Third Notice | | 7/24/2009 | 8/17/2009 | | DONE |
|
|
|
|
Second Notice BLD | 3/4/2009 | 3/4/2009 | 7/24/2009 | | DONE |
Darla L Downs
|
|
|
First Notice has not been responded to.
|
First Notice | 2/13/2009 | 2/13/2009 | 3/4/2009 | | DONE |
Tom Arcoraci
|
|
|
|
BLD-Final | 2/12/2009 | 2/13/2009 | 2/13/2009 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/12/2009 at 3:39:28 PM. Contact: ###-####.
|
DOC - Permit Finaled | 2/13/2009 | 2/13/2009 | 2/13/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
Zoning Approval | 2/3/2009 | 2/3/2009 | 2/6/2009 | | DONE |
Andrea Tuning
|
|
|
The applicant submitted a zoning certificate to allow for the 2 doors to be located in the north elevation. The applicant also submitted a revised north elevation to be inserted into the building plans. 2/9/09 ANT
|
FIRE-Final Inspection | 1/28/2009 | 1/29/2009 | 1/29/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 1/27/2009 | 1/28/2009 | 1/28/2009 | A | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 1/27/2009 at 3:55:33 PM. Contact: ###-####.
|
BLD-Aging Inspection | 1/27/2009 | 1/27/2009 | 1/27/2009 | | CANC |
Tom Arcoraci
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/27/2009 | | DONE |
|
|
|
doc expire by mistake put back to issue per Tom A. ///dld
|
BLD-Aging Inspection | 11/21/2008 | 11/21/2008 | 11/21/2008 | | NR |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 2/29/2008 | 2/29/2008 | 2/29/2008 | P | PASS |
Tom Arcoraci
|
|
|
steve Phone #: ###-####
|
BLD-Other | 2/20/2008 | 2/20/2008 | 2/20/2008 | P | PASS |
Jim Sly
|
|
|
steve Note: shear nail wall & roof Phone #: ###-#### Roof, walls, and hold downs OK
|
BLD-Footing | 2/6/2008 | 2/6/2008 | 2/6/2008 | P | PASS |
Tom Arcoraci
|
|
|
steve Phone #: ###-####
|
BLD-Footing | 2/4/2008 | 2/5/2008 | 2/5/2008 | A | PASS |
Tom Arcoraci
|
|
|
steve - late a.m. please Phone #: ###-####
|
(F) Reprint permit | | | 1/23/2008 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/17/2008 | | DONE |
|
|
|
|
Telephone call | | | 1/15/2008 | | DONE |
|
|
|
left vm for wes steele at ###-#### - permit ready and fees given - also need ACHD receipt
|
Permit Ready to Issue | | | 1/15/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/8/2008 | | 1/14/2008 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/14/2008 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/14/2008 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 12/14/2007 | | 1/14/2008 | | PASS |
John Menard
|
|
|
1/14/2008 08:57:32 JCM - activity updated through activity BLDA022 from case BLD07-03167.
|
Routing - FIRE | 1/3/2008 | | 1/8/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 1/8/2008 | | FAIL |
|
|
|
Failed Plumbing
|
Routing - PLAN CHECK | 12/28/2007 | | 1/3/2008 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 1/3/2008 | | PASS |
|
|
|
Reviewed and approved structural and nonstructural items. JCM
|
Routing - PLAN CHECK | 12/27/2007 | | 12/28/2007 | | |
John Menard
|
|
|
Routed to plumbing.
|
Routing - PLUMBING | 12/28/2007 | | 12/28/2007 | | PASS |
Gerry Varner
|
|
|
per plans and 2003 upc
|
Routing - PLANNING | 12/27/2007 | | 12/27/2007 | | PASS |
Andrea Tuning
|
|
|
Approved per DRH06-00487
|
Routing - PLUMBING | 12/21/2007 | | 12/26/2007 | | FAIL |
Gerry Varner
|
|
|
no plm value.....Provide site plan showing sanitary sewer size and location to building.
|
Routing - Erosion and Sediment | 12/20/2007 | | 12/21/2007 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 12/14/2007 | | 12/20/2007 | | PASS |
|
|
|
|
Routing PW Solid Waste | 12/19/2007 | | 12/20/2007 | | PASS |
|
|
|
Development is already built (curbs, gutters, trash enclosures, buildings), only a single shell building to be added.
|
Routing PW Drainage | 12/17/2007 | | 12/19/2007 | | PASS |
|
|
|
OKED PREVIOUS SUB BRIAN MURPHY ###-####
|
Routing PW Sewer Rating | 12/19/2007 | | 12/19/2007 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 12/14/2007 | | 12/14/2007 | | PASS |
Dave Abo
|
|
|
|
Routing - Addressing | 12/14/2007 | | 12/14/2007 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/14/2007 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 12/14/2007 | | |
|
|
|
|
Application received | | | 12/13/2007 | | |
|
|
|
|