Permit Information
Permit NumberBLD07-03222
StatusFinaled
Name UNLIMITED DESIGNS
Site Address 2200 W BOISE AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
LDS Church Steeple Retrofit - Scope of work to include: Adding bracing required by engineer under new steeple location, Installation of new aluminum steeple, and demolishion of existing ground spire. Approval per engineering and approved plans. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD6/6/20086/6/20087/28/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD4/23/20084/23/20086/6/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice2/29/20082/29/20084/23/2008 DONE
DetailsJim Storey
BLD-Final2/28/20082/29/20082/29/2008APASS
DetailsJim Storey
Dustin; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
DOC - Permit Finaled2/29/20082/29/20082/29/2008PPASS
DetailsJim Storey
DOC - Permit Finaled  2/29/2008 DONE
Steeple work completed per BLD07-03222
Code Occupancy Approval  2/29/2008 DONE
Issue PAID IN FULL permit  1/25/2008  
Routing - PLAN CHECK1/15/2008 1/17/2008 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  1/17/2008 DONE
Case Summary (BLD)  1/17/2008 DONE
Inspection Record Card- Bld  1/17/2008 DONE
Telephone call  1/17/2008 DONE
left vm for john at ###-#### - permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  1/17/2008 DONE
Plan assigned to (TLW)12/21/2007 1/17/2008 PASS
DetailsTim L. Woodard
1/17/2008 14:01:04 TLW - activity updated through activity BLDA022 from case BLD07-03222.
Routing Off Site - STRUCTURAL12/21/2007 1/17/2008 PASS
DetailsTim L. Woodard
Called Action Couriers for pick up. Recieved corrections sent to architect. Resubmittals recieved
Routing - FIRE1/14/2007 1/15/2008 PASS
DetailsKenneth R Roule
No fire review comments attached.
1st review completed  1/15/2008 FAIL
Routing - PLAN CHECK1/3/2008 1/14/2008 PASS
DetailsTim L. Woodard
Tim W.
Plan resubmittals received  1/14/2008  
received response letter, two copies of structural calculations and page S-4; taken to Tim Woodard
Routing - PLANNING12/26/2007 1/3/2008 PASS
Diane P.
Routing - PUBLIC WORKS  12/26/2007 PASS
Routing PW Sewer Rating12/24/2007 12/24/2007 PASS
Plans ACCEPTED BY PLAN TECH  12/21/2007  
Plan routing begun/NEW & ADDTN  12/21/2007  
Routing - PLANNING Land Div12/21/2007 12/21/2007 PASS
Application received  12/19/2007