Third Notice BLD | 6/6/2008 | 6/6/2008 | 6/6/2008 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 4/23/2008 | 4/23/2008 | 6/6/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 3/10/2008 | 4/23/2008 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 3/10/2008 | | DONE |
|
|
|
|
BLD-Final | 3/4/2008 | 3/5/2008 | 3/5/2008 | P | PASS |
Mike Jordan
|
|
|
dwyane Phone #: ###-#### ok for perm occ.
|
FIRE-Final Inspection | 3/4/2008 | 3/5/2008 | 3/5/2008 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 3/3/2008 | 3/4/2008 | 3/4/2008 | P | CANC |
Troy Cobbley
|
|
|
Duane, early afternoon if possible, please; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Final | 3/3/2008 | 3/4/2008 | 3/4/2008 | P | CANC |
Mike Jordan
|
|
|
Duane, late afternoon if possible please; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
FIRE-Final Inspection | 3/3/2008 | 3/3/2008 | 3/3/2008 | P | FAIL |
Troy Cobbley
|
|
|
Two exit lights are missing as shown on the city approved plans
|
BLD-Framing/Rough-in | 2/22/2008 | 2/25/2008 | 2/25/2008 | A | PASS |
Mike Jordan
|
|
|
duane - ceiling for cover Phone #: ###-####. ceiling grid is ok.
|
BLD-Framing/Rough-in | 2/21/2008 | 2/22/2008 | 2/22/2008 | P | FAIL |
Mike Jordan
|
|
|
duane - ceiling grid Phone #: ###-####. Needss to finish installing clips and remove screws from clips.
|
BLD-Framing/Rough-in | 1/31/2008 | 1/31/2008 | 1/31/2008 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/31/2008 at 7:05:45 AM. Contact: ###-####. Interior steel stud framed walls ok.
|
Routing - PLAN CHECK | 1/22/2008 | | 1/25/2008 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/25/2008 | | DONE |
|
|
|
|
Telephone call | | | 1/25/2008 | | DONE |
|
|
|
Called Duane permit ready and fee given
|
CHANGE STATUS TO (RDY) | | | 1/25/2008 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/25/2008 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 12/12/2007 | | 1/25/2008 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 1/16/2008 | | 1/22/2008 | | PASS |
Scott Arellano
|
|
|
Attached review comments to plans.
|
1st review completed | | | 1/22/2008 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 1/18/2008 | | DONE |
|
|
|
received 1 comments and 2 copies of sheets A3.0,E1.0 taken to Tim W.
|
Routing - PLAN CHECK | 12/13/2007 | | 1/16/2008 | | FAIL |
Tim L. Woodard
|
|
|
Plan corrections sent to architect. Dana@insightarchitects.com
|
Routing - PUBLIC WORKS | 12/12/2007 | | 12/13/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 12/11/2007 | | 12/12/2007 | | DONE |
|
|
|
12/12/2007 14:27:49 MYS - activity updated through activity BLDA185 from case BLD07-03143.
|
Plans ACCEPTED BY PLAN TECH | | | 12/11/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/11/2007 | | |
|
|
|
|
Application received | | | 12/11/2007 | | |
|
|
|
|