Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD07-03143
StatusFinaled
Name LAYTON CONSTRUCTION
Site Address 1444 S ENTERTAINMENT AVE Unit: 300
Project NameANTHEM OFFICE BLDG
Customer Number 
ePlanReviewNo
Description
(LAYTON CONSTRUCTION - ANTHEM OFFICE BLDG - 3RD FLR) To finish a 2,070 square foot, tenant space on the third floor of a five story 77,000 square foot office shell and core building (BLD06-01621). Scope of work includes: Installation of new electrical, installation of a new mechanical system, [construction of non-bearing interior partition walls that create a 190 square foot conference room, two enclosed offices, Reception area, plan review area, open office space, copy room, and a break room,] and interior finishes in compliance with chapter eight of the 2003 IBC. All construction to be in compliance with the approved plans and attached comment list.**TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD6/6/20086/6/20086/6/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD4/23/20084/23/20086/6/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 3/10/20084/23/2008 DONE
Permanent Occupancy UNPAID FEE  3/10/2008 DONE
BLD-Final3/4/20083/5/20083/5/2008PPASS
DetailsMike Jordan
dwyane Phone #: ###-#### ok for perm occ.
FIRE-Final Inspection3/4/20083/5/20083/5/2008APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection3/3/20083/4/20083/4/2008PCANC
DetailsTroy Cobbley
Duane, early afternoon if possible, please; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
BLD-Final3/3/20083/4/20083/4/2008PCANC
DetailsMike Jordan
Duane, late afternoon if possible please; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
FIRE-Final Inspection3/3/20083/3/20083/3/2008PFAIL
DetailsTroy Cobbley
Two exit lights are missing as shown on the city approved plans
BLD-Framing/Rough-in2/22/20082/25/20082/25/2008APASS
DetailsMike Jordan
duane - ceiling for cover Phone #: ###-####. ceiling grid is ok.
BLD-Framing/Rough-in2/21/20082/22/20082/22/2008PFAIL
DetailsMike Jordan
duane - ceiling grid Phone #: ###-####. Needss to finish installing clips and remove screws from clips.
BLD-Framing/Rough-in1/31/20081/31/20081/31/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 1/31/2008 at 7:05:45 AM. Contact: ###-####. Interior steel stud framed walls ok.
Routing - PLAN CHECK1/22/2008 1/25/2008 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  1/25/2008 DONE
Print Occupancy Form  1/25/2008 DONE
Telephone call  1/25/2008 DONE
Called Duane permit ready and fee given
CHANGE STATUS TO (RDY)  1/25/2008 DONE
Issue PAID IN FULL permit  1/25/2008 DONE
Plan assigned to (TLW)12/12/2007 1/25/2008 DONE
DetailsTim L. Woodard
Routing - FIRE1/16/2008 1/22/2008 PASS
DetailsScott Arellano
Attached review comments to plans.
1st review completed  1/22/2008 FAIL
Plan resubmittals received  1/18/2008 DONE
received 1 comments and 2 copies of sheets A3.0,E1.0 taken to Tim W.
Routing - PLAN CHECK12/13/2007 1/16/2008 FAIL
DetailsTim L. Woodard
Plan corrections sent to architect. Dana@insightarchitects.com
Routing - PUBLIC WORKS12/12/2007 12/13/2007 PASS
Pending Assignment by MYS12/11/2007 12/12/2007 DONE
12/12/2007 14:27:49 MYS - activity updated through activity BLDA185 from case BLD07-03143.
Plans ACCEPTED BY PLAN TECH  12/11/2007  
Recd Pcfee & Taken To Pln CK  12/11/2007  
Application received  12/11/2007