Second Notice BLD | 9/22/2008 | 9/22/2008 | 9/26/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
Second Notice BLD | 9/22/2008 | 9/22/2008 | 9/26/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 8/26/2008 | 9/22/2008 | | DONE |
|
|
|
|
First Notice | | 8/8/2008 | 9/22/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 8/26/2008 | | DONE |
|
|
|
|
BLD-Final | 8/21/2008 | 8/22/2008 | 8/22/2008 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 8/18/2008 | 8/19/2008 | 8/19/2008 | P | PASS |
Forrest France
|
|
|
Jim- fire life safety Phone #: ###-####
|
FIRE-Final Inspection | 8/11/2008 | 8/12/2008 | 8/12/2008 | A | NR |
Forrest France
|
|
|
Project is not in condition for final fire life safety at this time.
|
BLD-Final | 8/11/2008 | 8/12/2008 | 8/12/2008 | P | CANC |
Tom Arcoraci
|
|
|
Jim Phone #: ###-####
|
Reopen Permit (ISS) | | | 8/11/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
per Rita, ok to reopen
|
Code Occupancy Approval | | | 8/8/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/23/2008 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 5/21/2008 | 5/22/2008 | 5/22/2008 | A | PASS |
Tom Arcoraci
|
|
|
jim Phone #: ###-#### do not cover sprinklered unit until inspection
|
BLD-Framing/Rough-in | 5/19/2008 | 5/20/2008 | 5/20/2008 | P | PASS |
Tom Arcoraci
|
|
|
jim Phone #: ###-####
|
BLD-Framing/Rough-in | 5/13/2008 | 5/14/2008 | 5/14/2008 | A | PART |
Tom Arcoraci
|
|
|
jim Note: sheet rock Phone #: ###-#### eve protection installed
|
Case Summary (BLD) | | | 5/12/2008 | | DONE |
|
|
|
|
BLD-Other | 3/28/2008 | 3/31/2008 | 3/31/2008 | A | PASS |
Tom Arcoraci
|
|
|
jim NOte: nailing fire aSSEMLY WALLS Phone #: ###-####
|
BLD-Framing/Rough-in | 3/21/2008 | 3/21/2008 | 3/21/2008 | P | PASS |
Tom Arcoraci
|
|
|
Jim, nailing on a fire wall; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Foundation | 3/5/2008 | 3/6/2008 | 3/6/2008 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/5/2008 at 7:25:07 AM. Contact: ###-####.
|
BLD-Footing | 3/5/2008 | 3/5/2008 | 3/5/2008 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/5/2008 at 7:24:36 AM. Contact: ###-####.
|
BLD-Footing | 2/28/2008 | 2/29/2008 | 2/29/2008 | P | PASS |
Tom Arcoraci
|
|
|
Matt ###-####
|
Issue PAID IN FULL permit | | | 2/28/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/27/2008 | | DONE |
|
|
|
|
Telephone call | | | 2/27/2008 | | DONE |
|
|
|
t/c w james larkin at ###-#### - permit ready and fees given - also faxed copy of fees to james at ###-####
|
Permit Ready to Issue | | | 2/27/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/12/2008 | | 2/26/2008 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 2/26/2008 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 1/2/2008 | | 2/26/2008 | | PASS |
Sam Zahorka
|
|
|
2/26/2008 11:32:56 SRZ - activity updated through activity BLDA022 from case BLD07-03283.
|
Plan resubmittals received | | | 2/22/2008 | | |
|
|
|
plans resubmittal received A3.1, A4.1, A5.1, & E1-- plans taken to Sam Zahorka
|
Routing - PLUMBING | 2/7/2008 | | 2/12/2008 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing - FIRE | 2/11/2008 | | 2/11/2008 | | PASS |
Scott Arellano
|
|
|
Revised Comments. Attached updated IFC comments to plans
|
Routing - PLAN CHECK | 2/6/2008 | | 2/7/2008 | | PEND |
Sam Zahorka
|
|
|
Pending Plan corrections. (SRZ) ###-####
|
1st review completed | | | 2/6/2008 | | FAIL |
|
|
|
Failed Plumbing, Plan Check, Fire
|
Routing - FIRE | 2/5/2008 | | 2/6/2008 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
Routing - PLAN CHECK | 1/16/2008 | | 2/5/2008 | | FAIL |
Sam Zahorka
|
|
|
Plan corrections needed. Correction letter sent to Applicant. Routed to other departments for review. (SRZ) ###-####
|
1st review completed | | | 2/5/2008 | | FAIL |
|
|
|
Plan corrections needed. Correction letter sent to Applicant. Routed to other departments for review. (SRZ) ###-####
|
Case Summary (BLD) | | | 2/5/2008 | | |
|
|
|
|
Plan resubmittals received | | | 1/17/2008 | | |
|
|
|
received "2" sheets each of C-4 & PME7.1-- plans taken to Sam Zahorka
|
Routing - PLANNING | 1/11/2008 | | 1/16/2008 | | PASS |
Diane C Perkins
|
|
|
Approved per DRH07-00517 and passed on to Diane P for review of the CUP. Andrea T
approved the cup - dcp
|
Routing - PLUMBING | 1/11/2008 | | 1/11/2008 | | FAIL |
Bill VanDegrift
|
|
|
provide plumbing plans and size water service.
|
Routing - Erosion and Sediment | 1/11/2008 | | 1/11/2008 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 1/7/2008 | | 1/11/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Solid Waste | 1/10/2008 | | 1/11/2008 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Street Lights | | | 1/10/2008 | | PASS |
|
|
|
|
Routing PW Sewer Rating | | | 1/10/2008 | | PASS |
|
|
|
|
Routing PW Drainage | 1/8/2008 | | 1/9/2008 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING Land Div | 1/4/2008 | | 1/7/2008 | | PASS |
Todd Tucker
|
|
|
Property has a pending condominium plat. As such, individual units may not be sold until the condominium plat has been recorded with the county.
|
Plans ACCEPTED BY PLAN TECH | | | 1/4/2008 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 1/4/2008 | | |
|
|
|
|
Application received | | | 12/28/2007 | | |
|
|
|
|