Permit Information
Permit NumberBLD07-03193
StatusFinaled
Name CARRIAGE CROSSING SHOPPING CENTER L
Site Address 2329 S APPLE ST
Project NameCARRIAGE CROSSING
Customer Number 
ePlanReviewNo
Description
Carriage Crossing Retail (Shell Only) - To construct a new 10,120 square foot, one story, wood framed retail shell building and related site improvements. This is a shell permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. No A-2 occupancies will be allowed in this building unless within a fire area of less than 5,000 square feet and an occupant load of less than 100, separated by a minimum two-hour fire barrier or the building is fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  11/12/2008  
BLD-Final6/6/20086/6/20086/10/2008PCANC
DetailsJim Storey
Kil Phone #: ###-####
Letter of compliance  6/10/2008 DONE
DetailsCathy Weisshaupt
Letter of Compliance issued 5-10-08
BLD-Final6/9/20086/9/20086/9/2008PPART
DetailsJim Storey
Keil Phone #: ###-#### final ok pending p&z sign off.
FIRE-Final Inspection6/9/20086/9/20086/9/2008PPASS
DetailsTroy Cobbley
fire life saftey passed
Code Occupancy Approval6/6/20086/6/20086/9/2008PPASS
DetailsCarol Montgomery
Temporary signed. Still need to provide arbs at the rear property line. 5' at planting - 1 every 15'. The arb's were determined not to be required by Matt Halisty and Sarah Schafer. Pass.
FIRE-Final Inspection6/6/20086/6/20086/6/2008PPART
DetailsForrest France
Still need site work complete at both entrances-paving is not finished-need to comply with fire department access requirements-see fire code review notes for specific details.
FIRE-Final Inspection5/30/20086/2/20086/2/2008PCANC
DetailsTroy Cobbley
Paving was not complete which affected the fire dept access. Inspection to be rescheduled for wednesday.
BLD-Framing/Rough-in5/30/20085/30/20085/30/2008PPASS
DetailsJim Storey
keil Phone #: ###-#### letter from engineer on file.
FIRE-Final Inspection5/30/20085/30/20085/30/2008PCANC
DetailsForrest France
keil - fire life safety Phone #: ###-#### Overbooked
BLD-Energy code compliance5/20/20085/20/20085/20/2008PPART
DetailsMike Jordan
keal Phone #: ###-####Still Need paperwork from engineer on hold down issues. Also need submital for flame spread on exposed facing for insul. Contractor noted that enginner has given a verbal ok on changes and is waiting for letter. Gave ok to cover exterior walls only. Items for restrooms not completed and still needs plumbing ri.
BLD-Framing/Rough-in5/16/20085/16/20085/16/2008PPART
DetailsJim Storey
keil Phone #: ###-#### ok to insulate/ pending letter from engineer of record as to justifacation of design to meet chapter 16 for lack of special insp for epoxy bolts replacment of simpson holddowns for wall bracing design. vapor barrior must meet smoke/flame spread where exposed.
BLD-Framing/Rough-in4/25/20084/28/20084/28/2008ANR
DetailsJim Storey
keil Phone #: ###-####
BLD-Framing/Rough-in4/17/20084/18/20084/18/2008ANR
DetailsJim Storey
keil Phone #: ###-#### need truss engineering.
BLD-Framing/Rough-in4/10/20084/11/20084/11/2008APART
DetailsJim Storey
Keil, shear nail; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt exteror nailling ok
BLD-Framing/Rough-in4/7/20084/7/20084/7/2008PPART
DetailsJim Storey
keil - partial Phone #: ###-#### colums in front post atchment ok to cover/ center colums grouted ok to cover. roof nailling ok for cover.
Extend Permit 180 days4/7/20084/7/20084/7/2008APASS
DetailsJim Storey
colums in front post atchment ok to cover/ center colums grouted ok to cover.
BLD-Framing/Rough-in4/2/20084/3/20084/3/2008APART
DetailsTom Arcoraci
kile Note: shear Phone #: ###-#### ok at columns only
BLD-Conference3/26/20083/27/20083/27/2008APASS
DetailsJim Storey
keil Phone #: ###-####
BLD-Conference3/11/20083/12/20083/12/2008APASS
DetailsJim Storey
keil Phone #: ###-####
BLD-Other3/6/20083/7/20083/7/2008APASS
DetailsJim Storey
KEIL NOTE: STEM WALL Phone #: ###-####
BLD-Footing3/3/20083/4/20083/4/2008APASS
DetailsJim Storey
kyle Phone #: ###-####
(F) Reprint permit  2/12/2008  
Issue PAID IN FULL permit  2/11/2008 DONE
Inspection Record Card- Bld  1/31/2008 DONE
Telephone call  1/31/2008 DONE
t/c w matt rhees at ###-#### x 5 - permit ready and fees given - also need gc name, rce#, rp name, and ACHD receipt
Permit Ready to Issue  1/31/2008 DONE
Plan assigned to (JCM)12/20/2007 1/30/2008 PASS
DetailsJohn Menard
1/30/2008 16:18:00 JCM - activity updated through activity BLDA022 from case BLD07-03193.
Routing - PLAN CHECK1/28/2008 1/30/2008 PASS
DetailsJohn Menard
Plan Reviewer's activity  1/30/2008 PASS
Reviewed and approved revised structural plans and additional calculations. JCM
PLANS/APPL TAKEN TO FRONT DESK  1/30/2008 DONE
Routing - PUBLIC WORKS1/28/2008 1/28/2008 PASS
DetailsBeverly Hall
Routing PW Sewer Design1/28/2008 1/28/2008 PASS
Details
Routing PW Environmental1/28/2008 1/28/2008 PASS
DetailsWalt Baumgartner
Segratated grease waste line noted on plans full length of shell to serve any TI space. Grease interceptor to be installed at a later date with any food service TI's as needed.
Routing - PLAN CHECK1/24/2008 1/28/2008  
DetailsJohn Menard
Plan resubmittals received  1/25/2008 DONE
received 1 project letter, 2 review calcs ,1 comments,3 calcs, 2 copies of sheets A3.0,A4.0,A4.1,E1.1,P1.0 and 3 copies of sheets S1.0,S2.0,S4.0,S5.0 inserted by Matt Rhees from The Architects Office plans taken back to John M.
Routing - FIRE1/24/2008 1/24/2008 PASS
DetailsScott Arellano
Attacehed updated fire review comments to plans.
Plan resubmittals received  1/23/2008 DONE
Matt Rhees dropped off site plan identifying addtional fire hydrant locations along Apple street. This submitted document will satisfy the Fire Code resubmittal request. Final approval will be subject to satisfactory field verification by the PDS/Fire inspector.
Plan Reviewer's activity  1/22/2008 PASS
Verified required attic access was on the plans. JCM
1st review completed  1/18/2008 FAIL
Routing - FIRE1/17/2007 1/18/2008 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Plan resubmittals requested  1/17/2008 DONE
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PLAN CHECK1/14/2008 1/17/2008 FAIL
DetailsJohn Menard
Routing - PLANNING  1/11/2008 PASS
drh07-00389- matthew halitsky
Plan resubmittals requested  1/9/2008 DONE
Faxed the achitect a copy of the structural review requesting revisions. JCM
Routing Off Site - STRUCTURAL12/19/2007 1/8/2008 FAIL
DetailsJohn Menard
Received comment list from consulting structural engineer requesting revisions. JCM
Routing - PLUMBING1/4/2008 1/7/2008 PASS
DetailsDaryl Spivey
per plans and 2003 upc
Routing - Erosion and Sediment1/4/2008 1/4/2008 PASS
Details
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS12/20/2007 1/4/2008 FAIL
DetailsConnie Baumgartner
Routing PW Environmental1/2/2008 1/2/2008 FAIL
DetailsWalt Baumgartner
Shell DR was conditioned in 8/2007 to include seperate grease waste line to accomodate food service tenants. Current plans do not show grease line on plumbing sheet
Routing PW Sewer Rating12/28/2007 12/31/2007 PASS
Routing PW Street Lights12/28/2007 12/28/2007 PASS
Routing PW Solid Waste12/28/2007 12/28/2007 PASS
Routing PW Drainage12/21/2007 12/28/2007 PASS
Plan routing begun/NEW & ADDTN  12/20/2007  
Routing - PLANNING Land Div12/20/2007 12/20/2007 PASS
Surrey Crossing sub
vf-tt
Plans ACCEPTED BY PLAN TECH  12/20/2007  
Pending Assignment by MYS12/17/2007 12/20/2007 DONE
12/20/2007 09:14:47 JCM - activity updated through activity BLDA166 from case BLD07-03193.
Application received  12/17/2007  
Recd Pcfee & Taken To Pln CK  12/17/2007  
Routing PW Sewer Design12/28/2007 1/4/2007 FAIL
DetailsJim Pardy
Sanitary sewer service easement required.

Contacted Lance Warnick of Treasure Valley Engineers and requested easment on 1/4/07.

Please contact Jim Pardy with any questions ###-####.
PubWorks Occupancy Approval6/6/20086/6/2008  DONE
Signed final occupancy D. Erskine.
Routing - PLAN CHECK     
John Menard
Routing - PLAN CHECK1/18/2008