BLD-Final | 4/24/2008 | 4/25/2008 | 4/25/2008 | A | PASS |
Mike Jordan
|
|
|
brandon Phone #: ###-####
|
DOC - Permit Finaled | 4/25/2008 | 4/25/2008 | 4/25/2008 | P | PASS |
Mike Jordan
|
|
|
Cert of occ. issued. All issues resolved.
|
BLD-Final | 4/23/2008 | 4/24/2008 | 4/24/2008 | A | FAIL |
Mike Jordan
|
|
|
brandon Phone #: ###-####. Provide address numbers on house. Complete fine grading. Provide and post insulation cert. Complete firecaulking on penetrations in garage. c/n posted.
|
BLD-Energy code compliance | 2/15/2008 | 2/15/2008 | 2/15/2008 | P | PASS |
Mike Jordan
|
|
|
brandon Phone #: ###-####
|
BLD-Energy code compliance | 2/13/2008 | 2/14/2008 | 2/14/2008 | P | NR |
Mike Jordan
|
|
|
brandon Phone #: ###-####
|
BLD-Framing/Rough-in | 2/12/2008 | 2/13/2008 | 2/13/2008 | P | PASS |
Mike Jordan
|
|
|
brandon Phone #: ###-####. All framing issues have been corrected. Will check glazing at stairway on final insp.
|
BLD-Framing/Rough-in | 2/11/2008 | 2/12/2008 | 2/12/2008 | A | FAIL |
Mike Jordan
|
|
|
Brandon Phone #: ###-####. Strap all top and bottom plates at gas pipe penetrations and at plumbing pentration at future warter softner. Provide header at doorway bonus room at T22 truss bearing. Tempered glazing required at window at landing. Provide fireblocking on furout 2x4 wall above 2x6 wall at ceiling level. (southwall). Provide additional bracing on gable truss on southwest wall by main entry. ok to insul. after mech. ri insp has passed. c/n posted on site.
|
BLD-Framing/Rough-in | 2/8/2008 | 2/11/2008 | 2/11/2008 | P | CANC |
Mike Jordan
|
|
|
Brandon Phone #: ###-####
|
BLD-Footing | 1/14/2008 | 1/14/2008 | 1/14/2008 | P | PART |
Mike Jordan
|
|
|
eliza - Note: pour concrete noon Phone #: ###-####. Approved plans on site. set backs ok. wip on stemwall.
|
BLD-Footing | 1/11/2008 | 1/11/2008 | 1/11/2008 | P | PART |
Mike Jordan
|
|
|
brandon Phone #: ###-####. no approved plans on site. inspected footings as per supplied plans. Noted to contractor that he procceds at his own risk. Will need approved plans on stemwall. If any changes are noted, contractor will repair.
|
Telephone call | | | 1/11/2008 | | DONE |
|
|
|
t/c w brandon read at ###-#### - permit ready and fees given - also need rp
|
Permit Ready to Issue | | | 1/11/2008 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/11/2008 | | DONE |
|
|
|
|
Pending Assignment by SRZ | 12/17/2007 | | 1/10/2008 | | DONE |
Ben S. Pavelka
|
|
|
|
Routing - PLAN CHECK | 12/19/2007 | | 1/10/2008 | | PASS |
Ben S. Pavelka
|
|
|
|
Case Summary (BLD) | | | 1/10/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/10/2008 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/10/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/27/2007 | | |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 12/26/2007 | | DONE |
Ben S. Pavelka
|
|
|
Plan review complete, ready to issue permit pending the approval of Scott Brown with Code Enforcement. Currently a stop work order on the parcel. (BSP) Parcel tag has been lifted 1-10-08, taking plans to front desk. (BSP)
|
Plan Reviewer's activity | | | 12/26/2007 | | DONE |
|
|
|
Verified note in Pulic Works document "Structure out of floodplain as per LOMR of Oct. 10, 2006 case no 06-10-B542A JW 12-19-07" with Beverly Hall in Public Works Department.
|
Routing - PUBLIC WORKS | 12/18/2007 | | 12/19/2007 | | PASS |
|
|
|
|
Routing - Addressing | 12/17/2007 | | 12/18/2007 | | PASS |
|
|
|
|
Routing - PLANNING | 12/18/2007 | | 12/18/2007 | | PASS |
|
|
|
|
Application received | | | 12/17/2007 | | |
|
|
|
|