractor to have Strata note repair on report and also to have soils insp. reports on site.
(F) Reprint permit  3/20/2008  
Issue PAID IN FULL permit  3/13/2008 DONE
Routing - PLAN CHECK3/6/2008 3/7/2008 PASS
DetailsTim L. Woodard
Approval based on alternate attached to plans. For restroom opening into food prep.
PLANS/APPL TAKEN TO FRONT DESK  3/7/2008 DONE
Case Summary (BLD)  3/7/2008 DONE
Print Occupancy Form  3/7/2008 DONE
Telephone call  3/7/2008 DONE
DetailsTisha Gallop
called Tim Foley (GC) and told him permit is ready, fees and need ACHD
Permit Ready to Issue  3/7/2008 DONE
DetailsTisha Gallop
Plan assigned to (TLW)11/30/2007 3/7/2008 PASS
DetailsTim L. Woodard
3/7/2008 13:36:34 TLW - activity updated through activity BLDA022 from case BLD07-03063.
Routing PW Drainage3/4/2008 3/6/2008 PASS
DetailsBrian Murphy
Routing - PUBLIC WORKS3/4/2008 3/6/2008 PASS
DetailsBeverly Hall
Routing - PLAN CHECK2/29/2008 3/4/2008 PEND
DetailsTim L. Woodard
Plans routed back to public works (Brian Murphy) for review
Plan resubmittals received  3/4/2008  
received five copies of e-mail, 2 pg. swale details, sheet C2.0; inserted into plans by arch. rep. and taken back to Tim Woodard
Routing PW Drainage2/22/2008 2/29/2008 FAIL
DetailsBrian Murphy
ENGINEER SAYA HE IS WAITING ON PERC TEST RESULTS. BRIAN MURPHY ###-####.
Routing - PLAN CHECK2/20/2008 2/22/2008 PEND
DetailsTim L. Woodard
Routed to Public works for review
Plan resubmittals received  2/22/2008  
Received four copies of e-mail, document regarding seepage rates, geotechnical report, and five copies of C1.0, C2.0; inserted into plans by LEG and taken back to Tim Woodard
Routing - PUBLIC WORKS GRADING2/15/2008 2/20/2008 FAIL
DetailsLouise Waldorf
Routing PW Drainage2/15/2008 2/20/2008 FAIL
DetailsBrian Murphy
GEOTECH REPORT INSUFFICENT.BRIAN MURPHY ###-####.
Routing - PLAN CHECK2/14/2008 2/15/2008 PEND
DetailsTim L. Woodard
Routed back to public works on Brian's request.
Routing - PUBLIC WORKS GRADING2/11/2008 2/14/2008 FAIL
DetailsLouise Waldorf
Routing PW Drainage2/11/2008 2/14/2008 FAIL
DetailsBrian Murphy
SYSTEM DEPTH, GROUNDWATER SEASONAL HIGH,POLLUTION PREVENTION BMPS IN O&M. BRIAN MURPHY ###-####
Routing - PLAN CHECK2/8/2008 2/11/2008 PEND
DetailsTim L. Woodard
Routed to Public works (Brian Murphy)
Routing - PLANNING2/6/2008 2/8/2008 PASS
DetailsMatthew A Halitsky
Routed to Plan Check (Tim).
Plan resubmittals received  2/4/2008 DONE
received 1 transmittal, 1 response,O & M correction comments,3 O & M PLAN,4 copies of sheets C1.0,C2.0, and 3 copies of sheets A7.1,A2.1,A5.1,A6.1 inserted by Tim Foley of FMG plans taken back to Tim W.
Routing - PLANNING1/29/2008 1/30/2008 FAIL
DetailsMatthew A Halitsky
Conditions of DR approval still not met. Re-faxed memo of 12-24-2007.

Routed to Plan Review (Tim).
Routing PW Sewer Rating1/29/2008 1/29/2008 PASS
DetailsLouise Waldorf
Routing PW Drainage1/22/2008 1/29/2008 FAIL
DetailsBrian Murphy
ASTM SAND C-33 SIX INCHES, SIC CIODE, OFFSITE DRAINAGE. BRIAN MURPHY ###-####.
Routing - PUBLIC WORKS1/17/2008 1/29/2008 FAIL
DetailsLouise Waldorf
Routing PW Sewer Design1/17/2008 1/22/2008 PASS
DetailsJim Pardy
Routing - PLAN CHECK1/10/2008 1/17/2008 PEND
DetailsTim L. Woodard
routed to public works by Request from LW
1st review completed  1/10/2008 FAIL
Failed P.W., Planning, Plan Check
Routing - FIRE1/9/2008 1/10/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
Routing - PLAN CHECK12/24/2007 1/9/2008 FAIL
DetailsTim L. Woodard
Tim Woodard/ sent plan review report to architect
Routing Off Site - STRUCTURAL12/3/2007 1/9/2008 PASS
DetailsTim L. Woodard
Recieved corrections sent them to arch
Plan Reviewer's activity  1/7/2008 DONE
Sent Architect Engineering comments.
Routing - PLANNING  12/24/2007 FAIL
DRH07-00513 Matt H.

Conditions of DR approval not met. Faxed letter to architect 12-24-2007.
Routing - PLUMBING12/13/2007 12/18/2007 PASS
per plans and 2003 upc satisfy public works request
Routing - Erosion and Sediment12/10/2007 12/13/2007 PASS
ESC plan approved with attached conditions.
Routing PW Environmental12/11/2007 12/13/2007 PASS
DetailsWalt Baumgartner
Reviewed pasta process w/ owner. No pretreatment appears necessary. OK to go.
Routing PW Drainage12/10/2007 12/11/2007 FAIL
Depth of free draining material 1% grades.Brian Murphy ###-####
Routing PW Sewer Rating12/11/2007 12/11/2007 FAIL
Routing PW Solid Waste12/11/2007 12/11/2007 PASS
Plan to use 95-gallon carts stored inside.
Routing - PUBLIC WORKS12/3/2007 12/11/2007 FAIL
Routing PW Street Lights12/7/2007 12/7/2007 PASS
Telephone call  12/3/2007 DONE
Called Action Couriers for pick up
Routing - PLANNING Land Div12/3/2007 12/3/2007 PASS
VLL-tt
Plans ACCEPTED BY PLAN TECH  12/3/2007 DONE
Recd Pcfee & Taken To Pln CK  12/3/2007 DONE
Plan routing begun/NEW & ADDTN  12/3/2007 DONE
Pending Assignment by MYS11/28/2007 11/30/2007 DONE
11/30/2007 15:43:35 JCM - activity updated through activity BLDA185 from case BLD07-03063.
Application received  11/28/2007