Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD07-03236
StatusVoid/No Violation
Name JUSTIN TOUCHSTONE (ARCH REP)
Site Address 398 S 9TH ST Unit: 270
Project NameBODO BLDG #4
Customer Number 
ePlanReviewNo
Description
(KOWALIS & MACKEY - BODO BLDG #4 - STE 270) This building is fully sprinklered for allowable area increase. To build out a SHELL & core area of 1,529 sq. ft. on the second floor for office use. Work include interior non-combustible wall framing, finishes, millwork, electrical, mechanical, sprinkler and alarm systems installation and a suspended ceiling grid system, all per approved plans, notes and attachments of all reviewing agencies. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Plan Reviewer's activity  3/31/2008 DONE
DetailsScott Arellano
Permit voided. The scope of work is now part of BLD07-03135.
BLD-Wall cover3/21/20083/21/20083/21/2008PCANC
DetailsDave Hannah
Zack, ceiling inspection please; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok to cover
BLD-Framing/Rough-in1/31/20082/1/20082/1/2008APASS
DetailsDave Hannah
zack Phone #: ###-#### ok to cover walls
Print Occupancy Form  1/28/2008 DONE
Telephone call  1/28/2008 DONE
t/c w justin touchstone at ###-#### - permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  1/28/2008 DONE
Issue PAID IN FULL permit  1/28/2008 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/25/2008 PASS
Routing - PLAN CHECK1/14/2008 1/25/2008 PASS
DetailsDan Stuart
Resubmittals of 1/22/08 inserted into plans. Plans red-lined for clarifications and plan review conditions modified for code clarifications. Routing plans to permit desk to issue permit.
Plan assigned to (DRS)12/21/2007 1/25/2008 PASS
DetailsDan Stuart
1/25/2008 18:59:21 DRS - activity updated through activity BLDA022 from case BLD07-03236.
Plan resubmittals received  1/22/2008  
received response letter, revised cert of value, letter from engineer, and two copies of pages T0.1, T1.1, A2.1, A3.1, A3.2, A4.1, MG1.1, MG2.1, M1.1, M2.1, M3.1, E0.0, E1.0, E2.1, E2.2, E2.3, E2.4; taken to Dan Stuart
Routing - FIRE1/9/2008 1/14/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  1/14/2008 FAIL
Failed Plan Check
Plan resubmittals requested  1/9/2008 DONE
E-mailed copy of plan review items needing resubmittals to architect.
Routing - PLAN CHECK12/21/2007 1/9/2008 FAIL
DetailsDan Stuart
Resubmittals required. Plan review report e-mailed to architect. Plans to fire code analyst for his review.
Routing - PUBLIC WORKS12/21/2007 12/21/2007 PASS
Pending Assignment by MYS12/20/2007 12/21/2007 DONE
12/21/2007 10:17:32 MYS - activity updated through activity BLDA168 from case BLD07-03236.
Application received  12/20/2007  
Plans ACCEPTED BY PLAN TECH  12/20/2007  
Recd Pcfee & Taken To Pln CK  12/20/2007  
VOIDED CHANGE STATUS     
This permit is to be incorporated into permit Bld07-03135, see Plan Modification submitted at Bld07-03135 on 3/21/08 //LEG